1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
B4K2 |
|
Contract Number: |
EP-S4-07-04 |
D.O. Number: |
130 |
|
Action Memo Date: |
6/30/2011 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
6/22/2011 |
|
Start Date: |
6/22/2011 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
SCD987673458 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
6/21/2011 |
FPN#: |
|
|
Reimbursable Account #: |
|
For background information including Site Description, Location, and Description of Threat please refer to previous POLREPs.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
EPA has transitioned from the Emergency Response Phase of the project into the Time-Critical Removal Phase. However, the dangers at the Site continue to pose an immediate threat to human health and the environment. The current focus at the Site is to mitigate the immediate threats of release from the Site to off-site migration pathways. EPA's estimated time to complete the removal is approximately April 30, 2012.
2.1.2 Response Actions to Date
To date the following response activities were completed during this reporting period:
Activities performed during the week of March 26th:
- ERRS contracter transported off-site Stockpiles #22 and #24 for a weekly total of 664 tons of arsenic contaminated soils.
- OSC, RM and START met with USACE personnel to discuss stream restoration plans.
- ERRS began final grading of western portion of site.
- A sample from the treated stockpile #23 was sent for TCLP analysis.
Activties performed the week of April 2nd:
- ERRS contractor received TCLP results from treated stockpile #23 for cadmium at .0070 mg/L.
- ERRS contractor began disposal of treated stockpile #23 for a weekly total of 649 tons of arsenic contaminated soil.
- START contractor placed erosion control mats and planted vegatation along the western and eastern sides of the stream bank per the stream restoration plan.
- START contractor has planted selveral pines along the western boundary of the site per the stream restoration plan.
Analytical Results of Stockpiled Material that failed the TCLP limit for non-hazardous waste of 1. mg/L for cadmium. Soil above this limit is considered hazardous waste and must be treated before it can be disposed in a Subtitle D Landfill. The treatment standard for cadmium is .11 mg/L or an alternative treatment standard of 90% reduction of the initial TCLP value and below 1.0 mg/L, in order to meet the Land Disposal Reguirements for Subtitle D Landfills.
Stockpile # |
Cadmium Initial TCLP Result (mg/L) |
Cadmium TCLP Result After Treatment(mg/L) |
7 |
3.43 |
.019 |
6 |
1.84 |
.011 |
1 |
3.61 |
.036 |
8 |
2.44 |
.017 |
9 |
2.64 |
.026 |
19 |
24.9 |
.091 |
20 |
23.2 |
.071 |
21 |
2.87 |
.119 |
23 |
1.07 |
.007 |
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Treatment |
Disposal |
Non-Hazardous, Arsenic and Cadmium Contaminated Soil (Total soil) |
Soil |
10,106 tons |
None |
Upstate Regional MSW Subtitle D Landfill |
Hazardous, Cadmium Contaminated Soil Treated On-Site |
Soil |
3,003 tons |
Free Flow 300/200 |
|
Magnesium Oxide |
Bulk |
4 tons |
None |
Upstate Regional MSW Subtitle D Landfill |
Scrap Metal |
Scrap Metal |
30.97 tons |
Cleaned |
Belton Metals Recycling |
Drums |
Metal |
3.4 tons |
Cleaned |
Upstate Regional MSM Subtitle D Landfill |
Non-friable Asbestos |
Vinyl Floor Tiles with Mastic |
1 cubic yd |
None |
Enterprise C&D Landfill (TSCA) |
Cement Pad |
Cement |
401 tons |
|
Upstate Regional MSM Subtitle D Landfill |
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
The following activities are planned during the next reporting period:
- ERRS contractor will continue load out of stockpile #23.
- ERRS will continue with site restoration activies.
- START contractor will conduct confirmation sampling under stockpile #23 and assist ERRS contractor with site restoration.
2.2.2 Issues
Now that all of the dangerous chemicals have been removed from the Site, EPA will focus on removing contaminated soils that contain arsenic. EPA will continue to work closely with local, state, and county officials throughout the cleanup process.
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
3.1 Unified Command
3.2 Cooperating Agencies
The following Agencies are Cooperating in the cleanup:
South Carolina Department of Health and Environmental Control
Anderson County Fire Department
Anderson County Sheriff's Office
Anderson County Emergency Services Department
United States Army Corps of Engineers
|
4. Personnel On Site
|
|
Maximum on-site personnel for reporting period:
USEPA OSC - 1
ERRS (ER) - 6
START (OTIE) - 1
DHEC -0
US Army Corps of Engineers - 1
|
5. Definition of Terms
|
|
ACM - Asbestos Containing Material
EPA - Environmental Protection Agency
EPM - Enforcement Project Manager
ERRB - Emergency Response and Removal Branch
ERRS - Emergency and Rapid Response Services
ERT - Environmental Response Team
MCL - Maximum Contaminant Level
OSC - On Scene Coordinator
PCB - Polychlorinated biphenal
PPE - Personal Protective Equipment
PRP - Potentially Responsible Party
RAL - Removal Action Level
RSE - Removal Site Evaluation
RSL - Removal Screening Level
RFQ - Request For Quote
SCDHEC - South Carolina Department of Health and Environmental Control
START - Superfund Technical Assessment and Response Team
TCLP - Toxicity Characteristic Leachate Procedure
USACE - United Stated Army Corps of Engineers
XRF - X-Ray Fluorescence
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|