U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Warren Recycling

All POLREP's for this site Warren Recycling
Warren, OH - EPA Region V
POLREP #6
Printer Friendly  |   PDF
 
On-Scene Coordinator - Mark Durno 7/21/2005
Time-Critical - Removal Action Pollution Report (POLREP) #6
Start Date: 4/25/2005
Pollution Report (POLREP) #6
Site Description
Refer to Polrep #1

Current Activities
From July 18 through July 22, 2005, U.S. EPA and its Emergency Rapid Response Services (ERRS) and Superfund Technical Assessment and Response Team (START) contractors continued actions to reduce releases of hydrogen sulfide from the landfill and eliminate high level exposure to nearby receptors.

Routine actions include on-site and off-site monitoring for hydrogen sulfide and particulate matter, site security, and general site maintenance.  Specific response actions are detailed below.  

SITE ACTIVITIES TO DATE:
From July 18-July 22, 2005, the following activities occured:

·  As leachate treatability studies have concluded, cost analysis is being performed to select an appropriate product supplier.

·  The western portion of the site where the water treatment system will be located was cleared and grubbed.

·  Capping of the eastern slope and top of the "phase 2 summit" area of the landfill continues.  The first lift of the eastern slope of the Summit was completed on July 13, 2005.

·  One pond, contaminated with leachate, was treated with a biological product to test that product's effectiveness.  Water quality samples of the biologically treated pond were periodically collected to monitor for pH, dissolved oxygen (DO), sulfite levels, and hydrogen sulfide ‘headspace’ levels.

·  Site surveying continued to support the surface water management design.


Planned Removal Actions
·  Install a temporary, high capacity leachate treatment system.
·  Per the design plans, install a surface water / storm water management system which includes capping of the "phase 2 summit" location.
·  Design and install a permanent leachate management system.
·  If necessary, design and install a soil vapor extraction and treatment system.


Next Steps
·  Begin development of the surface water management system.
·  Continue placing a compacted cap over the "summit" location of the Phase 2 landfill.


Key Issues
None