1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
A6FW |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
|
Response Authority: |
CERCLA |
|
Response Type: |
Emergency |
Response Lead: |
PRP |
|
Incident Category: |
Removal Assessment |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
10/17/2012 |
|
Start Date: |
10/17/2012 |
Demob Date: |
10/18/2012 |
|
Completion Date: |
|
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
1027649 |
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Emergency Response
1.1.2 Site Description
At approximately 1930 on 17 October, 2012, a fire was discovered at the Conecsus warehouse at 304 Industrial Drive, Forney, Texas. Shortly thereafter, the Forney Fire Dept. was notified and responded to the fire. The warehouse is leased by Conecsus and contains refurbished drums, poly totes with a 25% Caustic Solution, and used baghouse filter bags from their baghouse fume that is part of their lead and tin recycling facility in Terrell, Texas. The chemical of concern is lead, and the Conecsus representatives stated that the bags are being temporarily stored until they can be recycled at their facility. The Kaufman County Emergency Manager also responded to the incident and notified the TCEQ, and the City of Dallas HAZMAT Team.
1.1.2.1 Location
304 Industrial Drive, Forney, Kaufman County, Texas
1.1.2.2 Description of Threat
Lead dust from baghouse filters.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Initial findings indicated dust/ash debris along building exterior walls along with fire water.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
2.1.2 Response Actions to Date
The EPA OSC Response Duty Officer and contractors were activated by the EPA Phone Duty Officer at approximately 2145 on 17 October, 2012. EPA OSC Adam Adams arrived onsite at approximately 2240. The NRC was notified (NRC # 1027649) at 2315 local time. The remaining EPA Team members arrived onsite at approximately 2350. The fire inside the storage facility was predominantly out by 0030 on 18 October 2012. In the process of fighting the fire, a hole was cut in the side of the building to allow for better access to the burning materials. A small amount of fire water runoff was produced and collected in the loading bay which is below gradient and at the front of the building, and some of the materials spread to the ground on the exterior of the building. TAS Environmental, Conecsus’ cleanup contractor arrived onsite at approximately 0100 on 18 October 2012, and conducted initial assessment activities. After discussing the remediation plan with Conecsus and TAS Environmental, the EPA Team departed the site at approximately 0140 on 18 October 2012.
Air monitoring conducted by EPA did not indicate any hazardous environments at the time of the air monitoring.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The Potentially Responsible Party at this time is Conecsus.
2.1.4 Progress Metrics
Waste volumes created and managed by the PRP have not been provided at the time of this POLREP.
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
Remediation actions will be conducted to protect workers, public health, and the environment from the release of hazardous substances.
2.2.1.1 Planned Response Activities
PRP remediation plan:
1.Pump or push any remaining firewater back into the building and allow to evaporate.
2. Excavate the surface of the ground around the exterior of the building approximately 3 to 6 inches to remove any surficial contamination, and collect soil samples for Total Lead Analysis.
3. Repair the hole in the building that was cut by the Fire Department
4. Wipe down all undamaged pallets in warehouse and transfer drums/totes/contents to a different warehouse for temporary storage.
5. Properly dispose of fire damaged materials.
6. Once warehouse is empty, warehouse will be cleaned and wipe samples for lead will be collected for confirmation.
Activities 1 -3 are of highest priority and are anticipated to be completed by end of day on 18 October 2012 to remove the threat of offsite migration due to rainfall events.
An EPA Team member will return to the site and observe and document activities by TAS Environmental conducted on 18 October 2012
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
3.1 Unified Command
Incident Command was provided by the Forney Fire Department.
3.2 Cooperating Agencies
Additional responding agencies include EPA and Kaufman County Emergency Management.
The PRP, Conecsus LLC, was onsite during the response as well, and assumed lead after the fire was secured and control of the Site was passed by Forney Fire Department.
|
4. Personnel On Site
|
|
Additional persons onsite include the local ambulance service.
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
Additional information can be obtained at www.epaosc.net/ConecsusFire.
6.2 Reporting Schedule
A final POLREP will be provided at the completion of response actions and analytical results have been provided by the PRP.
|
7. Situational Reference Materials
|
|
No information available at this time.
|