U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ore Knob Mine Site

All POLREP's for this site Ore Knob Mine Site
Ore Knob, NC - EPA Region IV
POLREP #1 - Initial Polrep
Printer Friendly  |   PDF
 
On-Scene Coordinator - Terrence Byrd 10/23/2008
Time-Critical - Removal Action Pollution Report (POLREP) #1
Start Date: 10/20/2008
Pollution Report (POLREP) #1
Site Description
The Site contains areas affected by mining, including three principal areas that were directly affected by mining along with other areas, primarily downstream, where hazardous substances have come to be located.  The three principal areas include the 1950s Mine and Mill Area, the 19th Century Operations Area and a Main Tailings Impoundment.  This Action memo recommends response actions to address threats from the main tailings impoundment.

The 1950's Mine and Mill Area comprises 15 acres and is located northwest of the intersection of Ore Knob Road and Little Peak Creek Road, just north of Highway 88.  This area contains derelict ore bins, concrete mill foundations, a transformer building, other ruins, a small sawmill currently in operation, two acres with about 10,000 cubic yards of tailings - now mostly covered with stumps, and a two acre former pond where process water was stored.  Little Peak Creek starts just upstream of the former pond, flows through the former pond, and discharges into Peak Creek 2.5 miles downstream.  

The 19th Century Operations Area and the Main Tailings Impoundment are located across Little Peak Creek Road, at the end of Ore Knob Mine Road.  The 19th Century Operations Area includes a series of barren and nearly barren stretches of land (totaling about 5 acres) near the top of Ore Knob that contain waste rock dumps from at least 11 mine shafts as well as locations where ore was roasted to drive off sulfur and smelted to recover copper.


Current Activities
EPA, NCDENR and ERRS met at the Site to discuss the Site remedy.  ERRS widened and graded the access road, making it accessible for heavy equpiment.  ERRS also began gaining access to the sediment pond.  Drilling contractors have taken SPT and CPT samples of the tailings dam in order to determine its stability.  Site security has been obtained and aerial photography has been taken.  

Planned Removal Actions
NCDENR and EPA plan to take surface water samples within the next few weeks.  The diversion channel will be staked based on conceptualized drawings provided by the US Bureau of Reclamation.  Construction of the diversion channel will begin after the results of the stability analysis are received.  Meanwhile, the lower sediment pond will be emptied.

Next Steps
EPA is planning a community meeting to inform residents of the removal activities at the Site.

Key Issues
no key issues at this time