Southeastern Wood Preserving

All POLREP's for this site Southeastern Wood Preserving
Canton, MS - EPA Region IV
POLREP #6
Printer Friendly  |   PDF
 
On-Scene Coordinator - Carter Williamson 11/18/2009
Time-Critical - Removal Action Pollution Report (POLREP) #6
Start Date: 8/31/2009
Pollution Report (POLREP) #6
Site Description
The Southeastern Wood Preserving Site is an abandoned wood preservation plant facility which operated from 1928 until it filed for bankruptcy in early 1979.  The Site covers approximately 20 acres and is located in a predominantly commercial/residential area just east of downtown Canton, Madison County, Mississippi.  Batchelor Creek and Illinois Central Gulf Railroad border the Site to the north.  The railroad is no longer operational.  The City of Canton's drinking water well field lies just south of the Site.  An abandoned industrial area lies to the east and a residential area borders the Site to the west.

The production process involved debarking of the Southern Yellow Pine timbers and placing them in retort cylinders for drying and pressure treatment using creosote and pentachlorophenol as preservatives.  Prior to 1977 and the Clean Water Act, the facility reportedly discharged approximately 50,000 gallons of waste-water directly into Batchelor Creek.  In May of 1977, the company was hooked into the City of Canton sewage system.  The wastewaters were to be pre-treated prior to discharge into the City lagoons.  On several occasions the City ordered the facility to cease discharge due to failure to adequately treat the wastewaters.

Batchelor Creek flows through a City park approximately 1 mile downstream from the Site, passes through a residential area and then continues through downtown Canton before leading into the Big Black River approximately 10-12 miles downstream.  There is evidence of fishing and recreational usage in the Big Black River.

The Site has a long history of EPA involvement.  The Emergency Response and Removal Branch (ERRB) of the EPA initiated an emergency response in early 1986 in order to stabilize three unlined surface impoundments that were overflowing on-site.  Each impoundment contained creosote sludge and waters.  The response action consisted of pumping 30,000 gallons of water from flooded areas of the Site, treating it, and discharging it into Bachelor Creek.  Subsequent to this response, it was evident that the Site would be referred to ERRB for a removal action.

The initial Action Memo was signed in May 1986.  It requested that site activities be addressed and funded in two phases.  The scope of the first phase consisted of excavating and stockpiling hazardous waste on-site.  The contaminated soils and sludges in the vicinity of the former lagoons were stabilized with lime kiln dust, placed in a stockpile and fenced.  The second phase of the action was to consist of on-site treatment or off-site disposal of the material, but this action was delayed for several years.

In 1988 the Soil Conservation Service (SCS) contacted EPA after observing oily waste leaching into the Creek from the Southeastern Wood Preserving Site.  SCS had designed a soil erosion prevention plan that called for excavating and widening Bachelor Creek.  Through an Interagency Agreement, SCS contributed $190,000 towards the excavation work.  The Creek was widened according to Plan and a geofabric liner was placed in the bed of the Creek.  The bed and the banks were then covered with rip rap in order to prevent erosion.

An exemption from the twelve-month statutory limit and ceiling increase as approved in August of 1989 in order to address the second phase of the removal action.  A composite sample from the waste pile indicated a PAH concentration of 5016 ppm and a phenol concentration of 62 ppm.  The 8000 cubic yard on-site stockpile was to be treated through bioremediation landfarming techniques.  A ceiling increase and $2 million exemption was approved in 1990 once proposals were received.  The RCRA Land Ban treatment standards and air emission standards required a slurry phase treatment due to the health based risk associated with the Site's surrounding residential/commercial areas.  The removal action required the treatment of the contaminated soil to the K001 waste code Land Disposal Requirements (LDR) standards.  The contractor proposed to utilize a batch bioremediation process consisting of screening, mixing with water, slurrying in two parallel biological slurry reactors (BSRs), and final treatment and drying in a double lined land treatment unit (LTU).

In 1992 An Amendment to Removal Action Memoranda Requesting a Treatability Variance was approved.  After several failed attempts to reach the K001 LDR Standards with the bioremediation technique, it became apparent that a treatability variance would be necessary.  The clean-up levels for phenanthrene and pyrene were adjusted without compromising the goals of the Removal Action by maintaining concentration of total PAHs below 100 ppm.

On February 26, 2003, representatives from the EPA and the Mississippi Department of Environmental Quality (MDEQ) met at the Site for a reconnaissance.  During the reconnaissance the non effective treated soil was observed.  It was noted that the pile had sunken over the years and could possibly be leaking into Bachelor Creek.

On June 6, 2007 On-Scene Coordinator Hughes visited the Site to perform a Removal Site Evaluation after the Site was referred to the Branch from the MDEQ.  The OSC met the State representative on-site in order to characterize the layout of the Site and address the needs to fully perform the Removal Site Evaluation.  The temperature mobilized the creosote present in the bed of Bachelor Creek enabling observation of releases downstream.  Please see the photos in the Images Section.

On September 18, 2007 OSCs Hughes and Negron met with representatives from EPA's Science and Ecosystem Support Division in order to perform several borings in the area between the stockpile, the former lagoon and the Creek.  The stream invert adjacent to location A0 was surveyed and found to lay approximately 14 feet below ground surface at the borehole location.  The stream has a mild gradient as it flows west and is estimated to drop less than 5 feet.  

Starting on August 25, 2009, EPA and ERRS personnel mobilized to the Site. Excavation of Batchelor Creek began and continues at present.  OSC Carter Williamson is directing all on-site activities with the assistance of the United States Coast Guard, Gulf Strike Team.


Current Activities
ERRB discussed the test trenching results with the Remedial Program and began excavating an additional 6-8 feet of depth in creekbed to remove additional contaminated soils and free product.  These soils are being placed in a separate staging pile alongside the first impoundment that holds the first 4 feet of creekbed excavated.  Equipment failures and break-downs have hampered site activities, however, a great deal of excavation of the creek-bed have taken place since the last reporting period.  

Approximately 400 additional feet of creekbed (11 Cubic yards of contaminated soil per foot) has been excavated and stockpiled.  Additional clean backfill has been deployed on the Western wall of the creekbed to bolster the existing embankment to prevent cave-ins and safety issues.

The Community Involvement Coordinator (CIC) was deployed to the site to work with MDEQ staff to conduct additional community involvement activities, visits to adjacent residential properties, Canton City Government etc.  The CIC and MDEQ staff canvassed neighborhoods, established an Information Repository at the Madison County Library, visited the Chamber of Commerce and drafted a fact sheet to be distributed amongst the community.  

START has been deployed to sample the excavated creek basin (5 point composites) and the existing stockpiles.  Once collected, samples will be run through CLP with results to determine confirmation that creekbed is either clean or in need of additional excavation.  Sample results of stockpiles will help determine potential for disposal and/or temporary/permanent placement on site.

U.S. Coast Guard (Gulf Strike Team) are on-site to provide federal presence in the absence of the EPA FOSC.  USCG personnel are being tasked to provide site safety, photo-documentation and assistance with Canton community involvement.


Planned Removal Actions
Approximately 400 feet of Batchelor Creek has been excavated down to a 10 foot depth (approximate) with the same distance exceeded planned moving Southward after EPA OSC, GST and ERRS staff return from the Thanksgiving holidays break.  

ERRS will continue to excavate creekbed to the appropriate depth when creosote contaminated soils are noted and move Southward approximately 400 feet to remove additional soils.  

Once the creekbed is removed, excavation equipment will be re-directed to remove Western bank of creek that is contaminated and replace with clean backfill and rip-rap.  Upon completion of that task, ERRS will be begin construction of a 3 foot by 22 foot (approximate) slurry wall containment structure to prevent further migration of contaminants off-site and into Batchelor Creek.  
  




Next Steps
EPA and ERRS will be off-site from November 21-29 for the Thanksgiving Day holidays.  Site activities will continue on November 30, 2009.

Receive sample results from creekbed and stockpiles to determine future removal activities in creekbed and to determine possibility of disposal of staged soils on-site.  

Continue excavation of Batchelor Creek, coordination with community and Canton city government and discussions with EPA Remedial Program regarding the long term remediation of the SE Wood Site.


.


Key Issues
Inclement weather's impact on site work

Repetitive breakdown of heavy equipment on site.

Coordination with the City of Canton Utilities Department regarding unscheduled and scheduled releases of large volumes of waste water into Batchelor Creek which impacts site activities.

Removal of additional creekbed soils in Batchelor Creek to the clean Yazoo Clay layer.  

Coordination with MDEQ, the City of Canton and the EPA Remedial Program on the successful completion of this time-critical removal action.

Sample results of excavated soils to determine constituents in soils for future transfer and disposal options and to confirm degree of removed contamination in Batchelor Creek..

Question as to transfer of contaminated soils off-site or stockpiled and capped at the present location.

Determination on how to address opposing (Eastern) creek bank that has evidence of creosote contaminated soils present.