2.1.1 Narrative
On September 23, 2015, verbal authorization was granted by the Region 2 Division Director to initiate a removal action at the Site. On October 6, 2015, written confirmation of the verbal authorization was submitted to the Division Director. The Removal Action activities
proposed under this verbal authorization included:
: Consolidating wastes;
: Installing security fencing and signage;
: Evaluation/Stabilization of entrance roads;
: Pre-classification of wastes;
: Preparation of work plans to remove lead-contaminated
wastes; and
: Pilot tests on passive treatment systems designed to reduce lead concentrations in surface
water discharges.
2.1.2 Response Actions to Date
-On October 14, 2015, EPA, NYSDEC, Weston Solutions and the ERRS contractor conducted a Site inspection of the proposed work areas. NYSDEC representatives included personnel from the Division of Environmental Remediation, Division of Lands and Forests and Division of Fish, Wildlife and Marine Resources.
-On October 27, 2015, a subsequent Site inspection was conducted and included ERRS mining professionals from Region 8, NYSDEC Division of Mineral Resources (Region 3), Division of Lands and Forests and Division of Environmental Remediation. During this meeting, anticipated activities were outlined and included areas of potential tree/brush clearing, soil and surface water sampling and D&H Canal sediment excavation.
-During the week of November 3, 2015, ERRS personnel and heavy equipment was delivered to the Site. Work performed focused on repairing the lower railroad access road, clearing small trees, securing the former Mill Area waste and preparing the Mill Area for delineation soil sampling work.
-During the week of November 9, 2015, ERRS and Weston personnel completed sampling activities within the former Mill Area and adjacent wetlands. The sampling event resulted in the collection of 183 soil samples and 7 surface water samples. The analytical results from this event are currently being evaluated against applicable standards. Additionally, ERRS completed the removal of sediment within the D&H Canal which protruded above the waterline. Approximately 15-cubic yards of material was generated as a result of this remediation.
From November 30 through December 16, 2015, EPA and Weston personnel collected approximately 700 soil samples from 215 grid locations within the 17-acre wetland area adjacent to the Mill Area. All samples are currently at the laboratory being analyzed.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
-Pending
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|