U.S. EPA OSC Steve Faryan and Weston Solutions Inc. (WSI) START personal, Ben Maradkel continue conducting oversight, while PRP contractor installs soil vapor extraction (SVE) wells.
■ Installation of twenty-three soil vapor extraction (SVE) wells outside facility and four inside facility. ■ On 6 January 2003, meeting was held at the village to discuss site status and upcoming tasks.
■ Transported and Disposed soil cuttings off-site.
■ PRP will remediate the surficial silty clay till and fill in Area 1 and 2 with Electrical Resistive Heating (ERH) technology.
■ PRP will remediate the mass waste sand and gravel in Area 1 and 2 with SVE technology.
■ Continue to install SVE wells.
■ Solve run-off problem in temporary parking lot (TBD e.g. catch basin)
■ Cut into concrete floor inside plant (former degreaser area).
■ Install equipment and process piping to the SVE wells.
■ Construct storage building.
■ Install electrodes and vapor wells for ERH.
■ Hookup vapor/air/water piping (ERH).
■ Review and Approve confirmation sampling plan.
■ Transport and Dispose soil cuttings and decontamination water off-site.
|