U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #34
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #34
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 2/2/2018
Reporting Period: 1/20/2018 - 2/2/2018

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Removal operations continue in BRSA 7 and BRSA 8. Removal of the temporary WCS continues.

2.1.2 Response Actions During Reporting Period

BRSA 6
- Staging area maintenance.

BRSA 7
- Excavation of contaminated soils and sediments continues with confirmation results received in riverbank and stream tube grids shown in Tables 1 & 2 below. There are 63 total river bank grids in BRSA 7, with each grid consisting of approximately 50 feet of riverbank. There are 3 stream tubes, with each varying in size. The target clean-up goal in riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs;
- Continued transportation and disposal of contaminated soils and sediments (utilizing the staging pad in BRSA 6); and
- Continued maintenance of stream tube protection measures to prevent erosion.

BRSA 7

RIVERBANK GRID

 

 

 

 

TOTAL ESTIMATED EXCAVATION DEPTH (in)

 

 

 

 

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

 

 

 

 

13

 

 

 

 

48

 

 

 

 

3.8

 

 

 

 

Table 1. BRSA 7 Riverbank Grid Confirmatory Sampling Results

 

 

 

 


BRSA 7

STREAM TUBE

 

 

 

 

TOTAL ESTIMATED EXCAVATION DEPTH (in)

 

 

 

 

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

 

 

 

 

09E-13

 

 

 

 

36

 

 

 

 

0.12

 

 

 

 

Table 2. BRSA 7 Stream Tube Confirmatory Sampling Results

 

 

 

 


General Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 7 & 8. Both documents can be found in the ‘Documents' Section of the project website. Stream tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 1-7 of the BRSA 7 & 8 TM.

BRSA 8

- Excavation of contaminated soils continues, with confirmation results received in riverbank and stream tube grids shown in Tables 3 & 4 below. There are 63 total river bank grids in BRSA 8, with each grid consisting of approximately 50 lineal feet of riverbank. There are 3 stream tubes, with each stream tube varying in size. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs; 
- Continued maintenance of stream tube protection measures to prevent erosion; and
- Continued transportation and disposal of contaminated soils and sediments (utilizing the staging pad in BRSA 9).

BRSA 8

RIVERBANK GRID

 

 

 

TOTAL ESTIMATED EXCAVATION DEPTH (in)

 

 

 

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

 

 

 

1

 

 

 

6

 

 

 

< 0.03

 

 

 

2

 

 

 

6

 

 

 

< 0.031

 

 

 

3

 

 

 

6

 

 

 

0.16

 

 

 

4

 

 

 

6

 

 

 

0.11

 

 

 

5

 

 

 

6

 

 

 

0.22

 

 

 

6

 

 

 

6

 

 

 

0.13

 

 

 

7

 

 

 

6

 

 

 

0.44

 

 

 

8

 

 

 

6

 

 

 

4.0

 

 

 

9

 

 

 

12

 

 

 

3.3

 

 

 

10

 

 

 

12

 

 

 

0.20

 

 

 

11

 

 

 

12

 

 

 

0.58

 

 

 

12

 

 

 

12

 

 

 

< 0.047

 

 

 

13

 

 

 

12

 

 

 

< 0.050

 

 

 

19

 

 

 

24

 

 

 

< 0.034

 

 

 

20

 

 

 

24

 

 

 

< 0.043

 

 

 

21

 

 

 

24

 

 

 

< 0.059

 

 

 

22

 

 

 

24

 

 

 

< 0.061

 

 

 

23

 

 

 

24

 

 

 

< 0.065

 

 

 

24

 

 

 

24

 

 

 

< 0.071

 

 

 

25

 

 

 

24

 

 

 

< 0.072

 

 

 

45

 

 

 

24

 

 

 

0.41

 

 

 

46

 

 

 

24

 

 

 

1.4

 

 

 

47

 

 

 

36

 

 

 

< 0.066

 

 

 

49

 

 

 

48

 

 

 

< 0.038

 

 

 

50

 

 

 

36

 

 

 

0.073

 

 

 

51

 

 

 

36

 

 

 

0.089

 

 

 

52

 

 

 

6

 

 

 

2.4

 

 

 

53

 

 

 

6

 

 

 

TBD

 

 

 

54

 

 

 

36

 

 

 

TBD

 

 

 

60

 

 

 

6

 

 

 

0.89

 

 

 

61

 

 

 

6

 

 

 

0.25

 

 

 

62

 

 

 

6

 

 

 

1.9

 

 

 

63

 

 

 

6

 

 

 

1.9

 

 

 

Table 3. BRSA 8 Riverbank Grid Confirmatory Sampling Results

 

 

 


BRSA 8

STREAM TUBE

 

 

 

TOTAL ESTIMATED EXCAVATION DEPTH (in)

 

 

 

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

 

 

 

07A-19

 

 

 

6

 

 

 

< 0.034

 

 

 

07A-20

 

 

 

6

 

 

 

< 0.043

 

 

 

07A-21

 

 

 

6

 

 

 

< 0.059

 

 

 

07A-22

 

 

 

6

 

 

 

< 0.061

 

 

 

Table 3. BRSA 8 Stream Tube Confirmatory Sampling Results

 

 

 


General Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 7 & 8. Both documents can be found in the ‘Documents' Section of the project website. Stream tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 1-8 of the BRSA 7 & 8 TM.


BRSA 9
- Staging area maintenance.

OVERALL SITE
- Transport/disposal of approximately 3,719 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4);
- Daily particulate monitoring (PM10) around the site perimeter (when feasible) with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity monitoring utilizing a hand held monitoring instrument with no sustained exceedances;
- Treatment of approximately 21,020 gallons of contact water from contaminated grids and contaminated soils staging pads in on-site WWTPs located in BRSAs 6 & 9 (see Section 2.1.4). Sampling results from both WWTPs continue to show non-detect levels for PCBs in the treated discharge; and
- Removal of the temporary WCS continues (see photo of sheet pile removal on north side).

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 20 lbs 1230 lbs NA recycling Otsego Recycling Center
 Plastic solid 10 lbs 545 lbs NA recycling Otsego Recycling Center
 Steel solid 20 lbs 27,560 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 3,719 tons (est) 39,875 tons(est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 21,020 gal           1,803,496 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 6
- Continue staging pad and WWTP operations to support removal operations in BRSA 7.

BRSA 7
- Continue access road construction along riverbanks;
- Continue excavation of contaminated riverbank soils and in-stream sediments;
- Treat contact water from contaminated grids, stream tubes and staging pad (located in BRSA 6); and
- Transport contaminated soils & sediments for disposal.

BRSA 8
- Continue excavation of contaminated riverbank soils and in-stream sediments;
- Treat contact water from contaminated grids, stream tubes and staging pad (located in BRSA 9); and
- Transport contaminated soils & sediments for disposal.

BRSA 9
- Continue staging pad and WWTP operations to support removal operations in BRSA 8.

SITEWIDE
- Operate dust and turbidity control/monitoring systems (as feasible & necessary); and
- Continue removal of the temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- A land use permit will be issued by MDNR for the restoration component of the proposed work plan once design plans are submitted, reviewed and approved.
- MDNR will be issuing a project advertisement requesting for demolition of the auxiliary spillway located adjacent to the temporary WCS the week of February 5.
- MDOT permits for warning signage posted on M-89 at 1) 106th Street, 2) 19th Street, and 3) at the Kalamazoo River bridge (BRSA 3 entrance) were amended to extend the expiration date. This warning signage is still necessary as slow trucks continue to enter the highway.

2.2.2 Issues
- Verification sampling is needed in BRSA 7 in the vicinity of riverbank grids 41-43 to confirm the presence of PCB contaminated soils with concentrations > 50 ppm, which were detected in a historical sample.The sampling will be conducted consistent with Section 2.7 of the draft FSP.
- Residents raised the concern of truck speeds on 19th Street, which provides access to the BRSA 6 staging area. All drivers were put on notice to respect the posted speed limit of 12 mph on 19th Street.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day by on-site safety officer(s) from Envirocon & AMEC-FW.

2.5.2 Liaison Officer

2.5.3 Information Officer
MDNR responded to an inquiry for a tour of the temporary WCS removal by a reporter from the Allegan News / Otsego Union Enterprise on February 1.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
MDNR - 1
MDEQ - 1
Envirocon - 35
Milbocker & Sons, Inc. - 4
Spicer Group, Inc. - 1
AMEC-FW - 2

TOTAL: 46

5. Definition of Terms
  AMEC-FW          AMEC Foster Wheeler     
BRSA                 Bank Removal and Stabilization Area
FSP                    Field Sampling Plan
MDNR                Michigan Department of Natural Resources     
NTU    Nephelometric Turbidity Unit
OSC                   On Scene Coordinator
PCB    Polychlorinated Biphenyl
PM    Particulate Matter
PolRep               Pollution Report
PRP                    Potentially Responsible Party
START                Superfund Technical Assessment & Response Team (US EPA contractor)
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on February 16.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images