See Initial POLREP dated 12/8/2004.
On March 29, 2005, the removal contractor remobilized to the site to begin excavation and treatment operations. The treatment system, which is comprised of a pug mill, reagent silo, and screen, was mobilized to the site and set up. Additional site preparation work which involved clearing of vegetation and on-site road repairs was completed. The excavation of contaminated soil above cleanup levels and on-site treatment was started on April 4, 2005.
Continue excavating of contaminated soils and on-site treatment. Treated soils will be disposed off-site at an appropriate landfill.
|