U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Synthron Chemical Fire

All POLREP's for this site Synthron Chemical Fire
Morganton, NC - EPA Region IV
POLREP #5
Printer Friendly  |   PDF
 
On-Scene Coordinator - Perry Gaughan 6/2/2006
Time-Critical - Removal Action Pollution Report (POLREP) #5
Start Date: 5/9/2006
Pollution Report (POLREP) #5
Site Description
For Site description and background information, refer to previous POLREP.

Current Activities
Hazardous Materials Activites
Total drum inventory is 684 and over 450 drums have been sampled and hazcatted.  More than 200 totes have been collected on site.  Above storage tanks 1-15 and 20-21 have been sampled and hazcatted.  One unopened drum of liquid organic peroxide has been removed from site for reuse.  Large quantity of lab chemicals have been recovered from an office trailer on site.  Additional lab chemicals, unbreached drums, and totes remain in the ruins of the structure and will be recovered as demolition continues.  WRS is contacting suppliers for removal of unopened chemicals on site and will schedule lab packing of recovered lab chemicals.  ERRS chemist is contacting the manufacturers of unopened raw materials to schedule returns.  All compressed gas cyclinders have been removed from rhe site.

Buidling Demolition Activities
NC Dept. of Public Health approved asbestos demolition permit pending the selection of landfill for asbestos containing material.  START developed and implemented asbestos perimeter monitoring and personal samplers during demolition activities.  Synthron management provided location of two underground storage tanks on site.  One has been closed in place and the other is  permitted for fuel oil, but is not longer in use.  Natural gas company removed gas meter and purged lines through property. ERRS filled nitrogen tank on site to purge process lines containing solvents prior to demolition.  Damaged Sales Office trailer and pipe rack from tank farm to building have been demolished.  Crew is removing the roof structure of main building to obtain access to reactors.  Fencing was installed around area where office trailer was located and area  was cleared to stage recovered items for forensic evidence examination.

Wastewater Disposal Activities
Received sample analysis for all 12 Frac tanks.  FT 1-6 will require pretreatment prior to discharge to the POTW.  Cost analysis of pretreatment vs. off-site treatment/disposal indicated the latter to be most cost effective.  Sent samples of FT 7-12 to SESD for LC-50 test as requested by POTW.  Results expected the week of 6/12.  POTW is analyzing samples from FT 7-12 for TSS.  Expect disposal of FT 7-12 to POTW beginning the week of 6/12 through 6/23.

Off Site Activities
Soil sediment analysis from the stormwater ditches on both sides of Amherst Rd and Hunting Creek showed no contaminate above the industrial soil sediment PRGs.  Copy of analysis was forwarded to Laura Niles and Catamba Riverkeepers.  Charlotte Channel 9 News on site 6/2 for footage for a short update on the site.  Synthron provided information on location of USTs, electronic version of raw material MSDSs, and profiles for hazardous waste drums.

Misc. Activities
Coast Guard mobed on site 5/31.  USCG is providing perimeter dust monitoring during demolition activities and site radio communications.  USCG will provide H&S and oversight assistance during forensic evidence recovery.  



Planned Removal Actions
Continue demolition of main building to recover hazardous materials.  Continue sampling and hazcatting of drums, totes, and tanks.  Complete the forensic evidence recovery for NC OSHA and CSB.  Begin discharge of FT 7-12 to POTW.  Continue perimeter monitoring for dust and asbestos during demolition activities.

Key Issues
Forensic evidence recovery
Disposal of wastewater for off site treatment and to POTW.
Disposition of unopened raw materials
Bulking of hazardous and non-hazardous waste for disposal
Asbestos segregation and removal
Demolition of main building and boiler rooms
Inventory of assets that will be left on site