U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Holcomb Creosote - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV
|
|
Subject:
|
POLREP #5
Progress
Holcomb Creosote
B4E6
Yadkinville, NC
Latitude: 36.1622924 Longitude: -80.6771124
|
|
To:
|
Jim McGuire, USEPA R4 ERRB
|
|
From:
|
Karen Buerki, OSC
|
|
Date:
|
7/14/2011
|
|
Reporting Period:
|
4/22/2011 - 5/31/2011
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
B4E6 |
|
Contract Number: |
EP-S4-07-04 |
|
D.O. Number: |
117 |
|
Action Memo Date: |
3/17/2011 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
1/20/2011 |
|
Start Date: |
1/21/2011 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
NCD024900987 |
|
RCRIS ID: |
|
|
ERNS No.: |
965285 |
|
State Notification: |
1/20/2011 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
The site was demobilized on May 26, 2011, through May 31, 2011, for the Memorial Day Holiday.
2.1.2 Response Actions to Date
ERRS continued to remove creosote lumber, debris, and scrap metal and stage separately. Seven loads of debris were removed from the site. Five loads of scrap metal were removed from the site by the PRP during this reporting period. Sorbent boom, strung across the creek to capture sheen, was changed out as it became saturated.
Stabilization of the creosote sludge that had been staged in the containment area was completed. Soil in the containment area was excavated and handled as F034 waste due to failure of the containment lining. Drip pad soil was mixed with creosote sludge to achieve a 50% soil mixture required by disposal facilities. Resulting F034 soil is being staged under the 80' X 50' metal building.
Decommissioning of the creosote plant was completed. Additional ACM was discovered in the form of fire bricks in the boiler and gaskets. These materials were wetted, double-bagged and labeled for disposal which took place on May 20, 2011. Process piping and equipment is being deconned for scrap. The septic tank was discovered during removal of the vacuum tower. The boom truck broke through the lid. An oily layer was discovered floating in the septic tank. The contents of the septic tank were treated with 27% hydrogen peroxide and samples were taken for fecal coliform.
Excavation continued on the northern end of the property. Disposal of PAH-contaminated soil began on
May16, 2011. Eighty-four loads were taken to Republic's Foothills Landfill in Lenoir, NC.
Tank removal began May 16, 2011. Diesel tanks T5 and T8 and the evaporator tank T7 were emptied into totes. The tanks were cut and deconned for scrap. Creosote sludge had built up around the heating coils of the evaporator tank, which were also deconned for scrap.
The process water well was rendered safe with a concrete cap. Used tires were taken to Foothills Landfill and batteries (lead acid, lithium, NiCad, carbon zinc, and alkali) were removed for recycling.
The dilapidated barbed-wire/creosote post fence partially remaining around the RCRA landfarm was removed and a new fence, gate, and bilingual signage were installed.
Drummed waste disposal took place on May 23, 2011. Four drums of mercury-contaminated debris, one drum of elemental mercury and mercury-containing devices, four drums of HHW, and one drum of halogenated refrigerant oil were shipped for disposal or retort. One drum of used antifreeze was shipped for recycling on May 25, 2011.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The PRP is Holcomb Creosote Company. Access was granted verbally in a meeting at the Law Offices of
Lee Zachary on January 20, 2011. A formal access agreement was signed on May 23, 2011. The remaining assets of the company are tied up in real estate, rendering the company not viable to perform a Removal Action.
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| F034/K001 Sludge/Soil |
Solid |
est. 1500 tons |
|
|
|
| Asbestos/ACM |
Solid
Solid |
10 cy
1 cy |
4/21/11
5/20/11 |
Subtitle D Landfill |
Republic Services, Inc., Foothills Environmental Lenoir, NC |
| PAH Soil |
Solid |
1575 tons |
|
Subtitle D Landfill |
Republic Services, Inc., Foothills Environmental Lenoir, NC |
| F034 Debris |
Solid |
20 tons |
|
|
|
| Creosote |
Liquid |
14,100 gallons |
|
|
|
| Lab Pack/HHW |
Solid and Liquid |
4 Drums |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
| PPE/Debris/Creosote Lumber |
Solid |
310 cy |
155777, 155778, 155779, 155781,
155787, 155780,
155788, 155969,
411249, 411250 |
Subtitle D Landfill |
Republic Services, Inc. Foothills Environmental Lenoir, NC |
| Diesel |
Liquid |
730 gallons |
|
|
|
| Used Antifreeze |
Liquid |
55 gallons |
5/25/11 |
Recycle |
Shamrock
Browns Summit, NC |
| Mercury/Devices |
Liquid |
4 pounds |
001170331 |
Retort |
Environmental Enterprises, Inc. Atkins, VA |
| Mercury Debris/Soil |
Solid |
4 drums |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
| Refrigerant Oil - Halogenated |
Liquid |
1 drum |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
Remove visual contamination from the North lot and South lot, stockpile, dispose. Backfill and seed excavated areas.
Dispose of debris/trash/PPE.
Blend stabilized sludge with remaining F034 waste associated with the drip pad and process area (up to two feet). Place notification barrier in areas with contamination remaining at two feet. Dispose of stabilized F034 sludge.
Dispose of creosote and sludge remaining in the pressure vessel and two large tanks and scrap them.
Pump out and remove sludge from the three horizontal creosote tanks and scrap tanks.
Pump around and remove up to 6" sediment in approximately 400' of the creek and place a barrier to control creosote seeps.
Provide fencing and signage for the RCRA impoundment.
2.2.1.2 Next Steps
Continue to take down tanks, remove sludge, and scrap.
2.2.2 Issues
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
An emergency response was initiated under the OSC's warrant authority to stabilize the site. Task Order No. 117 was issued to Environmental Restoration, LLC, in the amount of $200,000 and TDD No. TTEMI-05-001-0145
was issued to Tetra Tech in the amount of $50,000.
A Ceiling Increase and Emergency Exemption Action Memo was signed on March 17, 2011. The new site ceiling is $3,530,000. The new ERRS ceiling is $2,440,000 and the new START ceiling is $500,000.
Totals reflect costs through May 31, 2011, and do not account for disposal of liquid creosote remaining in tanks and F034 sludge/debris.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - ER, LLC |
$1,450,000.00 |
$618,839.96 |
$831,160.04 |
57.32% |
| START - Tetra Tech |
$206,602.00 |
$139,291.93 |
$67,310.07 |
32.58% |
|
Intramural Costs
|
| |
| Total Site Costs |
$1,656,602.00 |
$758,131.89 |
$898,470.11 |
54.24% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
2.6 Liaison Officer
2.7 Information Officer
2.7.1 Public Information Officer
2.7.2 Community Involvement Coordinator
The Community Involvement Coordinator assigned to the site is Sherryl Carbonaro. Sherryl made a site visit the week of May 16, 2011, to get access agreements for RPM Carolyn Callihan's Site Inspection the week of May 23, 2011.
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
3.2 Cooperating Agencies NCDENR is providing support in the response.
|
|
4. Personnel On Site
|
|
|
1 EPA OSC
1 START
12 ERRS - 1 Project Manager, 1 Field Clerk, 1 Foreman, 1 Health and Safety Officer, 3 Equipment Operators, and 5 Technicians
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #5 Last Updated 9/1/2011
|
|
|