|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
10KL |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
4/27/2011 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
10/17/2011 |
|
Start Date: |
4/18/2011 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
WAN001002932 |
|
RCRIS ID: |
none |
|
ERNS No.: |
none |
|
State Notification: |
4/15/2011 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Removal Action
1.1.2 Site Description
Two pits and a large disposal area of fruit pomace and diatomaceous earth waste on agricultural land currently being farmed for concord grapes.
1.1.2.1 Location
36108 North District Line Road, Prosser, WA 99350, Benton County
1.1.2.2 Description of Threat
Heat produced by the decomposing piles in excess of 1000 degrees F. Unrestricted access has led to several people walking into the piles and being severely burned.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Heat readings in several areas were measured to be in excess of 1000F, accompanied by smoldering humous material. Removal Evaluation results for SVOC, pesticides, herbicides and metals show exceedances of RSLs only for arsenic and vanadium. No MTCA exceedances. Background levels for arsenic and vanadium were higher than the concentrations in the waste samples.
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
2.1.2 Response Actions to Date
On 10/4/2011 PRP contractor reinforced the fencing.
EPA and ERRS mobed to site on Monday 10/17/2011 - 6 ERRS, 1OSC. Set up office trailer and started filling water tower. Received heavy equipment - excavator, wheel loader, D6 Dozer, two 10 cy haul trucks.
Tuesday 10/18/2011 - 6 ERRS, 1OSC. 7am safety meeting. Pushed apple trees into three piles for burning. Started excavating Pit #1 in afternoon. Hauled and spread waste material on southwest corner of site. Three PRP experts arrived to observe excavating and collect soil samples and temperature measurements. Unarmed security hired to prevent trespassers from entering open pits and to protect equipment.
Wednesday 10/19/2011 - 6 ERRS, 1OSC. 7am safety meeting. Continued excavating Pit #1. Hauled and spread waste material on northeast corner of site. Three PRP experts on-site to observe excavating and collect soil samples and temperature measurements. Replaced haul trucks with 20 cy articulated trucks.
Thursday 10/20/2011 - 6 ERRS, 1OSC. 7am safety meeting. Continued excavating Pit #1. Hauled and spread waste material on southeast and northwest corners of site. Two PRP experts on-site to observe excavating and collect soil samples and temperature measurements
Friday 10/21/2011 - 6 ERRS, 1OSC. 7am safety meeting. Started excavating Pit #2. Spread hot material in front of the pit, watered and mixed it until it was not hot to the touch. The burn ban was lifted so the landowner torched the three piles of apple wood, which burned down by noon. Copy of burn permit provided to OSC. Two PRP experts on-site to observe excavating and collect soil samples and temperature measurements.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
*Enforcement Confidential*
2.1.4 Progress Metrics
All waste material will be land-applied on-site.
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| D001 |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
2.2.2 Issues
More waste material is present than expected. Also, more Diatomaceous Earth is present in the waste than expected. Applying the excess to the current site footprint may make the land unusable for the landowner’s intended purpose (planting grapes). EPA will investigate the cost of off-site disposal of the excess waste material vs adding organic amendment to the site soil to off-set a higher application rate of the inorganic component of the waste material.
A large quantity of non-hazardous solid waste (household garbage such as toys and beds and indsutrial waste such as tires and machine parts) has been found mixed into the waste in both pits. ERRS crew is separating out the solid waste at each stage of handling. Tires, large rocks, and moderately hazardous household waste (herbicide containers) will be left on-site for proper disposal by the land-owner. Other debris will be removed with site trash.
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
$5,656 ERRS costs from April 2011 removal work will count toward the action memo ceiling. This amount is not reflected in the ERRS costs through COB 10/21/2011 of $108,866 (including pending.)
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$10,000.00 |
$0.00 |
$10,000.00 |
100.00% |
| TAT/START |
$10,000.00 |
$0.00 |
$10,000.00 |
100.00% |
|
Intramural Costs
|
| |
| Total Site Costs |
$20,000.00 |
$0.00 |
$20,000.00 |
100.00% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
ERRS RM Brad Coury was designated as Site Safety Office during Field work. HASP wa prepared by ERRS
2.6 Liaison Officer
2.7 Information Officer
2.7.1 Public Information Officer - Mark Macintyre
2.7.2 Community Involvement Coordinator
|
|
3. Participating Entities
|
|
|
No information available at this time.
|
|
4. Personnel On Site
|
|
|
6 ERRS, FOSC, 4 total PRP experts, and the landowners were on-site during field work.
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
6.1 Internet location of additional information/report
www.epaosc.org/prosserpomacepits
6.2 Reporting Schedule
weekly
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #2 Last Updated 10/22/2011
|