U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Holcomb Creosote - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV
|
|
Subject:
|
POLREP #6
Progress
Holcomb Creosote
B4E6
Yadkinville, NC
Latitude: 36.1622924 Longitude: -80.6771124
|
|
To:
|
Jim McGuire, USEPA R4 ERRB
|
|
From:
|
Karen Buerki, OSC
|
|
Date:
|
8/12/2011
|
|
Reporting Period:
|
5/31/11 - 7/5/11
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
B4E6 |
|
Contract Number: |
EP-S4-07-04 |
|
D.O. Number: |
117 |
|
Action Memo Date: |
3/17/2011 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
1/20/2011 |
|
Start Date: |
1/21/2011 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
NCD024900987 |
|
RCRIS ID: |
|
|
ERNS No.: |
965285 |
|
State Notification: |
1/20/2011 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
The site was demobilized on June 30, 2011, through July 5, 2011, for the Independence Day Holiday.
2.1.2 Response Actions to Date
ERRS continued to remove creosote lumber, debris, and scrap metal and stage separately. Two more loads of debris were removed from the site. Two more loads of scrap metal were removed from the site by the PRP during this reporting period. Sorbent boom, strung across the creek to capture sheen, continues to be changed out as it becomes saturated.
Excavation continued on the north and west sides of the site. Excavation also took place along the creek bank. Contaminated soil was also removed from around tree stumps left by the PRP's logging effort. An area along the north side of the warehouse that had been used by Holcomb Creosote to store gasoline was excavated. There was a strong gasoline odor present during excavation. Also, heavily-stained soil was observed extending under the warehouse. Disposal is pending award of an additional 2000 ton subcontract. Backfilling on the north end of the site began. The sloped areas were seeded and straw erosion matting was put in place.
Tank removal continued. Horizontal creosote tanks T1, T2, and T3 were pumped into totes and hoisted off of their saddle to cut. All of these tanks were found to be one-half to three-quarters full of sludge. The plates on all three tanks described them as underground storage tanks. Creosote work tank T6 and the pressure vessel were also pumped into totes. The pressure vessel was found to contain the drip pad rail and lumber carts. Creosote remaining in vertical tanks T4 and T6 as well as the creosote in the totes was recycled as boiler fuel. Tanks T4 and T6 also had sludge covering their heating coils. The tanks, pressure vessel, drip pad rail, carts, and heating coils were deconned and cut for scrap.
Drip pad soil and creosote-stained site soils are being mixed with creosote sludge recovered from storage tanks to achieve a 50% soil mixture required by disposal facilities. Resulting F034 soil is being staged under the 80' X 50' metal building.
ERRS began preparing F034 debris for disposal (less than 3', no free liquids, no protruding rebar).
The broken septic tank and drain field line was removed.
Tetra Tech redeveloped and sampled all of the monitoring wells.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The PRP is Holcomb Creosote Company. Access was granted verbally in a meeting at the Law Offices of
Lee Zachary on January 20, 2011. A formal access agreement was signed on May 23, 2011. The remaining assets of the company are tied up in real estate, rendering the company not viable to perform a Removal Action.
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| F034/K001 Sludge/Soil |
Solid |
est. 1500 tons |
|
|
|
| Asbestos/ACM |
Solid
Solid |
10 cy
1 cy |
4/21/11
5/20/11 |
Subtitle D Landfill |
Republic Services, Inc., Foothills Environmental Lenoir, NC |
| PAH Soil |
Solid |
1575 tons |
|
Subtitle D Landfill |
Republic Services, Inc., Foothills Environmental Lenoir, NC |
| F034 Debris |
Solid |
est.100 tons |
|
|
|
| Creosote |
Liquid |
8100 gallons |
145582, 145583 |
Boiler Fuel |
Giant Cement Company, Harleyville, SC 29448 |
| Lab Pack/HHW |
Solid and Liquid |
4 Drums |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
| PPE/Debris/Creosote Lumber |
Solid |
310 cy |
155777, 155778, 155779, 155781,
155787, 155780,
155788, 155969,
411249, 411250 |
Subtitle D Landfill |
Republic Services, Inc. Foothills Environmental Lenoir, NC |
| Diesel |
Liquid |
730 gallons |
|
Boiler Fuel |
Giant Cement Company, Harleyville, SC 29448 |
| Used Antifreeze |
Liquid |
55 gallons |
5/25/11 |
Recycle |
Shamrock
Browns Summit, NC |
| Mercury/Devices |
Liquid |
4 pounds |
001170331 |
Retort |
Environmental Enterprises, Inc. Atkins, VA |
| Mercury Debris/Soil |
Solid |
4 drums |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
| Refrigerant Oil - Halogenated |
Liquid |
1 drum |
001170331 |
|
Environmental Enterprises, Inc. Atkins, VA |
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
Remove visual contamination from the North lot and South lot, stockpile, dispose. Backfill and seed excavated areas. Dispose of debris/trash/PPE.
Stabilize creosote sludge with remaining F034 waste associated with the drip pad and process area (up to two feet). Place notification barrier in areas with contamination remaining at two feet. Dispose of stabilized F034 sludge.
Prepare and dispose of F034 debris including the concrete pit.
Pump around and remove up to 6" sediment in approximately 400' of the creek and place a barrier to control creosote seeps.
Provide fencing and signage for the RCRA impoundment.
2.2.1.2 Next Steps
Dispose of F034 soil and debris.
2.2.2 Issues
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
An emergency response was initiated under the OSC's warrant authority to stabilize the site. Task Order No. 117 was issued to Environmental Restoration, LLC, in the amount of $200,000 and TDD No. TTEMI-05-001-0145
was issued to Tetra Tech in the amount of $50,000.
A Ceiling Increase and Emergency Exemption Action Memo was signed on March 17, 2011. The new site ceiling is $3,530,000. The new ERRS ceiling is $2,440,000 and the new START ceiling is $500,000.
Totals reflect costs through July 5, 2011, and do not account for disposal of all of the contaminated soil or the F034 sludge/debris.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - ER, LLC |
$2,450,000.00 |
$856,240.35 |
$1,593,759.65 |
65.05% |
| START - Tetra Tech |
$335,764.00 |
$185,545.05 |
$150,218.95 |
44.74% |
|
Intramural Costs
|
| |
| Total Site Costs |
$2,785,764.00 |
$1,041,785.40 |
$1,743,978.60 |
62.60% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
2.6 Liaison Officer
2.7 Information Officer
2.7.1 Public Information Officer
2.7.2 Community Involvement Coordinator
The Community Involvement Coordinator assigned to the site is Sherryl Carbonaro.
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
3.2 Cooperating Agencies NCDENR visited the site on June 28, 2011.
|
|
4. Personnel On Site
|
|
|
1 EPA OSC
1 START
8/9 ERRS - 1 Project Manager, 1 Field Clerk, 2/3 Equipment Operators, and 4/5 Technicians
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #6 Last Updated 9/1/2011
|
|
|