U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Sunoco Pipeline Woodville

All POL/SITREP's for this site Sunoco Pipeline Woodville
Woodville, TX - EPA Region VI
POLREP #2
Interim POLREP
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Sunoco Pipeline Woodville - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VI

Subject: POLREP #2
Interim POLREP
Sunoco Pipeline Woodville

Woodville, TX
Latitude: 30.9318800 Longitude: -94.5312200


To:
From: Mike McAteer, OSC
Date: 3/1/2013
Reporting Period: 2/26/13 to 2/28/13

1. Introduction
  1.1 Background
   
Site Number: FPN E13609    Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: OPA    Response Type: Emergency
Response Lead: PRP    Incident Category:
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 2/24/2013    Start Date: 2/24/2013
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#: E13609    Reimbursable Account #:

On February 24th, the NRC contacted the USEPA and informed them of an oil spill near Woodville, TX. OSC Mike McAteer was dispatched to the scene to determine the size and scope of the incident. NRC Report# 1039285 stated that the incident was discovered in Otter Creek on February 23rd at 1648 local incident time. Pipeline operator Sunoco had established a clean up contractor the evening that the spill was discovered to begin using boom and vacuum trucks for containment and recovery. Most recent estimates from Sunoco state that 550 bbl were released.

.

.

2. Current Activities
  2.1 Operations Section
    February 26 - 28th, Sunoco contractors continued to remove crude oil from the affected drainage ditch, Otter Creek, and Russell Creek. Cleanup methods employed by contractors include vacuuming and skimming, utilizing sorbent pads, booms, and snares to remove oil, and flushing of Otter Creek utilizing water from Russell Creek (upstream of Otter Creek confluence); proper permitting from TCEQ has been obtained for surface water extraction. Oiled sorbent pads, booms, snares, and debris are removed, placed in drum liners, put in roll-offs and secured for disposal. Total crude oil removed from the affected areas through February 28th is 105 bbls, and approximately six roll-offs filled with oiled debris bags

  2.2 Planning Section
    2.2.1 Anticipated Activities
Review and approve Sunoco's daily IAP and continue to observe creek conditions and progress of cleanup activities.

Sunoco engineers are calculating a more accurate volume of crude oil released from the pipeline.  The current 550 bbl estimate may be updated soon.

Sunoco is planning to conduct an integrity inspection of the Colmesneil pipeline in the next few days.  The goal is to hopefully determine the cause of the release last week and determine if other locations of the pipeline may be at risk of rupture.

2.2.1.1 Planned Response Activities
Sunoco will continue clean up operations in all divisions of the affected area.  OSRO contractor staffing will be maintained at 159 employees involved in field cleanup activities.  Vac truck operations will be reduced to one vac truck (instead of 3) due to the fact that access to remaining heavily oiled areas does not allow for large vehicular traffic.

2.2.1.2 Next Steps

2.2.2 Issues

Sunoco continues to arrange for access with landowners along the 6 miles of impacted creek.  Physical access to the majority of the impacted creek area is very difficult due to rolling terrain and heavy vegetation.  

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  3.1 Unified Command
We are not in unified command at this stage, however, the EPA OSC is involved in all significant cleanup decisions and is part of the sign off chain of the daily IAP.

Sunoco is using ICS and has set up an ICP at the Woodville Inn.

3.2 Cooperating Agencies

U.S. EPA

Texas Commission on Environmental Quality (TCEQ)
Texas Rail Road Commission (TRRC)
Texas Parks and Wildlife (TPWD)

Tyler County Emergency Management (TCEM)

4. Personnel On Site
  2 - START-3 Contractors for documentation and oversight of RP and cleanup progress

159 - Sunoco OSRO Contractors for field cleanup and recovery efforts

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.