U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ore Knob Mine Site

All POLREP's for this site Ore Knob Mine Site
Ore Knob, NC - EPA Region IV
POLREP #2 - Sludge Removal Continues
Printer Friendly  |   PDF
 
On-Scene Coordinator - Terrence Byrd 11/3/2008
Time-Critical - Removal Action Pollution Report (POLREP) #2
Start Date: 10/20/2008
Pollution Report (POLREP) #2
Site Description
The Site contains areas affected by mining, including three principal areas that were directly affected by mining along with other areas, primarily downstream, where hazardous substances have come to be located.  The three principal areas include the 1950s Mine and Mill Area, the 19th Century Operations Area and a Main Tailings Impoundment.  This Action memo recommends response actions to address threats from the main tailings impoundment.

The 1950's Mine and Mill Area comprises 15 acres and is located northwest of the intersection of Ore Knob Road and Little Peak Creek Road, just north of Highway 88.  This area contains derelict ore bins, concrete mill foundations, a transformer building, other ruins, a small sawmill currently in operation, two acres with about 10,000 cubic yards of tailings - now mostly covered with stumps, and a two acre former pond where process water was stored.  Little Peak Creek starts just upstream of the former pond, flows through the former pond, and discharges into Peak Creek 2.5 miles downstream.  

The 19th Century Operations Area and the Main Tailings Impoundment are located across Little Peak Creek Road, at the end of Ore Knob Mine Road.  The 19th Century Operations Area includes a series of barren and nearly barren stretches of land (totaling about 5 acres) near the top of Ore Knob that contain waste rock dumps from at least 11 mine shafts as well as locations where ore was roasted to drive off sulfur and smelted to recover copper.


Current Activities
Contractors began removing tailing sludge from the sediment pond at the north end of the tailings dam.  To date approximately 1,500 cubic yards of sediment has been removed from the sediment pond and deposited onto the sediment dam.

Planned Removal Actions
sludge removal of the sediment pond should continue until the next week.  EPA plans to ground truth the planned location of the diversion channel based on plans that will be obtained with the aid of BOR.  

Next Steps
EPA will meet with US Bureau of Reclamation during the week of 11/03/08 in order to finlize plans for construction of the diversion pond.  EPA will be distributing fact sheets to local residents and planning a date for a local information session.

Key Issues
none to date