1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
059B05 |
|
Contract Number: |
EP-S5-08-02 |
D.O. Number: |
0087 |
|
Action Memo Date: |
7/5/2011 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
NPL |
|
Operable Unit: |
05 |
Mobilization Date: |
9/26/2011 |
|
Start Date: |
8/30/2011 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
MID006007306 |
|
RCRIS ID: |
NA |
ERNS No.: |
|
|
State Notification: |
Yes |
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Fund-lead removal action
1.1.2 Site Description
See POLREP #1
1.1.2.1 Location
See POLREP #1
1.1.2.2 Description of Threat
See POLREP #1
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See POLREP #1
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Though additional work will be necessary in Spring of 2014, restoration activities were completed for the season in SA1A&B, SA3A and SA5A.
2.1.2 Response Actions to Date
From November 23 to December 20, EPA and ERRS contractors conducted the following activities:
Site Activities - SA1A & B
- Completed restoration plantings according to area-specific restoration plan;
- Removed remaining construction fence in work area; and
- Installed silt fence along creek banks in areas where trees/shrubs planted or seed/fertilizer/straw applied.
Project Management Activities
- Attended and provided a presentation at a public meeting for overall Allied Paper/Portage Creek/Kalamazoo River Superfund site;
- Continue review of post-construction soil sampling result data from work areas;
- Met with individual property owners affected by project to discuss and obtain signatures on close-out document (signed letters obtained from 7 of 11 property owners to date); and
- Continued review and development of project final report.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See POLREP #1
2.1.4 Progress Metrics
NA
|
|
2.2 Planning Section
|
|
|
Removal activities anticipated to take place from December 21, 2013 to March 28, 2014 include the following:
Site Activities - SA1A&B
- Conduct additional soil removal/grading activities in SA1A work area as needed;
- Apply seed/fertilizer mixture in areas around restoration plantings and concrete/asphalt repairs;
- Install erosion control blanket in areas where soil removal/grading/seed/straw applied; and
- Conduct additional restoration plantings as requested by property owner(s).
Project Management Activities
- Obtain close out letters from 4 remaining property owners affected by project;
- Plan replacement of 2012 restoration plantings (anticipated Spring 2014);
- Plan additional restoration plantings as requested by property owners (anticipated Spring 2014);
- Plan for additional soil removal/grading of soils in SA1A staging area (anticipated Winter/Spring 2014);
- Plan additional asphalt repairs needed in SA1C; and
- Continue development of project final report.
2.2.1 Anticipated Activities
See POLREP #2
2.2.1.1 Planned Response Activities
See above
2.2.1.2 Next Steps
See above
2.2.2 Issues
None
|
|
2.3 Logistics Section
|
|
|
The resources present on site during this reporting period include:
- ERRS contractor
- ERRS sub-contractor work crews (restoration plantings)
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer
Craig Thomas, Andy Maguire and Paul Ruesch served as safety officer(s). The HASP is reviewed and signed by all site personnel. All new personnel, including sub-contractors, are provided a site orientation and safety briefing.
2.6 Liaison Officer
Craig Thomas, Paul Ruesch and Andy Maguire serve as liaison(s) with local officials and interested parties.
2.7 Information Officer
See Section 2.6
2.7.1 Public Information Officer
A public meeting was held on December 4 to provide an update on the status of the project. Approximately 50 interested parties attended the meeting. An updated Fact Sheet (dated November 2013) was developed and distributed by mail and at the public meeting. The updated Fact Sheet is available in the 'documents' section of the project website.
2.7.2 Community Involvement Coordinator
Don DeBlasio and Patti Krause - U.S. EPA
|
3. Participating Entities
|
|
3.1 Unified Command
N/A
3.2 Cooperating Agencies
U.S. Environmental Protection Agency
Michigan Department of Environmental Quality
Michigan Department of Agriculture and Rural Development
Michigan Department of Natural Resources
U.S. Fish and Wildlife Service
City of Kalamazoo:
Department of Public Services
Parks and Recreation Department
Economic Development Department
Community Planning & Development
Public Safety Department
Fire Department
Police Department
Redevelopment Department
Bronson Methodist Hospital
Kalamazoo Nature Center
|
4. Personnel On Site
|
|
U.S. EPA - 1
ERRS contractor (Environmental Quality Management, Inc) - 1
ERRS subcontractor (restoration plantings) - 3
TOTAL PERSONNEL = 5
|
5. Definition of Terms
|
|
ERRS - Emergency and Rapid Response Services
FOSC - Federal On Scene Coordinator
HASP - Health and Safety Plan
KRVT - Kalamazoo River Valley Trail
mg/kg - milligrams per kilogram
mg/m3 - milligrams per cubic meter
MDEQ - Michigan Department of Environmental Quality
NA - Not Applicable
NPL - National Priorities List
PCB - polychlorinated biphenyl
ppm - parts per million
SA - Slope Area
START - Superfund Technical Assessment and Response Team
U.S. EPA - United States Environmental Protection Agency
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
See the project website at http://www.epaosc.org/portagecreekarea.
6.2 Reporting Schedule
The next POLREP will be generated on March 28, 2014.
|
7. Situational Reference Materials
|
|
See the project website at http://www.epaosc.org/portagecreekarea.
Additional information on the overall Kalamazoo River Project can be found at http://www.epa.gov/Region5/cleanup/kalproject/index.htm.
|