U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Elkton Farm Firehole

All POLREP's for this site Elkton Farm Firehole
Elkton, MD - EPA Region III
POLREP #24 - Continuation of work
Printer Friendly  |   PDF
 
On-Scene Coordinator - Dominic Ventura 5/15/2006
Time-Critical - Removal Action Pollution Report (POLREP) #24
Start Date: 1/31/2006
Pollution Report (POLREP) #24
Site Description
Work Mission Statement:

Safely and efficiently investigate and remove Munitions and Explosives of Concern (MEC); Materials Potentially Possessing an Explosive Hazard (MPPEH), Munitions Debris (MD) and explosively contaminated soil(TNT) from the Elkton Farms Firehole Site, as defined in EPA's geophysical study.


Current Activities
During this reporting period the intrusive activities continued within grids: B3,C3,G6 and J5.  These activities included magging and flagging of all metal items and the hand digging/shovelling of these flagged materials.  In addition bush hogging and general brush clearing continued in grids C2, B2, A2 and A4.  These are preparatory clearing activities for Rangemaster work.  

The Rangemaster, originally scheduled to arrive on site on April 17 and then again on May 1, finally arrived on site on May 09. The delay was due to transport permit issues and sub contractor issues during the transport of this large piece of equipment from California. Ingress of this large (140k lbs) piece of equipment, thru two separate farms, resulted in negligible impact to crop and soil.  Both property owners have registered no complaints with the EPA.

Due to the USACE inability to obtain its HQ approval of the Explosive Safety Submission (ESS) for Phase II activities, the Rangemaster was limited to removal of site grass and topsoil. No intrusive activities were allowed.  As the Rangemaster hopper filled with topsoil/grass it was determined that the shaker hopper would have to be manually checked for MD.  The FOSC requested IPC/USACE to provide a HASP ammendment (SOP) for this manual action. See photo of this issue at  https://www.epaosc.net/image_zoom_update.asp?counter=30634. Limited IPC personnel worked both on Friday and Saturday (May 12 and 13) to effect removal of this material from the shaker hopper.    

START under direction from the FOSC has procured the services of a UXO certified contractor (Malcolm Pirnie Inc.) to assist the EPA with ordnance identification and Phase II oversite activities.  This oversite contractor commenced his onsite activity on May 15.    

MPPEH RECOVERED DURING WEEK AND DISPOSITION: (SHA-Safe Holding Area)  
11-ea 40mm tracer elements, grid J5d, SHA
3-ea partial base flares w/filler, J5d, SHA
1-ea 4lb incendiary w/ partial body no fuze, G6a, SHA
148-ea 40mm tracers, grid G6a, SHA
1-ea partial grenade fuze, C3d, SHA
123-ea 40mm tracers, grid G6a, SHA
7-ea 40mm tracer elements, grid J5d, SHA
14-ea 40mm tracers, Range Master Sweep (RMS), SHA
94-ea 40mm tracers, grid G6a, SHA
3-ea HE boosters, grid G6a, SHA
4-ea 40mm tracer elements, grid J5b, SHA
1-ea partial flare base w/residue, grid J5b, SHA
2-ea 40mm tracers, C3d, SHA
76-ea 40mm tracers, grid G6a, SHA
2-ea HE boostera, gris G6a, SHA
8-ea 40mm tracer elements, grid J5b, SHA
1-ea partial flare base w/residue




Through May 11, 2006 the following stats apply:
Total grids - 66 (200x200)
Grids cleared - 22
Percent complete - 33.3%
Grids cleared this reporting period: 0.50
Grids Government Qc'd - 22
Grids failed - 0
Total Number of digs - 37,253
Number of live MPPEH - 1,812
Pounds of MPPEH/MD found - 275
Pounds of non MEC scrap found - 1,477

Refer to this web site for updated adobe map of site completion activities:
https://www.epaosc.net/sites/1299/files/grid%20data%20update%20map%20060513.pdf


Planned Removal Actions
Initiate Phase II activities with the Rangemaster
ASAP.