See Initial POLREP
- The Mill building is more than three-quarters apart and staged for decon. - General site clean up is a continuous effort.
- Demolition will continue as weather permits. - EPA will take over removal of the remainder of the Mill Pond (1200 cubic yards) & IDW in 50 55-gal drums.
- Decon & sample wood to be reused/recycled.
- Confirm decon of wood meets reuse/reycle criteria prior to leaving site.
|