U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #19
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #19
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 7/7/2017
Reporting Period: 6/24/2017 - 7/7/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Riverbank re-construction was completed in BRSA 3. Excavation of contaminated riverbank soils and in-stream sediments continues in BRSA 4 along with riverbank restoration. The staging pad is under construction in BRSA 6.

2.1.2 Response Actions During Reporting Period

BRSA 3
- Transport/disposal of approximately 70 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4);
- Completed river bank re-construction;
- Removed of stabilization pad; and
- Demobilized equipment & construction materials.

BRSA 4
- Excavation of contaminated soils continues with excavation completed in Grids 21-24. There are 50 total grids in BRSA 4, with each grid consisting of approximately 50 lineal feet of riverbank. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs;
- Excavation of contaminated in-stream sediments completed in one of two 'stream tubes' in BRSA 4, which is located within the river channel immediately adjacent to Grids 15-24. The target clean-up goal for in-stream sediments is 1 mg/kg total PCBs;

The final excavation depths and reported confirmation sampling results are found in the tables below for riverbank grids (Table 1) and in-stream sediments (Table 2):

BRSA 4

RIVERBANK

GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

21

36

ND

22

36

ND

23

36

0.077

24

36

0.07

Table 1. BRSA 4 Riverbank Grid Confirmatory Sampling Results


BRSA 4

STREAM TUBE GRID*

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

21

6

0.20

22

6

0.19

23

6

0.78

24

12

0.32

Table 2. BRSA 4 Stream Tube Confirmatory Sampling Results


Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 4, 5, 6 & 9. Both documents can be found in the ‘Documents' Section of the project website. Stream Tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both riverbank grids and stream tubes can be found on Figure 8 of the BRSA 4, 5, 6 & 9 TM.


- Transport/disposal of approximately 530 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).

BRSA 6
- Construction of staging area and stabilization pad;
- Mobilized supporting equipment into staging area; and
- Completed widening of roads to improve access to riverbanks.

OVERALL SITE
- Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity control measures and monitoring in Kalamazoo River around the BRSA 3 - 9 excavation area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs above upstream levels;
- Treatment of approximately 45,300 gallons of contact water from contaminated grids and contaminated soils staging pads in the on-site WWTPs located in BRSA 3 and BRSA 4 (see Section 2.1.4). Sampling results from both WWTPs continue to confirm non-detect levels for total PCBs in treated water;
- Mussel relocation activities were completed in BRSAs 7 & 8. Approximately 500 threatened mussels were inventoried, measured, tagged and moved to an adequate area upstream and outside the work area;
- Check up on mussel colony relocated last year, with a very low mortality rate observed (approximately 3%); and
- Monitoring of the temporary WCS.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid  50 lbs 780 lbs NA recycling Otsego Recycling Center
 Plastic solid  25 lbs 275 lbs NA recycling Otsego Recycling Center
 Steel solid  20 lbs 9240 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 600 tons (est) 12,184 tons (est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 45,300 gal           504,612 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 3
- Decommission and demobilize WWTP along with other equipment from staging area.

BRSA 4
- Continue excavation of contaminated riverbank soils and in-stream sediments;
- Restore excavated river bank and in-stream sediment areas;
- Treat contact water from contaminated grids and contaminated soils staging pad; and
- Transport contaminated soils and sediments for disposal.

BRSA 6
- Complete construction of staging area and stabilization pad; and
- Mobilize and construct WWTP; and
- Mobilize supporting equipment into staging area;

SITEWIDE
- Operate dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- The draft TM for BRSAs 7 & 8 continues under review, with comments due by July 24.

2.2.2 Issues
Productivity was impacted by the July 4th holiday as work was paused for several days.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day. The meeting is led by on-site safety officer(s) from Envirocon & AMEC-FW.

2.5.2 Liaison Officer


2.5.3 Information Officer
A flyer was distributed door to door announcing a community meeting planned for July 26 from 6:00pm to 8:00pm at the Otsego City Hall to update project neighbors on work progress and plans for the remainder of 2017.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
Michigan DNR - 1
Michigan DEQ - 1
Envirocon: 35
AMEC-FW: 2
Spicer Group: 1
Environmental Solutions & Innovation, Inc. - 5

TOTAL: 47

5. Definition of Terms
  AMEC-FW           AMEC Foster Wheeler
BRSA                  Bank Removal and Stabilization Area
FSP                     Field Sampling Plan
GC                      General Contractor     
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
MDOT                 Michigan Department of Transportation     
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
START               Superfund Technical Assessment & Response Team (US EPA contractor)
TM                      Technical Memorandum
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on July 21.

7. Situational Reference Materials
  No information available at this time.