2.1.1 Narrative
On September 23, 2015, verbal authorization was granted by the Region 2 Division Director to initiate a removal action at the Site. On October 6, 2015, written confirmation of the verbal authorization was submitted to the Division Director. The Removal Action activities
proposed under this verbal authorization included:
: Consolidating wastes;
: Installing security fencing and signage;
: Evaluation/Stabilization of entrance roads;
: Pre-classification of wastes;
: Preparation of work plans to remove lead-contaminated
wastes; and
: Pilot tests on passive treatment systems designed to reduce lead concentrations in surface
water discharges.
2.1.2 Response Actions to Date
-Response actions which occurred prior to December 15, 2015 can be found in POLREP#1, dated January 6, 2016.
-Since December 15, 2015, response actions have included the following:
-meeting with Federal and State agencies at the Site to discuss biota sampling, historical preservation investigations, anticipated mountaintop access routes, and future activities.
-preparation of a draft work plan outlining the measures and procedures to mitigate the environmental conditions identified at the Site. These conditions include: tailings piles, access roads, canal peninsula sediment, security/bat gates, mill area wastes and mine runoff.
-On March 21-22, 2016, EPA and Weston Solutions completed delineation soil sampling along the perimeter of each of the upper mine tailings piles (Piles 1, 2 & 3). The objective of this sampling was to determine the horizontal and vertical extent of lead contamination in each of these areas. While completing the sampling, a additional area of mining operations and tailings pile was identified approximately 200-feet south of Pile 2. This pile was given the designation as Pile 5 and sampled in the same manner as Piles 1, 2 & 3. In total, this sampling event resulted in 83 samples being collected from 64 locations. The results have been received and are currently being incorporated into Site sampling maps.
-On May 16 - 18, 2016, EPA and Weston Solutions completed assessment sampling along the D&H Canal towpath and the former railroad bed located just east of the towpath. The objective of this sampling was to determine whether contaminants associated with the mill area had impacted these known public use areas. In total, this sampling event resulted in 252 samples being collected from 120 locations. All samples are currently at the laboratory being analyzed.
-On May 31, 2016, EPA and its ERRS contractor mobilized to the Site to oversee the installation of three (3) security/bat gates and to make repairs to the access roads following the winter months. On June 2, 2016, all on-site activities were completed.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
-Pending
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|