Atkinson Trucking

All POL/SITREP's for this site Atkinson Trucking
Kamiah, ID - EPA Region X
POLREP #2
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Atkinson Trucking - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region X

Subject: POLREP #2
Atkinson Trucking

Kamiah, ID

To: Wally Moon, EPA Region 10 (POLREP List)
Greg Buie, NPFC (POLREP List)
Rick Albright, EPA Region 10 (POLREP List)
Chris Field, EPA Region 10 (POLREP List)
Calvin Terada, EPA Region 10 (POLREP List)
Judy Goodson, Nez Perce Tribe

From: Angie Zavala, On-Scene Coordinator
Date: 8/31/2015
Reporting Period: 8/24/15 to 8/28/15

1. Introduction
  1.1 Background
   
Site Number:      Contract Number:  
D.O. Number:      Action Memo Date:  
Response Authority: OPA    Response Type: Emergency
Response Lead: PRP    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 8/7/2015    Start Date: 8/7/2015
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification: IDEQ
FPN#: E15008    Reimbursable Account #:

1.1.1 Incident Category
OPA Emergency Response

1.1.2 Site Description
Please refer to POLREP 1.


1.1.2.1 Location
Approximately Mile Post 62.5, US Route 12, Lewis County, Idaho, on the Nez Perce Indian Reservation


1.1.2.2 Description of Threat
Please refer to POLREP 1.
 

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Please refer to POLREP 1.

2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative
OSC Zavala conducting oversight at the Site.

2.1.2 Response Actions to Date

8/24/2015 to 8/25/2015

  1. EPA and RP and RP’s contractors attended the daily 0700 Site briefing and safety meeting;
  2. Traffic control is occurring 24/7;
  3. The West end of the east bound of the bypass lane was filled and compacted at a length of about25', which extended the bypass lane to help with traffic control;
  4. Traffic was then diverted into the bypass lane, and put a load of gravel on the west bound lane for the excavator PC600 to set on to minimize damage to the highway from the tracks; 
  5. The PC 600 was set on the west bond lane via lowboy truck, and unloaded it on the gravel;
  6. Excavation started at the toe of the bank; 
  7. Dust suppression was ongoing;
  8. Samples were taken from the stockpile to document the concentrations of diesel constituents in the soil disposed/recycled at the Jackson landfarm. Samples were sent to Anatek labs the following day.  

August 26, 2015 

  1. EPA, RP and RP’s contractors attended the daily 0700 Site briefing and safety meeting;
  2. Traffic control set up 24/7; flaggers during the day and portable traffic lights from 7:00pm to 7:00am
  3. The silt fence was re-anchored to the base material. Two 10 inch straw wattles were placed just up the bank from the silt fence along the entire area excavated immediate adjacent to the river;
  4. Large rocks that can be used to restore the riverbank and slope to near pre-spill conditions are being moved to the sides of the excavation area.;
  5. Two trenches were dug on the upriver side of the impacted area;
  6. Four closure samples were collected from the base of the most upriver trench. Three samples were collected from the sidewall of the upriver trench. Three closure samples were collected from the base of a second trench dug next to the first trench.
  7. Due to the slope stability concerns, the lower part of the trench was backfilled before excavating the upper area.  The areas were backfilled with 4 inch minus pit run to stabilize the slope; as backfilling, the material was compacted four times 12 to 18 inches per lift.
  8.  Bob Rees from NOAA Fisheries contacted OSC Zavala regarding her message about ESA Section 7 concerns.  He told her that endangered species (upper river salmon) migration doesn’t start until later next month.  He said that the precaution taken to prevent sedimentation going into the Clearwater river were pretty much what he would recommend.  

August 27, 2015

  1. EPA, RP and RP’s contractors attended the daily 0700 Site briefing and safety meeting;
  2. Traffic control set up 24hrs; flaggers during the day and portable traffic lights from 7:00pm to 7:00am;
  3. One trench was dug on the upriver side of the impacted area. One base confirmation sample was collected from the top area of the trench (lower base confirmation samples were collected yesterday). Due to the slope stability concerns, we backfilled the entire trench before excavating another trench. The area was backfilled with 4 inch minus pit run to stabilize the slope; the backfill material was compacted to IDT requirements;
  4. Another trench was excavated on the downstream side of the original exploratory trench. Bedrock was encountered at the toe of this trench and collected closure samples there. Excavation continued further up the slope and collected another base sample approximately 10 feet above the toe sample where bedrock was also encountered. Due to the slope stability concerns, the base of this trench was backfilled and compacted;
  5. Water to control dust was used throughout the day to minimize dust in the temporary traffic lane.

8/28/15 to 8/29/15

  1. EPA, RP and RP’s contractors attended the daily 0700 Site briefing and safety meeting;
  2. Traffic control set up 24hrs; flaggers during the day and portable traffic lights from 7:00pm to 7:00am;
  3. Water to control dust was used throughout the day to minimize dust in the temporary traffic lane;
  4. Due to several fires in the area, smoke was pretty heavy and OSC Zavala suggested to the RP contractor to have filtered facepiece respirators for the crew to use.  The contractor made the respirators available.
  5. Excavation of contaminated soil, following the same protocol as previous days, continued until reading of the FID showed less than 200 mg/kg, as the Work Plan called for.  Confirmation were taken according to the Work Plan as well.
  6. All impacted soil was excavated by the end of the day, backfilled and compacted;
  7. The road was cleaned and the excess backfill material was taken to be storage in case it was needed later;
  8. The area is ready to start the application of the gravel, compaction, and paving;
  9. A question was raised:  is it necessary to conduct more cleanup in the West bond of the road?  this matter will be discuss on the meeting arrange for Monday morning;
  10. OSC Zavala, RP, and RP contractor demobilized and are coming back on Monday to continue operations. Site meeting was held to discuss the Scope of Work for Sunday, August 30, 2015.  During that meeting, it was determined that additional work at the site could not be conducted until Monday August 31, 2015.  This was the result of the forecast of rain, the unavailability of an erosion control mat, the lack of a compaction proctor of the asphalt base coarse, and needed guidance from Idaho Transportation Department in regard to road and shoulder replacement.

2.1.3 Enforcement Activities, Identity of Responsible Parties (RPs)
Jeff Adams identified himself as the RP for Atkinson Distribution, Inc. Atkinson is the trucking company that owns the truck that went off the road.

2.1.4 Progress Metrics 

Waste Stream Medium Quantity Manifest # Treatment Disposal
 soil    560 Cubic Yards      Jacksons Landfarm
           
           


  2.2 Planning Section
    2.2.1 Anticipated Activities
Construction of the road and restoration of the river side hill.

2.2.1.1 Planned Response Activities
Monitor the deployed boom.


2.2.2 Issues
Smoke, due to the nearby fires, has been an issue since it has caused eyes irritation, headaches, nauseas, coughing, etc. to some people on the site.

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer
TETRA TECH

2.5.2 Liaison Officer

2.5.3 Information Officer

3. Participating Entities
  3.1 Unified Command
Environmental Protection Agency (EPA) 
Idaho Department of Environmental Quality (IDEQ)
Nez Perce Tribes
Responsible Party (RP)
Idaho Department of Transportation (IDT)

3.2 Cooperating Agencies
Idaho Department of Environmental Quality
Idaho Department of Transportation
Idaho Department of Lands
Idaho State Police
Lewis County Sheriff

4. Personnel On Site
  4.1 Equipment On Site
Case 500 Back Hoe
Case Bobcat
PC 600 Excavator
PC 330 Excavator
PC 200 Excavator
PC 200 mini Excavator with Vibrator
Plate for compaction
Rowland roller vibrator
3 12yard capacity dump trucks
500 Gallons water tank on a trailer w/pump

5. Definition of Terms
  Environmental Protection Agency - EPA
Idaho Department of Environmental Quality - IDEQ
Idaho Department of Transportation - IDT
Idaho Department of Lands - IDL
Idaho State Police - ISP
Lewis County Sheriff - LCS
RP - Responsible Party 