U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Flat Top Mine & Griffin Ashing Site (OU1) - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VIII
|
Subject:
|
POLREP #2
Progress
Flat Top Mine & Griffin Ashing Site (OU1)
08RW
Ludlow, SD
Latitude: 45.8456780 Longitude: -103.3678530
|
To:
|
|
From:
|
Shun-Ping Chau, OSC
|
Date:
|
4/29/2013
|
Reporting Period:
|
04/25/2013 to 04/29/2013
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
08RW |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
4/24/2013 |
|
Start Date: |
4/25/2013 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
SDN000802781 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-critical removal.
1.1.2 Site Description
The Flat Top Mine Site is northeast of the town of Ludlow, Harding County, South Dakota. Uranium mining activities occurred around Ludlow in the North Cave Hills, South Cave Hills and Flint Buttes from the late 1950s to 1964 under the General Mining Laws and Public Law 357, which did not require any restoration. The North Cave Hills and South Cave Hills are part of the Custer National Forest and subsequently owned by the United States Forest Service (USFS).
Flat Top Mine is located in the Flint Buttes and is currently on private ranch land. There have been two previous studies by the South Dakota School of Mines and Technology and the Oglala Lakota College around 2006 and 2007, but no clean-up activities have been done at the Flat Top Mine.
Uranium, arsenic, vanadium and molybdenum, defined by CERCLA Section 101(14) as hazardous substances, are naturally occurring in the Flint Buttes area. Previous mining activities removed the vegetation and top soil cover in certain areas and left large piles of waste materials and open pits that collect surface water. Many of the waste material piles have been covered with vegetation, but humans, livestock and wild animals are exposed to higher than background levels of these hazardous substances found in water which collects in open pits.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Planned removal action includes treating water from the largest mine pit at the Site, returning the treated water to its original use as livestock drinking water and/or pasture irrigation, backfilling and re-vegetating the pit, and drilling wells to replace the livestock water supply.
2.1.2 Response Actions to Date
Two water wells, approimately 700 feet deep with a flow rates of approximately 10 gallons per minute, were drilled to replace livestock water supply. The wells were completed in December 2012.
During the week of March 25, 2013, EPA and ERRS contractors re-visited the Site in anticipation of a late April mobilization to complete the removal work. Because of several years of drought, the contaminated water in the pond has significantly dried up and, it appeared that there was no longer a need to treat the water.
On April 25, 2013, ERRS contractors traveled to the Site and began preparation work. The existing route from the highway to the pond area was narrow, steep and washed out in places. A wider, safer road was cut. Mid-way up the hill a support zone was set up. A water tank holding clean water, trucked in from the town of Buffalo, for dust suppression was placed at this location as well.
Since March 25, 2013, the area received some precipitation and the water level in the pond has increased slightly. Two small ponds were created to allow for the water to drain and to increase evaporation.
On April 28, 2013, EPA traveled to the Site and, on April 29, START contractors traveled to the Site.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
Baring any severe weather and equipment issues, the pond will be backfilled first with tailings, then with borrowed top soil from undisturbed areas. The entire area will be graded and re-vegetated with hydroseeding.
All activities and materials will be contained within the Site. Air-monitoring will be conducted at the perimeter to ensure no off-Site migration of contaminated dust.
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
2.2.2 Issues
A property owner across Highway 85 and two properties away expressed concerns. He did not read the public notice posted last year. He was reassured that none of the response activities should affect his property. Also, "PRIVATE PROERTY - NO TRESPASSING" signs were posted at the entrance of the property/removal Site to discourage unauthorized visitors from randomly entering the work area/hot zone.
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
No information available at this time.
|
4. Personnel On Site
|
|
No information available at this time.
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|