U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
PI&I Trucking - Removal Polrep
Initial Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V
|
Subject:
|
POLREP #1
Initial
PI&I Trucking
Gary, IN
Latitude: 41.6292315 Longitude: -87.4232886
|
To:
|
|
From:
|
Mike Beslow, OSC
|
Date:
|
9/26/2014
|
Reporting Period:
|
Through 9/26/2014
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
|
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
|
Response Authority: |
|
|
Response Type: |
|
Response Lead: |
|
|
Incident Category: |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
|
|
Start Date: |
|
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
|
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
E14543 |
|
Reimbursable Account #: |
|
1.1.1 Incident Category
1.1.2 Site Description
The Site consists of two parcels (45-03-26-326-009 and 45-03-26-326-010) totaling approximately 5.2 acres, and is owned by the Gary Airport Authority (GAA). The site is bisected by a railroad line that runs east-to-west, which will be utilized for track switching. This railroad line has been constructed as part of the Gary Airport's runway expansion project. A gravel access road is located along the south side of the railroad line. Two drainage ditches also run through the site from east-to-west, one ditch is to the north of the railroad line, and the second is to the south of the line. The ditches are a tributary to the Grand Calumet River. The southern portion of the site consits of a cleared and leveled gravel area utilized as a parking lot and staging area by surrounding businesses.
1.1.2.1 Location
The site is located to the north of Chicago Avenue and west of Airport Road / Industrial Highway in Gary, Lake County, Indiana. The site is located in an industrial area, and is bordered by a CSX railroad line to the north, vacant land and Airport Road to the east, Chicago Avenue with Gary Airport beyond to the south, and an industrial facility to the west.
1.1.2.2 Description of Threat
As part of the Gary Airport runway expansion property, GAA needed to relocate a railroad spur used for switching tracks. The Site was acquired as part of the property on which the new switching line would be constructed. The Site had historical issues with contamination, most notable as a leaking underground storage tank (LUST) site. Prior to the construction of the new railroad spur, the LUSTs were removed and contaminated soil was excavated. The railroad spur was then constructed. After the construction of the railroad line, observations of potential contamination (notable sheen in the drainage ditches and staining of soil) were reported. As a result, an attempt was made by PRP contractors to determine the nature and extent of remaining contamination through the installation of groundwater monitoring wells.
On August 27, 2014, GAA began its assessment of contamination by installing monitoring wells. The high incidence of contamination observed in the soil borings associated with the installation of these monitoring wells made it impossible to determine the geographical extent of contamination on the Site. In response, a second effort was made beginning September 24, 2014 extent of contamination on the Site through the installation of additional groundwater monitoring wells. Additional soil borings were advanced, and surface soil and surface water/sheen samples were also collected to better understand the nature, extent, and source of contamination on the site. Analytical results from this secondary effort have not yet been received.
The petroleum-related contamination present at the Site currently appears to be seeping into the drainage ditches located on the Site. The material in these ditches runs from east-to-west, and eventually exits the Site. Once leaving the Site, the drainage ditches appear to be connected to a drainage ditch which runs from north-to-south along the east side of Cline Avenue. This drainage ditch is known to enter a culvert and eventually discharge directly into the Grand Calumet River.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
On August 27 and 28, 2014, U.S. EPA and START performed oversight of the installation of twelve groundwater monitoring wells on the Site. The wells were installed in an effort to determine the nature and extent of contamination remaining on the Site. During the installation of these monitoring wells, visual and PID evidence of contamination (dark staining, elevated VOC readings) was observed in 10 of 12 soil borings. The high incidence of contamination made it impossible to determine the geographical extent of contamination on the Site.
On September 24 and 25, U.S. EPA and START performed oversight and sampling while an additional eight monitoring wells were installed on the Site. In addition, three soil borings were completed in expected areas of contamination in an to determine the nature, extent, and source of contamination on the Site. Surface soil and surface water/sheen samples were also collected from the banks of the drainage ditch and within the drainage ditch, and a groundwater/petroleum product sample was collected from an existing monitoring well to better understand the nature and source of contamination on the Site. Samples collected during this effort will be analyzed by STAT Analysis Corporation (STAT) for volatile organic compounds (VOCs), semi-volatile organic compounds (SVOCs), and total petroleum hydrocarbons (TPH), including disel-range organics (DRO), gasoline-range organics (GRO), and extended-range organics (ERO). Select samples will also be analyzed by the U.S. Coast Guard Marine Safety Laboratory for oil fingerprinting in an attempt to determine the source of contamination being released to surface soil and drainage ditches.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
A secondary investigation into the nature, extent, and source of contamination on the Site was conducted on September 24 and 25, 2014. Groundwater sampling of monitoring wells on-site is scheduled to be conducted on September 29, 2014. Analytical results of these efforts will inform future and ongoing activities.
2.1.2 Response Actions to Date
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
As property-owner, Gary Airport is the primary identified potentially responsible party.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
PRP-contractors are scheduled to perform groundwater sampling from monitoring wells on September 29, 2014.
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
2.2.2 Issues
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
No information available at this time.
|
4. Personnel On Site
|
|
U.S. EPA
START
IDEM
GAA:
AECOM
IES
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|