U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

City Service Valcon

All POL/SITREP's for this site City Service Valcon
Powell, ID - EPA Region X
POLREP #2
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
City Service Valcon - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region X

Subject: POLREP #2
Progress
City Service Valcon

Powell, ID
Latitude: 46.4107600 Longitude: -115.1795400


To:
From: Earl Liverman, On-Scene Coordinator
Date: 12/19/2011
Reporting Period: 11/21/11 - 11/22/11

1. Introduction
  1.1 Background
   
Site Number:      Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: OPA    Response Type: Emergency
Response Lead: EPA    Incident Category: Removal Action
NPL Status:    Operable Unit:
Mobilization Date: 11/21/2011    Start Date: 11/21/2011
Demob Date: 11/22/2011    Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification: 11/12/2011
FPN#: E12002    Reimbursable Account #:

1.1.1 Incident Category

EPA emergency response to a transportation incident involving discharge of gasoline.


1.1.2 Site Description

Refer to Initial POLREP.

1.1.2.1 Location

Refer to Initial POLREP.

1.1.2.2 Description of Threat

The Potentially Responsible Party’s (PRP) contractor West Central Environmental Consultants (WCEC) prepared a preliminary mass balance reconciliation for the amount of spilled gasoline, recovered gasoline, and residual gasoline remaining on-site.   The estimated quantity of gasoline spilled during the incident was 1,169 gallons, based on product inventory from before and after the incident.  Of the 1,169 gallons lost, WCEC recovered an estimated 159 gallons in sorbent materials during the emergency response, based on weight of the saturated absorbents less the weight of unsaturated materials.  Additionally, the excavation removed an estimated 150 to 170 gallons based on disposal sample analytical data, residual soil concentration data, and field instrument observations from the disposal samples.  Thus, an estimated 850 gallons of gasoline remains on-site.

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

Refer to Initial POLREP.

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative

2.1.2 Response Actions to Date

An Initial Cleanup Action and Investigation Work Plan was approved on 17 November 2011; however, the removal action was not implemented until the week of 21 November 2011 due to inclement weather.

 

From 21 November through 22 November 2011, WCEC excavated approximately 184 cubic yards of PCS, including shot rock, road shoulder fill, and unconsolidated alluvium from the upslope ditch of U.S. Highway 12.  Excavation occurred over a distance of about 127 feet, and the width and depth of excavation below ground surface varied from 6 to 12 feet and 4 to 9 feet, respectively.  The excavation was backfilled with clean material.  The width and depth of excavation was limited due to the occurrence of shallow bedrock, close proximity of loose rocks along a steep cliff, and roadway stability concerns.  The PCS was transported to a nearby landfarm facility for treatment.

 

Fifteen soil samples were collected from the excavation – 10 discrete sidewall samples and 5 discrete bottom samples.  Four composite soil samples were also collected from the excavated material for use in quantifying the contaminant mass removed through excavation.  Soils from the immediate release area exhibited strong gasoline impacts with photoionization detector (PID) readings approaching 2,000 parts per million (ppm).  PID readings from the sidewalls and the bottom of the excavation ranged from 0 to 26 ppm.  An estimate of residual soil concentrations will be made following receipt of laboratory analytical results.

 

Three surface water samples were collected on 21 November 2011.  Preliminary data shows non-detect for the contaminants of concern.  The absorbent boom was removed from the Lochsa River on 22 November 2011 following the completion of all excavation activities.  The boom did not contain any gasoline constituents, product, staining, or sheen.


2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

Refer to Initial POLREP.

2.1.4 Progress Metrics

Waste Stream Medium Quantity Manifest # Treatment Disposal
Gasoline   Soil  184 cubic yards    Landfarm
           
           


  2.2 Planning Section
    2.2.1 Anticipated Activities

Continued weekly monitoring of the Lochsa River bank for evidence of a release to the river.

2.2.1.1 Planned Response Activities

The need fpor additional cleanup actions will be based on the soil and surface water analytical resulkts, river bank monitoring, and other practical considerations.

2.2.1.2 Next Steps

Refer to Sections 2.2.1 and 2.2.1.1.

2.2.2 Issues

None.

  2.3 Logistics Section
   
N/A

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

N/A

2.5.2 Liaison Officer

N/A

2.5.3 Information Officer

N/A

3. Participating Entities
  3.1 Unified Command

N/A

3.2 Cooperating Agencies

N/A

4. Personnel On Site
 
N/A

5. Definition of Terms
 
N/A

6. Additional sources of information
  6.1 Internet location of additional information/report

N/A

6.2 Reporting Schedule

Periodic POLREPS will be prepared.

7. Situational Reference Materials
 
N/A