2.1.1 Narrative
2.1.2 Response Actions to Date
WR Grace provided EPA, with a removal action plan for conduct of the clean-up. Upon review and approval of the plan and based on the analytical, excavation occured at three separate areas at the Site.
During the reporting period the following occurred (OSC Stilman, OSC Harper and START conducting oversite):
Concrete Pad activities:
From 7/8/11 until 7/12/11, JBR Environmental Services continued removal activities on and in the vicinity of the concrete pad that formerly housed the silos. Additional activities included:
- Use of vacuum truck and brooms to remove visible vermiculite and clean the concrete pad. Areas addressed included the concrete pad as well as the adjacent shallow trench that was excavated along the eastern edge of the pad (between the pad and the walking path).
- A total of 5 rolloff containers (total of approximately 50 cubic yards) and 1 vacuum truck (estimated 3 to 5 cubic yards) were generated during pad cleaning activities and were shipped offsite for disposal.
On 7/13/11, Rogers & Callcott conducted ABS air sampling (walking scenario) on the concrete pad using 3 personnel (each with a 3 liter per minute pump and a 10 liter per minute pump). Walking activities were conducted with sampling pumps running for a total of 60 minutes.
Backfill and Restoration Activities:
On 7/19/11, JBR personnel returned to the site to backfill, seed, and hay the areas of excavation. Areas addressed during these activities include the excavations at N300 and S250 (former sampling locations) as well as the shallow trench that was excavated along the eastern edge of the concrete pad (between the pad and the recreational path). Each area was backfilled with material that was previously cleared via sampling by Rogers & Callcott personnel (laboratory analytical for BTEX, PAHs, lead and PCBs). Prior to demobilizing, JBR personnel also removed the high-visibility fencing from along both sides of the recreational path.
Site-Specific Action Levels and Clean-up Goals:
The removal action level and clean-up goal for the Vermiculite Exfoliation Site GAO 150 are listed below. The clean-up goal was based on a college student scenario, which was the most conservative exposure scenario evaluated by EPA.
Action Level: 0.25% Libby amphibole asbestos
Clean-up Goal: 0.02 fibers/cubic centimeter (f/cc), for ABS
Conformation Bulk Sampling:
On 7/6/11 and 7/7/11 during the removal action, thirteen conformation bulk soil samples were collected by Rogers and Callcott. Four samples were collected from the northern excavation at N300, four samples were collected from the southern excavation at S250 and five samples were collected from the around the silo pad. All analytical results reported were below the site-specific action limit of 0.25% asbestos. The analytical results for the four samples at S250 were all reported as no asbestos detected, two samples at N300 were less than 0.25% asbestos and two were reported as no asbestos detected. Two samples collected adjacent to the silo concrete pad were reported as no asbestos detected and the other three sample adjacent to the silo concrete pad were reported as less than 0.25% asbestos.
Conformation Air Sampling:
On 7/7/11 and 7/13/11 during the removal action, thirteen conformation air samples were collected by Rogers and Callcott, nine ABS air samples and four background air samples. Of the nine ABS, three were collected in the excavation at S250, three in the excavation at N300 and three in the area of the silo pad. All air samples results reported were below the site-specific clean-up goal of 0.02 fiber per cubic centimeter (f/cc). The four background air samples results were reported less than detection limits of 0.001 structure per cubic centimeter (S/cc). Six of the nine ABS air samples reported results were less than 0.001 S/cc the remaining three ABS reported detectable levels of asbestos, S250 5 at 0.004 S/cc, Silo Pad 15 at 0.012 S/cc and Silo Pad 19 at 0.01 S/cc.
EPA co-located one ABS air sample with Rogers and Callcott ABS at the Silo Pad location. The co-located sample was to confirm WR Graces sample results. EPA sample GAO150-TT-AH-01 was collected by START and analyzed by a contract laboratory program (CLP) laboratory. The result was reported as no structures detected.
Final Site Visit:
On 9/14/2011, OSC Stilman and OSC Harper conducted a final site visit. The entire length of the Swamp Rabbit Trail located on the site had been graded, gravel placed on the trail, the trail was paved with asphalt and both sides of the trail have been graded smooth to the existing landscape.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
W R Grace is the present owner of the property and the former operator of the facility and conducted the action under EPA oversite.
2.1.4 Progress Metrics
<><><><><><><><> >
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Asbestos Contamination |
Soil |
110 CuY |
|
|
Landfill |
|
|
|
|
|
|
|
|
|
|
|
|
|