2.1.1 Narrative
See previous POLREPs
2.1.2 Response Actions to Date
See previous POLREPs for past actions.
Monday, October 18, 2010, ERRS continued filling the interior pits from bins of off-spec non-friable asbestos containing brake parts stored around the facility. ERRS completed filling the east pit with non-friable asbestos brake parts, and began to fill the west pit. Empty steel bins were decontaminated, crushed, and staged for later off site recycling. One load of scrap steel transported off site for recycling. START continued air sampling and dust monitoring.
Tuesday, October 19, ERRS continued filling the west pit with off-spec non-friable asbestos containing brake parts stored around the facility. ERRS continued decontaminating, crushing, and loading scrap steel for recycling. Three beaver dams were removed from the creek along the south perimeter of the Site to prevent the Site from flooding in the event of heavy rain. Representatives from Ohio EPA were on Site to observe removal activities. Roll-off boxes for non-friable ACM began arriving on Site. Three (3) loads of scrap steel transported off site for recycling. The site owner transported one (1) truck load (20 bins) of non-asbestos brake parts off site. START continued air sampling and dust monitoring.
Wednesday, October 20, ERRS began removing non-friable brake parts from the brake-part disposal area on the west side of the Site and placing the brake parts into the west pit inside the building. ERRS began lining and loading roll-off boxes with non-friable ACM brake parts from the southeast portion of the Site. Two (2) loads of scrap steel were transported off site for recycling. The site owner transported two truck loads (35 bins of non-asbestos brake parts, 2 tanks and a set of steel stairs) off site for recycling. START continued air sampling and dust monitoring.
Thursday, October 21, ERRS continued removal activities from previous day. Four (4) roll-off boxes of non-friable asbestos brake parts were transported off site for disposal. START continued air sampling and dust monitoring.
Friday, October 22, ERRS ERRS continued removal activities from previous day. ERRS began to assemble the vacuum trailer (Hurricane). Four (4) roll-off boxes of non-friable asbestos brake parts were transported off site for disposal. Two (2) loads of scrap steel were transported off site for recycling. START continued air sampling and dust monitoring and began collecting bulk samples from some of the containerized material inside the building.
Monday, October 25, ERRS continued excavating non-friable asbestos brake parts from the disposal area on the west and southeast areas of the Site. The non-friable brake parts were placed into roll-off boxes for offsite disposal. ERRS continued staging containers of material inside the southwest portion of the building. Scrap steel within the building was decontaminated, crushed, and staged for later off site recycling. Representatives from the Ohio EPA were on site to observe removal activities. START continued air sampling and dust monitoring and continued the assessment of the interior of the building. Twelve (12) roll-off boxes of non-friable asbestos brake parts transported off site for disposal. One (1) roll-off box of solid waste transported off site for disposal.
Tuesday, October 26, ERRS continued removal activities fom previous day. Orange snow fence and asbestos signs were installed over the backfilled non-friable ACM waste in the two pits inside the building. ERRS began the removal of asbestos contaminated bag house dust from Trailer #2 on the southeast portion of the Site. Nine (9) roll-off boxes of non-friable ACM brake parts were transported off site for disposal. START continued air sampling and dust monitoring activities.
Wednesday, October 27, ERRS continued removal activities from previous day. Representatives from Ohio EPA were on Site to observe removal activities. Other ERRS activities included cleaning-out of the Hurricane vacuum unit. Eight (8) roll-off boxes of non-friable ACM brake parts were transported off site for disposal. One (1) roll-off box of friable ACM was transported off site for disposal. START continued air sampling and dust monitoring.
Thursday, October 28, ERRS activities the same as previous day. Seven (7) roll-off boxes of non-friable ACM brake parts were transported off site for disposal. Two (2) roll-off boxes of friable ACM were transported off site for disposal. One roll-off of solid waste was transported off site for disposal. START continued air sampling and dust monitoring.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See POLREP 1
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| Oil/Water |
Liquid |
32,600 gallons |
NA |
Fuel Blending |
Clean Water, Limited, dayton, Ohio |
| Scrap |
Solid |
17.42 tons |
NA |
Recycling |
Brookman Iron & Metals Co., Washington, PA |
| Asbestos |
Solid |
401.07 tons (as of 10/27/2010) |
A071541
A071542
A071543
A071550
A071545
A071547
A071546
A071544
A071551
A071549
A071554
A071555
A071557
A071558
A071556
A071643
A071552
A071553
A071650
A071649
A071646
A071761
A071648
A071647
A071759
A071644
A071645
A071758
A071760
A071559
A071560
A071561
A071563
A071762
A071562
A071565
A071564
|
Land Disposal |
Imperial Landfill, Imperial, PA |
| Solid Waste |
Solid |
4.56 tons (as of 10/27/2010) |
NA |
Land Disposal |
Short Creek Landfill, Wheeling, WV |
|