1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
10KL |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
4/27/2011 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
4/18/2011 |
|
Start Date: |
4/18/2011 |
|
Demob Date: |
4/20/2011 |
|
Completion Date: |
4/20/2011 |
|
CERCLIS ID: |
pending |
|
RCRIS ID: |
none |
|
ERNS No.: |
none |
|
State Notification: |
4/15/2011 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Removal Evaluation and Removal Action
1.1.2 Site Description
Two pits and a large disposal area on agricultural land currently being farmed for concord grapes.
1.1.2.1 Location
37704 North District Line Road, Prosser, WA 99350, Benton County
1.1.2.2 Description of Threat
Heat produced by the decomposing piles in excess of 1000 degrees F. Unrestricted access has led to several people walking into the piles and being severely burned.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Heat readings in several areas were measured to be in excess of 1000F, accompanied by smoldering humous material. Removal Evaluation results for SVOC, pesticides, herbicides and metals show exceedances of RSLs only for arsenic and vanadium. No MTCA exceedances. Background levels for arsenic and vanadium were higher than the concentrations in the waste samples.
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
2.1.2 Response Actions to Date
Fire breaks 12 feet wide were bull-dozed around both pits. Fencing on site was moved to the outer perimeter of the fire break and additional fencing was purchased and installed to completely exclude people from entering the dangerous areas.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
*Enforcement Confidential*
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| D001 |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
Land owner intends to cool and spread the waste on-site with state oversight.
2.2.2 Issues
At the time of the removal action it was not clear if the waste material would be considered a RCRA hazardous waste. On 4/25/2011, EPA made the determination that it would be classified as a RCRA ignitable D001 waste, making it a CERCLA hazardous substance.
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
START and ERRS costs are being split between Removal Assessment and Removal Action funding.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$10,000.00 |
$0.00 |
$10,000.00 |
100.00% |
| TAT/START |
$10,000.00 |
$0.00 |
$10,000.00 |
100.00% |
|
Intramural Costs
|
| |
| Total Site Costs |
$20,000.00 |
$0.00 |
$20,000.00 |
100.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer START Mark Woodke was designated as Site Safety Office during Field work. HASPS were prepared by START, ERRS and EPA.
2.6 Liaison Officer
2.7 Information Officer
2.7.1 Public Information Officer
2.7.2 Community Involvement Coordinator
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
3.2 Cooperating Agencies Representatives of the Washington State Department of Ecology Hazardous Waste and Toxics Reduction Program were on-site during field activities.
|
|
4. Personnel On Site
|
|
|
4 ERRS, 2 START, FOSC, EPA staff, 2 WDOE staff, Benton-Franklin Health District, and the landowner were on-site during field work.
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #1 Last Updated 11/10/2011
|