U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ore Knob Mine Site

All POLREP's for this site Ore Knob Mine Site
Ore Knob, NC - EPA Region IV
POLREP #4 - Sludge Removal Continues
Printer Friendly  |   PDF
 
On-Scene Coordinator - Terrence Byrd 11/17/2008
Time-Critical - Removal Action Pollution Report (POLREP) #4
Start Date: 10/20/2008
Pollution Report (POLREP) #4
Site Description
The Site contains areas affected by mining, including three principal areas that were directly affected by mining along with other areas, primarily downstream, where hazardous substances have come to be located.  The three principal areas include the 1950s Mine and Mill Area, the 19th Century Operations Area and a Main Tailings Impoundment.  This Action memo recommends response actions to address threats from the main tailings impoundment.

The 1950's Mine and Mill Area comprises 15 acres and is located northwest of the intersection of Ore Knob Road and Little Peak Creek Road, just north of Highway 88.  This area contains derelict ore bins, concrete mill foundations, a transformer building, other ruins, a small sawmill currently in operation, two acres with about 10,000 cubic yards of tailings - now mostly covered with stumps, and a two acre former pond where process water was stored.  Little Peak Creek starts just upstream of the former pond, flows through the former pond, and discharges into Peak Creek 2.5 miles downstream.  

The 19th Century Operations Area and the Main Tailings Impoundment are located across Little Peak Creek Road, at the end of Ore Knob Mine Road.  The 19th Century Operations Area includes a series of barren and nearly barren stretches of land (totaling about 5 acres) near the top of Ore Knob that contain waste rock dumps from at least 11 mine shafts as well as locations where ore was roasted to drive off sulfur and smelted to recover copper.


Current Activities
EPA's environmental contractor continues to remove sludge from the sediment pond and deposit atop the tailings dam.  Approximately 1,000 cubic yards of sediment was excavated this week.  Site activities were suspended on 11/12/08 due to precipitation.  Work will resume Monday, November 17.  In order to prevent sludge from entering the tailings dam inlet pipe, a barrier of sawdust and topsoil was constructed around the sludge pile.

Planned Removal Actions
The crew will begin solidifying sludge upon remobilization to the site.  The defunct cement pipe in the sediment pond will be replaced.  A surveyor will be present to create a topo map of the Site as well as identify property boundaries.  

Next Steps
Construction plans for the diversion channel and dam face re-sloping will be completed within the next few weeks.  

Key Issues
A public meeting was held on Thursday, November 13th in Laurel Springs, NC.  Local residents inquired about the status of their drinking water.  Results of the sampling event conducted by the Remedial program were handed out.  The residents were advised to contact the EPA Remedial Project Manager (RPM) for more information about the sample results as it was outside the scope of ERRB's current removal activities.  

Representatives from a number of Divisions within North Carolina State government made a visit to the Site on Tuesday, November 12th.  among the issues discussed were the safety of the sediment pond dam, off-site sediment control, and off-site water quality.  EPA is currently working with the State in order to determine the most suitable method to minimize sediment run-off.