2.1.1 Narrative
EPA mobilized the Environmental Response
and Remediation Services (ERRS) contractor on 8/31/15 to begin set up of site
facilities and to initiate brush clearing, tree removal, site preparation and
excavation activities. At that time, portions
of the site contained a significant amount of vegetative overgrowth that
included heavy brush and large trees; a portion of the excavation area to the north
was mostly wooded. The RST contractor was
utilized to stake out the boundaries of the planned excavation to aid in the
identification of the large trees that required removal.
Tree removal operations were initiated on
9/2/15. An approximate total of 56 trees
have been cut down and removed from the excavation area to date and all operational
areas have been cleared of brush.
The trees and brush have been
processed in a chipper and the wood chips have been used as cover within the
operational area to aid in dust suppression.
EPA is maintaining an inventory of tree type, size and condition for all
trees being removed. The inventory will
be used to develop a plan for site restoration. EPA is making efforts to preserve trees in the shallow excavations and will use hand digging techniques as feasible to minimize the need for tree removal.
In response to community concerns, EPA
conducted a public meeting prior to initiating excavation activities. The public meeting was held on 9/9/15 at the
Lawrence Apartments, a Princeton University graduate housing apartment complex
located to the northwest of the site. Lawrence
Apartment residents expressed their concern that site activities might cause a
potential for exposure to site contaminants to Lawrence Apartment residents, a population
that includes young children. In order
to address their concerns, EPA provided an overview of the site contaminants,
planned site operations, a community air monitoring plan, and precautions to be
taken to prevent off-site migration of contaminated dust. An EPA toxicologist/risk assessor explained
the exposure risks as they relate to site action levels and answered
health-related questions posed by the residents. EPA is maintaining open communication with
the residents and Princeton University to report air sampling and monitoring
results as they become available. Princeton
University officials played a key role in assisting EPA by providing the meeting
place, assisting with logistics and communicating with the residents as needed
to coordinate the public meeting.
A site excavation and material
segregation plan based on PCB and lead content was developed using existing
site data. Highly contaminated soils are
being segregated and staged separately from low-level contaminated soils in
order to minimize disposal costs.
Site excavation activities were initiated
on 9/23/15 at the north end of the site along Lawrence Drive. Three shallow excavations have been completed
in the northern area of the site. Additionally, an area designated as potentially
containing TSCA-RCRA hazardous soil was excavated. An approximate total of 800 cubic yards of
contaminated soil have been excavated to date and placed in two separate piles.
Excavation progress was originally slowed
by technical difficulties encountered with the Global Positioning Systems (GPS)
survey equipment being used to stake out the excavation boundaries and document
the limits of the excavation. Interference from the heavy leaf foliage along
the borders of the excavation were impacting accuracy. Although the rate of excavation was originally
impacted, work activities have been managed so that site progress has not been
affected. Excavation operations have
been alternated with fence removal and tree cutting and chipping as needed to
maintain productivity. Corrective
measures have been implemented to improve the accuracy of the survey. An increase in soil excavation rates is
expected now that the technical issues have been resolved.
A Community Air Monitoring Plan (CAMP) has
been developed for this site. Continuous
real-time air monitoring for total dust particulates is being conducted on a
daily basis as per the Plan. A site action
level of 150 micrograms per cubic meter (ug/m3) has been established
as an 8 hour time-weighted average. No
exceedances have been experienced to date. Additionally, periodic air sampling is being
performed in conjunction with the continuous air monitoring. Air samples have been collected for PCB, lead
and benzo(a)pyrene analyses on 4 separate days; the first day was used to measure
background levels prior to implementing intrusive activities. Air sampling results indicate that all
contaminants were below method detection levels for all samples collected to
date.
2.1.2 Response Actions to Date
The following response actions have been implemented to date:
·
Developed a site health and safety plan, quality assurance project plan,
and community air monitoring plan.
·
Mobilized
an Emergency and Rapid Response Services (ERRS) contractor to establish support
zones, contaminant reduction zones, and exclusion zones. Initial work included marking out underground utilities and establishing excavation and
staging areas.
·
Established
engineering controls to assure proper management of excavated materials
(i.e. dust suppression, lined soil staging area, erosion and
sedimentation control).
·
Conducting air monitoring in order to monitor proper site management of excavated soil and protection of site workers and community members around the site.
·
Excavated and stockpiled approximately 800 cubic yards of contaminated soil.
·
Determined acceptable local backfill source.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
EPA is conducting PRP search activities including interviews and the preparation of 104e and notice of liability letters.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|