2.1.1 Narrative
Excavation operations continue. Approximately 2,500 cubic yards of contaminated soil have been excavated to date and have been staged on-site until analytical results were received and waste profiling could be completed. A site excavation and material segregation plan based on PCB and lead content has been developed using existing site data and is being used to excavate and segragate the soil into waste streams. Soils anticipated to be higher in contamination are being segregated and staged separately from anticipated lower-level soils in order to minimize disposal costs. Once stockpiled, excavated soils are being sampled to confirm accurate waste profiling. The majority of the soil analyzed to date for disposal (about 1500 tons) has been determined to contain PCBs in excess of 50 ppm and will be disposed of as Toxic Substances Control Act (TSCA) regulated material. Contaminated soil load-out is tentatively scheduled to begin by 11/6/15. Staged soils are being covered daily at the end of each shift to eliminate the possibility of off-site migration via wind and/or rain. TSCA soil will be transported by truck to a U.S. Ecology transfer facility in North Bergen, New Jersey. There the soil will be loaded onto rail cars and tansported to Wayne Disposal In Michigan for landfilling.
Excavation operations have been focused in the western portion of the site where the deepest cuts are required. The entire 8 foot excavation area has been completed and backfilled. The entire 7 foot excavation area has been excavated and approximately half has been backfilled with clean fill. Top soil will be brought in at a later date to complete final grades/restoration. NJDEP Certified Clean Backfill is being brought in from the Trap Rock Industries Moores Station Quarry in Hopewell Township, New Jersey. Topsoil sources are being evalauted for clean fill certification.
Bedrock was encountered between 6.5 and 7 feet BGS in the deepest (8 feet) part
of the planned excavation. An old 24" concrete sanitary sewer pipe
now being used for communication conduits was also discovered in
the excavation in the western (Lawrence Drive) portion of the site at approximately 5 feet
BGS. This pipe is owned by Princeton University and they have
requested that it not be disturbed. This area also has a bedrock high at a similar elevation in an 8'x8'
area immediately west of the pipe. The pipe and the bedrock high are sitting in the area prescribed for an 8
foot depth excavation. EPA is limiting the excavation in this approximately 8'x40' area to
six feet in depth to protect from undermining or damaging the pipe and because digging into
bedrock is not possible. NJDEP has agreed with this change in the excavation plan and has asked for one post excavation sample near the pipe in this area. This sample was collected on October 26, 2015. NJDEP also agreed that the encountering of bedrock in the excavation would represent the bottom of the dig regardless of the planned and agreed upon depth of excavation.
In the planned 7 foot part of the excavation bedrock was encountered as shallow as 5.5 feet BGS. Excavation attempts were ended in this area at between 5.5 BGS and 7 BGS depending on depth to bedrock. In this 7 foot planned excavation area strong PCB odors were encountered at the bedrock surface and in the berock surface fractures. This indicates PCBs have migrated down through the soils and into the bedrock on the site.
Tree removal operations were initiated on
9/2/15. Approxmiately 56 trees
have been cut down and removed from the excavation area to date. The trees have been
processed in a chipper and the wood chips have been used as cover within the
operational area to aid in dust suppression.
EPA is maintaining an inventory of tree type, size and condition for all
trees being removed. The inventory will
be used to develop a plan for site restoration.
EPA continues its efforts to preserve trees in the shallow excavations and is evaluating excavation techniques that might minimize the need for tree removal. A certified tree expert was retained and visited the Site on 11/2/15 to provide guidance on large native tree specimens that have been marked for preservation by the property owners. The tree expert has indicated that most of these trees may not be salvageable based on the extent of the required excavation; a report on his findings and recommendations is pending.
The EPA RST
contractor completed soil and sediment sample collection in the floodplain of Alexander Creek and in depositional areas along the stream down to the confluence with the Stoney Creek. Analytical results will be used to determine whether Site contamination has impacted the floodplain via rainwater run-off. Analytical results are expected in approximately 30 days.
A Community Air Monitoring Plan (CAMP) has
been developed for this site. Continuous
real-time air monitoring for total dust particulates is being conducted on a
daily basis as per the Plan. A site action
level of 150 micrograms per cubic meter (ug/m3) has been established
as an 8 hour time-weighted average. No
exceedances have been experienced to date. Additionally, periodic air sampling is being
performed in conjunction with the continuous air monitoring. Air samples have been collected for PCB, lead
and benzo(a)pyrene analyses to confirm real-time air monitoring results. Air sampling results indicate that all
contaminants remain below method detection levels for all samples collected to
date.
2.1.2 Response Actions to Date
The following response actions have been implemented to date:
· Developed a site health and safety plan, quality assurance project plan,
and community air monitoring plan.
· Mobilized
an Emergency and Rapid Response Services (ERRS) contractor to establish support
zones, contaminant reduction zones, and exclusion zones. Initial work included marking out underground utilities and establishing excavation and
staging areas.
· Established
engineering controls to assure proper management of excavated materials (i.e. dust suppression, lined soil staging area, erosion and
sedimentation control).
· Conducting air monitoring in order to monitor proper site management of excavated soil and protection of site workers and community members in close proximity to the site.
· Excavated and stockpiled approximately 2,500 cubic yards of contaminated soil.
· Determined acceptable local backfill sources. Backfilling of the excavation has been performed as digging progressed.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
EPA is conducting PRP search activities including interviews and the preparation of 104e and notice of liability letters.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|