U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Rolnick Property Site - Removal Polrep
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region I
|
Subject:
|
POLREP #10
Pollution Report #10 - Continuation of Operations
Rolnick Property Site
01EU
Brewer, ME
Latitude: 44.7903000 Longitude: -68.7700000
|
To:
|
|
From:
|
Dan Wainberg, On-Scene Coordinator
|
Date:
|
10/31/2009
|
Reporting Period:
|
10/18/09 to 10/31/09
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
01EU |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
8/18/2008 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
10/16/2008 |
|
Start Date: |
10/16/2008 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
MEN000105888 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
CERCLA Removal Action
1.1.2 Site Description
1.1.2.1 Location
The Site, which abuts the Penobscot River, is located in a mixed residential and commercial area and is approximately 0.5 miles from the Brewer town center. According to 2006 census data, Brewer has an approximate population of 9,079.
Location details are:
• 151 South Main Street, Brewer, Penobscot County, Maine; and
• North 44°47’25.31” latitude, west 68°46’12.43” longitude.
The Site is bordered to the:
• North by three residential properties along Hardy Street and a town owned parcel that is the location of a formerly active municipal landfill and currently houses a pump station. Additionally, this parcel is being utilized as a staging area for the Maine Department of Transportation;
• East by South Main Street;
• West by the Penobscot River; and
• South by the Penobscot River and a commercial property.
1.1.2.2 Description of Threat
In January of 2008, the Maine Department of Environmental Protection (MEDEP) requested that EPA Region 1 Emergency Planning & Response Branch evaluate the subject property, which is currently privately owned, to determine whether lead contaminated surface and subsurface soils along the Penobscot River pose a public health and environmental threat. On 18 April 2008, OSC Wainberg and Enforcement Coordinator Hennessy met with MEDEP representative Tracy Weston at the DEP Augusta offices to perform a file review and to conduct a site visit at the Rolnick Property. At the Site, T. Weston and the current property owner provided a tour and explained previous investigations and removal work. On 15 May 2008, the OSC, EPA contractors, and MEDEP completed a Removal Program Preliminary Assessment/Site Investigation (PA/SI), which included collecting soil samples in areas of concern MEDEP previously identified. OSC Wainberg recommended a time-critical removal action at the Rolnick Property Site in a Closure Memorandum dated 14 July 2008
On 19 August 2008 an Action Memorandum was approved authorizing a removal action at the Rolnick Property Site to address the public health and environmental threat posed by the lead in surface soils along the Penobscot River.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Since POLREP #9, the following activities have been conducted:
During the week of 19 October:
- The Emergency Rapid Response Services (ERRS) contractor continued riverbank excavation, rip-rap revetment installation, and contaminated soil staging activities (see section 2.1.2 Progress Metrics);
- The ERRS contractor cleared additional brush and trees along the riverbank south of current revetment installation work in preparation for revetment construction activities;
- The ERRS contractor shipped contaminated timber crib work to a permitted disposal facility;
- The ERRS sub-contracted surveyor added additional survey points along the riverbank to facilitate revetment installation;
- The Superfund Technical Assistance and Response Team (START) contractor conducted air monitoring activities; and
- Rip-rap revetment fill materials continued to be delivered to the site.
During the week of 26 October:
- The ERRS contractor continued riverbank excavation, rip-rap revetment installation, and contaminated soil staging activities (see section 2.1.2 Progress Metrics);
- The ERRS contractor shipped lead contaminated soil off site for disposal at a permitted disposal facility (see section 2.1.2 Progress Metrics);
- The START contractor conducted air monitoring activities; and
- Rip-rap revetment fill materials continued to be delivered to the site.
2.1.2 Progress Metrics
% Completion of Rip-Rap Revetment Installation As Of: 10/30/2009 |
Total Linear Feet of Riverbank |
Linear Feet Completed |
Linear Feet Remaining |
% Complete |
900 |
800 |
100 |
89% |
Waste Treatment and Disposal |
Shipped Week
Beginning |
Wastestream |
Quantity (tons) |
On-Site
Treatment |
Disposal Facility |
8/24/2009 |
Non-RCRA Lead Contaminated Soil |
529 |
Not Required |
Pine Tree Landfill
Hampden, ME |
8/31/2009 |
Non-RCRA Lead Contaminated Soil |
1040 |
Not Required |
Pine Tree Landfill
Hampden, ME |
9/28/2009 |
Non-RCRA Lead Contaminated Soil |
1311 |
Not Required |
Pine Tree Landfill
Hampden, ME |
10/26/2009 |
Non-RCRA Lead Contaminated Soil |
1956 |
Not Required |
Pine Tree Landfill
Hampden, ME |
|
Total |
4837 |
|
|
2.1.3 Response Actions to Date
In 2006, MEDEP performed a remediation of petroleum contaminated soils in the northeast corner of the property where the former gasoline station was located.
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
- Continue clearing and grubbing activities as necessary for riverbank work. Only a small amount of clearing remains at the north end;
- Continue to receive rip-rap revetment materials;
- Continue soil excavation and rip-rap revetment installation activities;
- Currently staged contaminated soil will be treated on site beginning next week and then shipped to a permitted disposal facility once sample analysis indicates effectiveness of the on-site treatment; and
- The portion of the riverbank that is adjacent to the previously constructed sea-wall will be addressed beginning next week. This will include the construction of a "bin-block" wall to the river side of the deteriorating crib work, followed by backfilling and rip-rap revetment construction. This is necessary to ensure the sea-wall is not compromised and reasonable slope grades are maintained.
2.2.2 Issues
Air monitoring will be conducted during all soil excavation activities.
|
|
2.3 Logistics Section
|
|
|
N/A
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer N/A
2.6 Liaison Officer Refer to Cooperating Agencies Section
2.7 Information Officer The OSC is available during site hours (generally 0700-1730) for inquiries from residents, the media, and other interested parties.
The OSC conducted an interview with NBC Channel 2 Bangor on 10/15/09. The news piece was broadcast on 10/15/09, but has not been posted to the web.
|
3. Participating Entities
|
|
3.1 Unified Command N/A
3.2 Cooperating Agencies EPA is working closely with the following agencies:
- MEDEP is providing field soil sampling analysis and anticipates funding and coordinating the re-vegetation of the riverbank;
- USACE has provided the Conceptual Plans for the riverbank stabilization and will remain available for concurrence, regulatory coordination, and technical support;
- U.S. Fish and Wildlife Service for coordination pursuant to Section 7 of the Endangered Species Act;
- National Marine Fisheries Service (NMFS) for coordination pursuant to Section 7 of the Endangered Species Act; and
- City of Brewer is providing assistance in areas of public works, law enforcement, fire, parks and rec., and other assitance as necessary.
|
4. Personnel On Site
|
|
- 1 EPA On-Scene Coordinator
- 1 START Contractor
- 8 ERRS Contractors
- 1 MEDEP Representative
|
5. Definition of Terms
|
|
N/A
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report For additional information please refer to http://www.epaosc.net/RolnickPropertySite.
6.2 Reporting Schedule POLREPs are issued every two to three weeks.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|