Oak Haven Lead

All POL/SITREP's for this site Oak Haven Lead
Salisbury, NC - EPA Region IV
POLREP #8
Final POLREP
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Oak Haven Lead - Removal Polrep
Final Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV

Subject: POLREP #8
Final POLREP
Oak Haven Lead
B433
Salisbury, NC
Latitude: 35.6369299 Longitude: -80.5296993


To:
From: Jeffery Crowley, On-Scene Coordinator
Date: 4/6/2010
Reporting Period: 2/10/2010 - 3/25/2010

1. Introduction
  1.1 Background
   
Site Number: B433    Contract Number: EP-S4-07-04
D.O. Number: 078    Action Memo Date: 11/5/2009
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 11/29/2009    Start Date: 11/30/2009
Demob Date: 2/26/2010    Completion Date: 3/25/2010
CERCLIS ID: NCN000410468    RCRIS ID:
ERNS No.:    State Notification: 9/10/09
FPN#:    Reimbursable Account #:

For Site Actions that occurred prior to this reporting period and background information, please refer to previous Pollution Reports.

2. Current Activities
  2.1 Operations Section
    The following activities occurred during this reporting period:

Rain continued to hamper efforts to remobilize to the Site until the week of February 23, 2010 when the following activities were completed:

  • All topsoil was placed on top of the clay cap and then seeded with naitve grasses.
  • Rock was placed in areas that historically washed out in order to protect the topsoil and clay from erosion.  This included constructing a drainage ditch coming down the main slope leading to inlet #2.  All inlets were protected with hay bales to prevent sediment from clogging the pipe.
  • Erosion control matting was placed over all areas where topsoil was placed.

The final activity completed onsite during this reporting was during the time March 24 and 25th when ERRS subcontracted some work to patch and repair some busted and cracked asphalt damaged during the removal action.

  2.2 Planning Section
    2.2.1 Anticipated Activities

    2.2.1.1 Planned Response Activities

There are no futher removal activities planned at this Site.
   

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  No information available at this time.

4. Personnel On Site
 
1 EPA OSC
3 ERRS - ER


5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  6.1 Internet location of additional information/report


6.2 Reporting Schedule
POLREPs will be completed on a bi-weekly basis through the duration of the project.