HoltraChem

All POLREP's for this site HoltraChem
Riegelwood, NC - EPA Region IV
POLREP #28
Printer Friendly  |   PDF
 
On-Scene Coordinator - Leo Francendese 12/29/2008
Time-Critical - Removal Action Pollution Report (POLREP) #28
Start Date: 5/19/2008
Pollution Report (POLREP) #28
Site Description
The HoltraChem Site (also known as Acme Alkali) is comprised of approximately 24 acres and is located at 636 John L. Riegel Road in Riegelwood, Columbus County, North Carolina.  It is surrounded on three sides by International Paper (IP), which is comprised of approximately 1,500 acres. Both HoltraChem and IP border the Cape Fear River.  The surrounding area is a mixture of industrial, residential and commercial uses.

The area subject to this removal action includes neighboring IP’s North Bay treatment pond, also known as Cell #2.  IP formerly accepted process water generated during chlorine production from the Holtra Chem facility.  HoltraChem operated as a chlor-alkali facility using the mercury cell process from 1963 to 1999, when facility operations ceased.  HoltraChem was originally constructed to provide chlorine gas, caustic soda, and bleach to the IP facility. Process water from the former HoltraChem facility was reportedly discharged to the northwest corner of Cell #2 via a 16-inch diameter, corrugated galvanized steel pipe from approximately 1963 to the late 1970s or early 1980s.

A time-critical removal action was conducted at the HoltraChem Site during 2003 – 2004, during which containerized hazardous waste and the former cell building were removed.  In 2004, an Engineering Evaluation / Cost Analysis (EE/CA) investigation began at the Site.  During the EE/CA, the primary contaminants of concern were identified as mercury and PCB Aroclor 1268.  Sampling conducted by IP identified PCB Aroclor 1268 at concentrations up to 5,100 mg/kg in Cell #2.  PCB contamination extends to a depth of approximately 12 feet below the ground surface.  PCB contamination has been found in the adjacent Cape Fear River sediments.  IP needs to utilize Cell #2 for the expansion of their landfill sooner than the EE/CA will be completed.  Therefore, a Time-Critical Removal Action is being taken to excavate the contaminated Wastewater Treatment Solids (WWTS) from Cell #2 and place the WWTS with concentrations exceeding 50 mg/kg in temporary storage on the HoltraChem Site until the final cleanup plan is selected for HoltraChem.  The estimated volume of this material was 6,500 cubic yards.  The cleanup goal for this removal action is 11 mg/kg based on the Human Health Risk Assessment for the Holtra Chem Site.  WWTS with concentrations between 11 mg/kg and 50 mg/kg will also be excavated, but will be placed in IP’s landfill Cell #1.  The estimated volume WWTS with PCB concentrations between 1 mg/kg and 49 mg/kg was 93,500 cubic yards.

The Enforcement Action Memorandum for this time-critical removal action was signed on May 13, 2008.  The Effective Date of the Administrative Order on Consent for this removal action was May 20, 2008.


Current Activities
Activities conducted by the PRPs' contractors during this reporting period, December 14-20, 2008, included:
* Completed rough grading of Cell No. 2, including backfill/compaction in the northwest corner of the Cell to promote drainage to the southeast corner.
* On 12/18, IP requested additional excavation of unsuitable material from the southeast corner. Approximately 200 cubic yards of material was excavated from grids S-10 and S-12.  On 12/19, this material was transported to IP's landfill.
* Continued completing the Pre-Final Inspection findings.
* 256,400 gallons of water was treated at the site during this reporting period.  This brings the total quantity of water treated since June to 6,082,700 gallons.
* On 12/16 and 12/19, water samples were collected for offsite lab analysis and TSS (TSS analysis by IP).  Analytical results for the samples collected on 12/10, 12/12 and 12/16, were reported to the Team during the week. An exceedance in the 12/10 influent sample resulted in the water treatment “clock” starting over. Note that on scheduled “every-other-day” sampling events, adequate water in the sump area is sometimes not available to pump/treat water.
* On 12/18, wipe sample results were submitted to the Team to demobilize the John Deere 650J.  All results were below the 10 ug/wipe decontamination goal.


Planned Removal Actions
Activities planned for the next reporting period, December 21-27, include:
* Due to the holidays, site work will only occur on 12/22 and 12/23.
* Demobilize John Deere 650J.
* Continue removal of unsuitable material in the southeast corner of Cell #2.
* Collect water treatment samples on 12/22.
* Continue completing the Pre-Final Inspection findings.
* Preparation for final site demobilization.


Next Steps
The schedule for the completion of the removal activities indicates demobilization has been shifted to January 14, 2008.  This date is dependent on influent water sample results of Aroclor 1268 remaining below 3 ppb for five consecutive sampling events.  The final walk-through is tentatively scheduled for January 12th or 13th, 2009.