Lockformer

All POLREP's for this site Lockformer
Lisle, IL - EPA Region V
POLREP #7
Printer Friendly  |   PDF
 
On-Scene Coordinator - Steven Faryan 7/3/2003
- Removal Action Pollution Report (POLREP) #7
Pollution Report (POLREP) #7
Site Description
See site Profile Page

Current Activities
U.S. EPA OSC Steve Faryan and Weston Solutions Inc. (WSI) START Member provide oversight , while PRP contractors initiated remediation of the surficial silty clay till and fill in Area 2 with Electrical Resistive Heating (ERH) technology and the mass waste sand and gravel in Area 1 and 2 with SVE technology.  OSC and START also provided oversight for the air monitoring and sampling conducted by the PRP during operation of the SVE system and ERH system.

SVE System

■ All SVE wells and vapor piezometers are installed in Area 1 and 2.
■ Above and below surface SVE piping is complete in Area 1 and 2.
■ The SVE manifold (48 SVE Extraction wells) in the remediation building is complete.
■ Security system is installed in the remediation building.
■ Clayton Group Services, Inc. and Fliteway Technologies, Inc. conducted inspection and testing of the SVE system.
■ On 10 June 2003, remediation of Area 1 and Area 2 mass waste unit with the SVE system was initiated.

ERH System

■ All electrodes are installed in Area 1 and 2.  Installation of eleven electrodes in the degreaser pit area are yet to be installed.
■ All temperature probes are installed in Area 1 and 2.  Two temperature probes in the degreaser area have yet to be installed.
■ All vacuum piezometers are installed.
■ ERH remediation fence is erected and proper signs are displayed.  
■ Double beam security system is installed around the perimeter of the plenum.
■ All ERH equipment (PCU, blower, condenser, cooling tower, heat exchanger) is on site.  
■ The hook-up of the ERH system in Area 2 is complete.  
■ Thermal Remediation Services Inc. and Lockformer’s private electrician conducted inspection and testing of the ERH system in Area 2.
■ On 24 June 2003, the ERH system was turned on in Area 2.
■ On 30 June 2003, the temperature of the surficial silty clay till and fill in Area 2 is at 15 degrees C

Common Features for SVE/ ERH System

■ The construction of the remediation building is complete.
■ Site perimeter fence is erected and proper signs are displayed.
■ Weather station is installed onsite and is operating.
■ SVE/ ERH software is installed and operating, so that the SVE and ERH system can be monitored and controlled through a computer on site and off site.
■ On 11 and 12 June 2003, Lisle Fire and Police department were given a walkthrough and orientation of the site.

Sampling and Air Monitoring

■ The hydrocarbon analyzer is installed and operating.  Air monitoring is being conducted from five different ports (ERH inlet, SVE/ERH inlet, Intermediate/ after first vapor carbon, stack/effluent and inside Lockformer plant).
■ Hydrocarbon analyzer readings for the ERH inlet ranged from 20 ppm-167 ppm, SVE/ERH inlet ranged from 20 ppm-78 ppm, Intermediate/ after first vapor carbon ranged from 17 ppm-44 ppm , stack/effluent ranged from 15 ppm-44 ppm and inside Lockformer plant ranged from 1.6 ppm-3.8 ppm.
■ Background samples were collected from all sample locations.
■ Outside perimeter and indoor ambient air monitoring was conducted using a Miran Sapphire and/or PID.  
■ Outside perimeter readings have been not-detects (ND) and indoor ambient air monitoring ranged from 1.0 ppm-1.8 ppm.
■ Summa canister samples were colleted from the ERH inlet, SVE/ERH inlet, Intermediate/ after first vapor carbon, stack/effluent, inside Lockformer plant, site perimeter and residential area.  U.S. EPA method TO-15 is being used.
■ Summa canister sample data while SVE was operating and prior to ERH start-up shows that TCE concentrations from the SVE inlet range from 9.5 ppm- 11 ppm, Intermediate/ after first vapor carbon ND-0.0035 ppm, stack/effluent ND-0.0016, inside Lockformer plant ND-0.0018 and site perimeter and residential area TCE was not detected.
■ Tedlar bag samples were collected from the ERH inlet, SVE/ERH inlet, Intermediate/ after first vapor carbon, stack/effluent, inside Lockformer plant, SVE extraction wells (48 wells) and vacuum piezometers (25 wells) and screened with a Miran Sapphire and/or PID.  Certain samples were also sent to a local lab for quick turnaround.  U.S. EPA method 18 is being used.


Planned Removal Actions
■ PRP will continue remediating the surficial silty clay till and fill in Area 1, 2 with Electrical Resistive Heating (ERH) technology.

■ PRP will continue remediating the mass waste sand and gravel in Area 1 and 2 with SVE technology.


Next Steps
■ Continue remediating the surficial silty clay till and fill in Area 2 with Electrical Resistive Heating (ERH) technology and the mass waste sand and gravel in Area 1 and 2 with SVE technology.

■ Install the eleven electrodes and two temperature probes in the degreaser area.

■ Hook-up the ERH system in Area 1 and degreaser area.

■ Start remediating surficial silty clay till and fill in Area 1 and degreaser area.

■ Continue conducting air monitoring and sampling.