U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Big River Mine - Lake Timberline Area - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VII
|
|
Subject:
|
POLREP #11
Site Progress Report
Big River Mine - Lake Timberline Area
07CRRV01
Bonne Terre, MO
Latitude: 37.9901241 Longitude: -90.5357385
|
|
To:
|
Scott Hayes, EPA
|
|
From:
|
Jeff Weatherford, OSC
|
|
Date:
|
10/3/2012
|
|
Reporting Period:
|
8/17/2012 to 9/17/2012
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
07CRRV01 |
|
Contract Number: |
EP-R7-07-12 |
|
D.O. Number: |
0086 |
|
Action Memo Date: |
9/24/2010 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
NPL |
|
Operable Unit: |
OU1 |
|
Mobilization Date: |
12/22/2010 |
|
Start Date: |
12/22/2010 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
MOD981126899 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
|
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-Critical Removal Action
1.1.2 Site Description
The Big River Mine - Lake Timberline Area is an on-going time-critical removal action at the Central Middle School Sub-Site (Site) and consists of high concentrations of lead contamination from mining and the use of mine waste as construction materials. The primary problem areas at this Site, which require action, are lead-contaminated soils in yards and gravel in driveways.
1.1.2.1 Location
The Site is located in northern St. Francois County and is a stand-alone lake development community north of the city of Bonne Terre and south of Valle Mines, Missouri.
1.1.2.2 Description of Threat
According to the Incidents of Mines, Occurrences and Prospects (IMOP) database created by the state of Missouri, there was only limited mining within the current boundaries of Lake Timberline. However, the Mississippi River and Bonne Terre Railway (MR&BTR) runs through the development. This railway (now abandoned) is comprised of mine waste (chat, tailings, smelter slag, etc.) based on visual observations and sample results. Three lakes within the development are adjacent to and receive storm-water runoff from the MR&BTR. In addition, based on documented conversations with some Lake Timberline residents, it appears lead-contaminated soil and gravel has been brought in from the surrounding areas. The soil was used as fill and the gravel was used for driveways throughout the community.
Elevated concentrations, greater than 400 parts per million (ppm), of lead have been found throughout the Site. Children playing in and around the contaminated areas have the highest potential to be exposed.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
In September 2005, the U.S. Environmental Protection Agency conducted screening of a portion of the MR&BTR, which runs through the development along with soil from a nearby playground and sediment from Kiddie Lake. The screening was conducted with an X-Ray Florescence Spectrometer (XRF) and the results detected lead contamination in the pond sediments at levels ranging from 1,383 to 2,793 ppm, results from soil screened in the park ranged from 213 to 3,390 ppm, and results from screening of the abandoned railroad ballast ranged from 646 to 2,080 ppm.
In March 2010, the EPA began a removal assessment which included soil and groundwater sampling in the Lake Timberline area. During this sampling event, the EPA contractors screened the soil at 362 residences and sampled 226 private drinking water wells. The results of this sampling effort revealed the following information:
Properties with Soil Levels greater than 400 ppm lead………….……209
Properties with Soil Levels greater than 1,200 ppm lead ….. ………104
Drinking Water Wells Exceeding 15 parts per billion lead…… ….. None
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
During this reporting period crews have completed excavation of contaminated soil at 7 properties. The site crew was reduced in size due to a reduction in site funding. Thus, property excavations will continue at a slower pace.
2.1.2 Response Actions to Date
To date, crews have completed excavation of contaminated soil at a total of 163 properties.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| Lead |
Soil |
36,164 Cubic Yards |
|
|
Re-Use |
| |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
Property excavations will continue at a reduced rate due to the decrease in site funding.
2.2.1.1 Planned Response Activities
The START contractor will continue sampling residential properties and child high use areas in the Lake Timberline area, weather and funding permitted. The ERRS contractor will continue excavation of contaminated properties.
2.2.1.2 Next Steps
Continue sampling, excavation, and report additional findings.
2.2.2 Issues
None identified to date.
|
|
|
2.3 Logistics Section
|
|
|
|
All logistics are being conducted by the EPA contractors.
|
|
|
2.4 Finance Section
|
|
|
|
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$4,128,489.00 |
$3,519,146.53 |
$609,342.47 |
14.76% |
| TAT/START |
$632,179.00 |
$504,053.57 |
$128,125.43 |
20.27% |
|
Intramural Costs
|
| |
| Total Site Costs |
$4,760,668.00 |
$4,023,200.10 |
$737,467.90 |
15.49% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
SO functions are being conducted by the EPA contractors.
2.6 Liaison Officer
LO functions are being conducted by the OSC.
2.7 Information Officer
2.7.1 Public Information Officer
There is no need for a PIO at this time.
2.7.2 Community Involvement Coordinator
The OSC and CIC are coordinating with private and public community leaders as needed.
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
n/a
3.2 Cooperating Agencies
MDNR
MDHSS
|
|
4. Personnel On Site
|
|
|
EPA
START
ERRS
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
6.1 Internet location of additional information/report
http://www.epaosc.org/
6.2 Reporting Schedule
monthly
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #11 Last Updated 10/23/2012
|
|
|