U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #20
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #20
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 7/21/2017
Reporting Period: 7/8/2017 - 7/21/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Excavation of contaminated riverbank soils and in-stream sediments continues in BRSA 4 along with riverbank restoration. The staging area continues under construction in BRSA 6.

2.1.2 Response Actions During Reporting Period

BRSA 3
- Demobilization of the WWTP from staging area and relocation into BRSA 6 staging area.

BRSA 4
- Excavation of contaminated soils continues with excavation completed and confirmation results received in Grids 29-38. There are 50 total grids in BRSA 4, with each grid consisting of approximately 50 lineal feet of riverbank. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs;
- Began removal of sheet piling installed to facilitate excavation of stream tube adjacent to grids 15-24 (see photo); and
- Preparations for excavation of contaminated in-stream sediments are complete for the second 'stream tube' in BRSA 4, which is located within the river channel immediately adjacent to Grids 43-50. The target clean-up goal for in-stream sediments is 1 mg/kg total PCBs.

Estimated excavation depths and confirmation sampling results are found in the table below for riverbank grids (Table 1):

BRSA 4

RIVERBANK

GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

29

36

0.30

30

36

0.28

31

24

<0.069

32

24

0.61

33

24

<0.060

34

24

<0.067

35

24

0.0851

36

24

0.071

37

24

<0.069

38

12

0.16

Table 1. BRSA 4 Riverbank Grid Confirmatory Sampling Results

Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 4, 5, 6 & 9. Both documents can be found in the ‘Documents' Section of the project website. Stream Tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both riverbank grids and stream tubes can be found on Figure 8 of the BRSA 4, 5, 6 & 9 TM.


- Transport/disposal of approximately 1,629 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).

BRSA 6
- Continued construction of staging area and stabilization pad (see photos);
- Mobilization of WWTP into staging area; and
- Removed abutment at old bridge crossing.

OVERALL SITE
- Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity control measures and monitoring in Kalamazoo River around the BRSA 3 - 9 excavation area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs above upstream levels;
- Treatment of approximately 90,318 gallons of contact water from contaminated grids and contaminated soils staging pads in the on-site WWTP located in BRSA 4 (see Section 2.1.4). Sampling results from the WWTP continues to confirm non-detect levels for total PCBs in treated water; and
- Monitoring of the temporary WCS.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 20 lbs 800 lbs NA recycling Otsego Recycling Center
 Plastic solid 10 lbs 285 lbs NA recycling Otsego Recycling Center
 Steel solid 10 lbs 9250 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 1,629 tons (est) 13,813 tons (est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 90,318 gal           594,930 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 4
- Complete excavation of contaminated riverbank soils and in-stream sediments;
- Continue restoration of excavated river bank and in-stream sediment areas;
- Treat contact water from contaminated grids and contaminated soils staging pad; and
- Transport contaminated soils and sediments for disposal.

BRSA 6
- Complete construction of staging area;
- Complete construction of stabilization pad;
- Construct and test WWTP; and
- Commence excavation of contaminated riverbank soils and in-stream sediments.

SITEWIDE
- Operate dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- All comments on draft TM for BRSAs 7 & 8 have been received and are being consolidated into a single, consolidated response to AMEC-FW.

2.2.2 Issues
Heavy rains and flooding delayed progress during the reporting period.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day. The meeting is led by on-site safety officer(s) from Envirocon & AMEC-FW.

2.5.2 Liaison Officer


2.5.3 Information Officer

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
Michigan DNR - 1
Michigan DEQ - 1
Envirocon: 35
Milbocker & Sons, Inc.: 4
AMEC-FW: 2
Spicer Group: 1

TOTAL: 46

5. Definition of Terms
  AMEC-FW           AMEC Foster Wheeler
BRSA                  Bank Removal and Stabilization Area
FSP                     Field Sampling Plan
GC                      General Contractor     
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
MDOT                 Michigan Department of Transportation     
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
START               Superfund Technical Assessment & Response Team (US EPA contractor)
TM                      Technical Memorandum
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on August 4.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images