|
|
Site Number: |
B4C1 |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
6/9/2014 |
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
11/3/2014 |
|
Start Date: |
11/3/2014 |
Demob Date: |
1/23/2016 |
|
Completion Date: |
6/6/2016 |
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Site Description
The
Virginia-Carolina Chemical Company Mobile Site (the Site) is located in
Prichard, Mobile County, Alabama. The Site is a former fertilizer production
plant which occupied approximately 24 acres and was operated by the
Virginia-Carolina Chemical (VCC) Company. Fertilizer manufacturing began at the
Site prior to 1895 and continued until 1961. Through a series of buyouts and
corporate mergers the ExxonMobil Oil Corporation became the corporate successor
to this VCC site.
1.2 Site Location
Most of the former VCC property was located within the
current I-165 corridor and the original plant structures no longer exist. The
I-165 corridor consists of an elevated six-lane freeway deck with frontage
roads on both the northeast and southwest sides of the interstate. Structures
associated with the former plant include a fertilizer mixing and storing area,
acid chambers with associated burners/furnaces, a sulfur heap, a bag house, a
boiler room, an oil house, a potash storage building, an ammonia tank house,
and several electrical transformers.
1.1.2.2 Description of Threat
Former
phosphate production plants have historically produced waste products
containing arsenic and lead. In May 2010, ExxonMobil's contractor (ARCADIS)
conducted a Removal Site Evaluation (RSE) at the VCC Mobile Site to assess the
environmental impact associated with this former VCC plant. A total of 106 samples
were collected and analyzed for arsenic and lead. The results compared to Site
Specific Screening Levels (SSSL) for arsenic (27 ppm) and lead (800 ppm). The
SSSLs have been used as remediation endpoints at other former VCC fertilizer
sites and meet EPA’s Removal Management Levels for arsenic (240 ppm) and lead
(800 ppm) for an industrial exposure scenario. Analytical results demonstrated
that 15 of the soil samples exceeded the SSSL for arsenic (27 ppm) and that 5
of the soil samples exceeded the SSSL for lead (800 ppm). The maximum arsenic
and lead concentrations detected in the soil samples were 294 ppm and 8,350
ppm, respectively. The depth of impacted soil varied from 0.0 to 4 feet below ground
surface across the Site.
|
|
|
2.1.1 Response Actions to Date
Initial soil excavations for properties east of the I-165
corridor began on November 2, 2014, using a soft dig technique via air knife
and vac truck. This soft dig technique was performed in areas surrounding
utilities and subsurface anomalies identified by ground penetrating radar. Once
these soft digs were completed the soil excavation commenced via excavator.
Excavated soil was staged onsite and sampled for TCLP values prior to
transportation and disposal at the Chastang Landfill in Mt Vernon, Al. Approximately 21,976 cubic yards (33,996
tons) of soil were excavated, stockpiled and sampled for arsenic and lead using
TCPL analysis. After confirming that the TCLP levels for arsenic and lead were
below 5 mg/l for each constituent the soil was transported to the landfill for
disposal. These removal activities were performed by AECOM and are documented
in their Removal Action Completion report dated February 23, 2016.
Activities associated with removing the impacted soils west
of the I-165 corridor began on November 7, 2015, and were performed by Arcadis.
The initial activities included a lane closure along Hall Street, utility
markings, the installation of erosion and sedimentation control measures, and
grubbing and clearing operations. Prior to the excavation activities the soils
were characterized for TCLP values for arsenic and lead so that the soils could
be directly loaded on to trucks for disposal thereby avoiding stockpiling and
storage issues. The TCLP values revealed that the soils targeted for excavation
were below the TCLP values for arsenic and lead. Approximately 628 tons of soil
and debris was excavated, loaded directly onto trucks, and transported to the
Chastang Landfill for disposal. Following the soil removal activities the lane
along Hall Street was reopened, a section of North Kate Street was repaved, and
the temporary check dam along the drainage ditch was removed. The work crew
demobilized on January 23, 2016. These removal activities were performed by Arcadis
and are documented in their Supplemental Removal Action Completion report dated
March 14, 2016.
Air monitoring was
performed for dust, arsenic and lead during the removal action. The air
monitoring strategy consisted of monitoring three locations surrounding the
periphery of the excavation area. Action levels for air were set at 0.150 mg/m3
(dust), 0.005 mg/m3 (arsenic), and 0.03 mg/m3 (lead) and have been monitored
since the beginning of the soil excavation activities. Air monitoring results demonstrated
that arsenic and lead levels in the air remained below the action levels of
0.005 mg/m3 and 0.030 mg/m3, respectively, since the beginning of the soil
excavation activities. Particulate (dust) levels did exceed the action level of
0.150 mg/m3 on December 4, 2014, and December 18, 2015. Corrective measures
including the application of water by water truck reduced the dust particulates
below the action levels. Work resumed after these two incidences with no
further dust problems.
A Public meeting was
held on Sept 22, 2014, prior to the start of the removal action. The first fact
sheet was distributed by mail to residents prior to this public meeting. A
second fact sheet was mailed on February 2015 to update the residents about the
status of the removal action. Additional public relation activities included a
site visit from the Mayor of Prichard on February 25, 2015.
2.1.2 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
ExxonMobil has entered into an Administrative Order on Consent on May 16, 2014, for performing this removal action.
2.1.3 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Arsenic/lead |
Soil |
34,624 tons |
|
|
Chastang Landfill |
|
|
|
|
|
|
|
|
|
|
|
|
|