See initial PolRep.
Continued the on-site treatment of contaminated soils by using quick lime, in order to reduce the TCLP levels of lead. Approximately 220 cubic yards of materials were treated (approximately 730 total cubic yards).
Continued the air monitoring of both the perimeter and the work area.
Collected one composite sample from the treated soils for analysis by an outside lab. Analytical test results indicated that the soil treatment was successful.
Transported and disposed off approximately 625 tons of PCB-contaminated soils (approximately 1800 total tons).
Continued the excavation of areas of concern. Approximately 75 cubic yards of contaminated soil (1700 total cubic yards), 5 drums (256 total drums) and 32 paint cans (46 total paint cans) were removed.
Secured the site for the annual OSC training.
Remove and Sample Drums & Containers
Sample soil stockpiles & generate waste profiles
Perform Hazard Categorization
Overpack/Repack Drums & Impacted Soils
Excavate/Treat Impacted Soils, as necessary
Transport/Dispose Drums & Impacted Soils
Backfill & Grade Excavated Areas
Restore Site, as necessary
Return to site after training on January 20th, 2009.
Transportation and disposal of treated soils.
Continue the excavation of contaminated soils and buried drums.
Continue the air monitoring and sampling activities.
Continue the treatment of the mixed PCB waste.
Secure funding for the continuation and completion of the project.
|