The former American Lead facility is located at 2102 Hillside Avenue, Indianapolis, Indiana. American Lead operated a lead smelter at this location from 1946 to 1965. In 1965, National Lead Industries, Inc. (NL Industries) acquired the property and operated a lead reclamation facility. A fire reportedly damaged the smelter building in 1970 and NL Industries removed several buildings and slag piles in 1971. After several different owners, Irving Materials, Inc., (IMI) acquired the facility in 1990. The southeastern part of the facility was formerly leased to DuraCrete and is currently leased to Adjustable Forms, Inc., a manufacturer of building products (ESE 1999).
The facility is located in a mixed residential and industrial area. During the period of lead smelting operations, lead fumes and dust would have been released from the facility as point and fugitive sources and may have contributed to lead contamination at the facility and the surrounding areas. Investigations performed by the facility contractor and the Indiana Department of Environmental Management (IDEM) found lead contamination in residential and non-residential soils surrounding the facility. On March 13, 2003, IDEM requested assistance from U.S. EPA Region 5 Emergency Response Branch for a removal assessment because of failed negotiations with the PRP to reach a compromise on the remedial aspect of the project. U.S. EPA’s negotiations with the PRP resulted in an administrative order that required the PRP to characterize lead contamination in the surrounding areas of the facility (off-site) and remediate lead contaminated soil.
•AGC is continuing to gain access to residential properties to conduct sampling activities. Thirty-three properties still need access agreements signed. •AGC collected samples from 1 residential and 2 vacant lot property pre-excavation soil samples during this reporting period. AGC screened 1 residential, 8 vacant lot property and 0 church proper pre-excavation soil samples during this reporting period. -Residential properties were sampled by collecting 5-point composite soil samples. One composite was collected from 0-3" and one from 6-12" depth. Each residential property was sampled from the front yard and the backyard. Additional samples were collected from gardens and play area, if applicable. Vacant lots and church properties were divided into four quadrants and a 5-point composite soil sample was collected from each of quadrant and from 0-3" and 6-12" depth. •AGC currently has signed access agreements for 200 properties and sampled a total of 177 properties. Of those 177, six had XRF lead readings below the cleanup action level of 400 ppm. 167 properties would have to be partially or completed remediated, and 4 still need to be screened by an XRF instrument. •ENTACT has excavated 40 vacant properties, 4 churches, and 32 residential properties to date,no properties were excavated during the reporting period. •ENTACT has disposed of 18,200 tons of non-hazardous lead-contaminated soil to date, 1150 tons during the reporting period. •ENTACT did not collect post-excavation confirmation samples during the reporting period. •ENTACT backfilled 33 vacant lots, 4 churches, and 32 residential properties to date. No properties were backfilled during the reporting period. •ENTACT has placed sod/seed on 2 vacant/side lots, 1 church and 0 residential properties to date. •ENTACT conducted daily air monitoring near residential entrance (if applicable) and up and down wind of every excavation area. To date there have been no exceedances of the ENTACT action level of 2.5 milligrams per cubic meter (mg/m3). •ENTACT and AGC demobilized for the winter. ENTACT has one person remaining on site to conduct oversight of tree removal.
1) Removal of trees on properties where owner has agreed. 2) Demobilize for the winter.
1) Demobilize for the winter, mobilize back in the spring of 2006
None.
|