See POLREP #1
Photograph Description (web site only): START chemist operating a BNC SAM 935 Multi-Channel Analyzer to determine waste activity levels.
October 6, 2004: 1 OSC, 3 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, RFPs for laboratory analytical out for bid, profiles for low (<30 pCi/g) and medium (30-222 pCi/g) radioactive waste submitted to U.S. Ecology for approval. START: worked on instrument technical issues with ERRS health physics sub-contractor, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 7, 2004: 1 OSC, 3 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm START: worked on instrument technical issues with ERRS health physics sub-contractor, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 8, 2004: 1 OSC, 3 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis START: assisted in segregation of rcm and non-rcm, MCA setup, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 11, 2004: 1 OSC, 5 START, 11 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis START: assisted in segregation of rcm and non-rcm, MCA analysis of samples, continued air surveillance, personnel decontamination assistance, update item web site and photodocumentation. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 12, 2004: 1 OSC, 4 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis, bulk medium level radioactive waste into roll-off bin. START: assisted in segregation of rcm and non-rcm, MCA setup, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 13, 2004: 1 OSC, 4 START, 11 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis, bulk medium level radioactive waste into roll-off bin. START: assisted in segregation of rcm and non-rcm, MCA analysis, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS
October 14, 2004: 1 OSC, 4 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis, bulk medium level radioactive waste into roll-off bin. START: assisted in segregation of rcm and non-rcm, MCA analysis, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS, intitate surface contamination migration assessments (support zone, sidewalk, street)
October 15, 2004: 1 OSC, 4 START, 12 ERRS, 2 PST ERRS: continued to bulk debris into roll-off bins, continued to segregate radium containing materials (rcm) and non-rcm, collect samples for MCA analysis, bulk medium level radioactive waste into roll-off bin. START: assisted in segregation of rcm and non-rcm, MCA analysis, continued air surveillance, personnel decontamination assistance. PST: gamma dose rate perimeter survey, personnel decontamination, medical surveillance, RCMS, continue surface contamination migration assessments (support zone, sidewalk, street)
Phase 2. North/South Yard Cleanout: Phase 2 operations expected to continue until late October 2004. Site operations will be suspended the week starting November 22, 2004 for the Thanksgiving holiday. Phase 3. North Building Cleanout: November 2004 Phase 4. North Building Structural Assessment: February 2005 Phase 5. North/South Building Decon: March 2005 Phase 6. Yard Area/Subsurface Assessment: March 2005 Phase 7. Yard/Subsurface Remediation: April 2005
See POLREP #10
1. Parking issues for site equipment and personnel 2. Discharge of gray water to POTW 3. Assessment of radioactive materials inside the structure.
|