See initial PolRep.
Continued the transportation and disposal of the PCB-contaminated soils. Approximately 500 tons of PCB-contaminated soil were shipped to Wayne Disposal facility in Detroit for landfilling.
Continued the segregation of the drums and containers. A total of 190 drums have been removed to date.
Continued the air monitoring of both the perimeter and the work area.
Conducted a treatability study for lead, and samples were sent to an outside lab, for analysis.
Prepared and secured the site for the holiday break.
Remove and Sample Drums & Containers
Sample soil stockpiles & generate waste profiles
Perform Hazard Categorization
Overpack/Repack Drums & Containers
Excavate/Treat Impacted Soils, as necessary
Transport/Dispose Drums & Impacted Soils
Backfill & Grade Excavated Areas
Restore Site, as necessary
Receive analytical test results from the treatability study. Determine the proper concentration of quick lime needed to treat the lead. Plan the on site treatment operations.
Continue hauling excavated and treated soils from the site, to the proper disposal facility.
Continue excavation operations.
Secure funding for the continuation and completion of the project.
|