2.1.1 Narrative
2.1.2 Response Actions to Date
11/2/09 to 11/13/09
Environmental Restoration, LLC. Emergency Rapid Response Services (ERRS) began identifying potential staffing, site security needs, safety work tasks, structural engineering support needs, vendors and obtaining cost proposals for equipment and other support services. The ERRS T&D Coordinator began review of analytical data to identify waste streams and vendors for procurement purposes.
11/16/09 to 11/27/09
On November 16, 2009, EPA OSC Hatzopoulos, ERRS, and Weston Solutions, Inc. Superfund Technical Assessment and Response Team III (START) contractor mobilized to the Site to begin the removal activities.
Equipment items delivered were an office, crew and decon trailers, two light towers, two generators, three porta-johns, long reach excavator, 60’ manlift. ERRS personnel cleared brush and debris outside the buildings to access work areas and began setting up and stabilizing inside building # 1 for asbestos work removal operations. The asbestos/ACM removal process shall include provisions for on-site decontamination of larger debris, and segregation of asbestos-free debris. Asbestos/ACM material will be documented, and shipped off site for disposal at EPA-approved facilities. All wastes will be staged in a secure area on-site while awaiting shipment to CERCLA compliant off-site disposal facilities.
ERRS also installed additional high visibility fencing to delineate further hot zones areas and removed loose brick and slate tiles from edge of perimeter along western edge of roof on double-gabled building.
A structural engineer performed exterior and interior inspection and assessment of the buildings.
Manned Site security began on November 16, 2009 and will continue to be on Site during the non-working hours throughout the duration of the removal action.
On November 17, 2009, OSC Hatzopoulos and the ERRS RM met with representatives from the City of Holyoke’s departments of public works, law, fire, building, gas and electric, and the conservation commission, to discuss the removal activities.
START photo documented the removal areas prior to the commencement of removal activities. START will also photodocument daily removal activities during the duration of the removal action. START also performed air monitoring, every day at five locations around the perimeter of the Site, to ensure that asbestos particulates were not escaping into the environment as a result of the removal activities. START will follow this protocol during the entire duration of the removal action.
Under the direction of the OSC, START personnel collected 54 debris samples from the standing buildings and foundation areas of the razed buildings. They were delivered to the EPA Office of Environmental Measurement and Evaluation (OEME) for asbestos analysis via Polarized Light Microscopy (PLM).
On November 23, 2009, EPA OSC Hatzopoulos, and EPA Public Affairs personnel met with MassDEP and representatives from the City of Holyoke’s departments of public works, law, fire, building, gas and electric, and the conservation commission, to discuss removal activities.
On November 25, 2009, all personnel demobilized for the Thanksgiving holiday.
11/30/09 to 12/11/09
ERRS continued securing and stabilizing areas at interior and exterior of the buildings. ERRS beging asbestos removal activities in Building 1. A temporary ramp was built at the north end of Building No. 1, so that there is direct access to the second floor. All loose ACM and debris was collected off the 2nd floor of Building No. 1 and double bagged. Asbestos removal continued on the 2nd floor of Building No. 1. The entire eastern wall of pipe installation was removed. Personnel air monitoring continued for asbestos analysis as well as perimeter monitoring. Between Buildings No. 2 and 3, work began to prep a staging area for large debris that needs to be removed to gain access to the asbestos.
Personnel air monitoring was conducted for lead and asbestos analysis. Perimeter asbestos air sampling was conducted during asbestos abatement activities.
Under the direction of the OSC, START personnel collected two additional ACM samples from insulation around an oven located on the second floor inside Building No. 3 and were delivered to OEME for asbestos PLM analysis.
On December 1, 2009, EPA OSC Hatzopoulos, EPA Branch Chief Art Johnson, and EPA Public Affairs personnel met with the City of Holyoke’s current and incoming Mayors including representatives from the departments of public works, law, fire, building, gas and electric, and the conservation commission, to discuss removal activities.
On December 8, 2009, EPA Health and Safety Officer mobilized to the Site to conduct a site health and safety inspection. A temporary construction fence was built on the eastern side of Building No. 4 per the Health and Safety Officer’s request.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|