U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Omaha Lead Site

All POLREP's for this site Omaha Lead Site
Omaha, NE - EPA Region VII
POLREP #22
Printer Friendly  |   PDF
 
On-Scene Coordinator - Davis, Garvey, Nold 5/28/2004
Time-Critical - Removal Action Pollution Report (POLREP) #22
Start Date: 9/25/2003
Pollution Report (POLREP) #22
Site Description
The site is located in the Omaha metropolitan area and encompasses Council Bluffs, Iowa, Carter Lake, Iowa, and east Omaha. It is centered around downtown Omaha, Nebraska.

ASARCO Incorporated (ASARCO) operated a lead refinery at 500 Douglas Street in Omaha, Nebraska, for over 100 years beginning in the 1870s.  The operation of the refinery ceased in 1997.  As a routine part of the refinery operation, lead particles were emitted into the atmosphere at the refinery.  In addition, the Gould Incorporated Lead Battery Recycling Plant was located at 555 Farnam Street in Omaha and was a secondary smelter of lead from discarded lead batteries. The blast furnace used to smelt the lead at the Gould plant emitted lead particles into the air from that refinery.  The Gould plant closed in 1982.

Several other facilities in the Omaha area used lead in their manufacturing processes.  A few of these included Carter White Lead at 21st and Locust Street which produced white lead paint bases and red lead and litharge protective coatings until 1936, Omaha Shot and Lead which later became Lawrence Shot and Lead, and then became National Lead Company which manufactured lead shot by melting pig lead, Grant Storage Battery Company, Storage Battery Factory, and Exide Corporation which manufactured lead storage batteries.  

Numerous other locations in the Omaha area such as foundries, iron works, metal salvaging companies and other manufacturers used or processed lead at their facilities


Current Activities
On March 25, 2004, an Action Memorandum Amendment was signed. This amendment changes the scope of work to include daycare facilities and elevated blood levels (EBLs) that were previously addressed under the first Action Memorandum, however, still addresses highly contaminated properties with lead-soil concentrations of 1,200 milligrams per kilogram (mg/kg) or greater.

Continued activities are being centralized from the Missouri River Treatment Plant located at 5600 S 10th Street, Omaha, Nebraska, 68107-3501. The city of Omaha has partnered with the EPA to allow the use of a portion of the facility.

There were 4 properties excavated, 6 back filled and 15 sodded during this reporting period. So far during this phase of the time-critical removal action (phase III), there have been a total of 81 properties excavated, 80 backfilled, and 64 sodded.


Planned Removal Actions
Continued prioritization will be given to EBLs, day care facilities, and highly contaminated properties where children seven years of age or younger live.  The majority of these higher priority locations have been completed, therefore, geographic groupings of properties will now be implemented.

There are currently 28 EPA contractor personnel working extended work hours, 6 days a week.  The breakdown of personnel is comprised of two excavation crews and two backfill crews.  There is also a "punch list crew" that follows behind the other work teams to re-install fences and other needed repairs.  Then, a local sod subcontractor lays/installs new sod on the properties.  A few of the final steps include having the sod watered by the EPA for a two week period.  At that point, the property owner is provided with an instruction sheet (bilingual) that explains future care steps concerning the sod.  At this point, the property owner is encouraged to take over the responsibilities of care.  


Next Steps
The site has plans to take a short break over the Memorial Day holiday.  Significant site activities are scheduled to cease at 1:00 p.m., Friday, May 28, 2004, and than commence again at 1:00 p.m. Tuesday, June 1, 2004.  There will however, be some limited work activities during the holiday break period.  The water truck with a small crew will continue to water newly laid sod on properties.  Also, in an effort to load out the 4th stockpile of lead-contaminated soil, continued loading throughout the day on Friday, May 28, 2004 will occur.  This extra effort is required due to Missouri River Treatment Plant personnel requesting to not have more than approximately 1,000 cubic-yards of contaminated soil on the concrete pad at their facility at any one time.      


Key Issues
There is a list of 570 properties, with greater than 1,200 ppm lead, that is currently being prioritized for this phase of the project.  At this point, many of these properties have been completed during phase III of the project.

Any additional EBLs or day cares (affecting children), once received are receiving the highest priority.  

After those prioritized properties have been cleaned up, geographic locations will be utilized to maximize available resources concerning the greater than 1,200 ppm lead properties.  Sometimes there are difficulties encountered when attempting to contact property owners for scheduling, however, diligent efforts toward this goal are maintained.


 
Disposition Of Wastes
All of the lead-contaminated soil that is being removed from the day cares, EBLs, and greater than 1,200 ppm properties is being stockpiled at the Missouri River Treatment Plant.

The lead-contaminated soil is accumulated in 1,000 cubic-yard piles. The 4th, 1,000 cubic-yard pile of contaminated soil was transported on 5/27-28/04.      

Once a 1,000 cubic yard pile is created, a composite sample is taken and analyzed for Toxic Characteristic Leaching Procedure (TCLP) lead and total lead.  

During the last two phases of the time critical removal action, the contaminated soil has be sent to the Loess Hills Regional Sanitary Landfill, 59722 290th Street, located in Malvern, Iowa 51551.