U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Princeton Recycles - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region II
|
|
Subject:
|
POLREP #5
Progress
Princeton Recycles
A25K
Princeton, NJ
|
|
To:
|
Judith Enck, Region 2
Walter Mugdan, ERRD Region 2
Joe Rotola, USEPA Region 02
Eric Mosher, USEPA , Region 2, ERRD-RPB
|
|
From:
|
David Rosoff/Cris D'Onofrio, OSC
|
|
Date:
|
6/17/2016
|
|
Reporting Period:
|
1/23/16-6/17/16
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
A25K |
|
Contract Number: |
EPS21502 |
|
D.O. Number: |
0014 |
|
Action Memo Date: |
12/23/2015 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
8/31/2015 |
|
Start Date: |
8/31/2015 |
|
Demob Date: |
5/4/2016 |
|
Completion Date: |
|
|
CERCLIS ID: |
NJR000048397 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
07/22/2015 |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Soil contamination associated with metal recycling
1.1.2 Site Description
The Site is a former paper and metal recycling business located on Basin Street in Princeton, New Jersey. The recycling business began operations in 1955 and ceased operations in 2003. Allegedly operations at the facility included draining PCB transformers and the burning of wire casings. In 2014 and 2015 NJDEP performed extensive sampling of the surface and subsurface soil on the Site and determined the extent of PCB, lead, SVOC and dioxin contamination. Levels of all of these contaminants exceed the RMLs in Site soils. PCB concentrations (mainly Aroclor 1260) were found as high as 2,800 parts per million (ppm) in surface soils. Lead concentrations were detected as high as 11,300 ppm. Benzo(a)pyrene and dioxin were detected as high as 17 ppm and 1.3 parts per billion (ppb), respectively.
The Site is located in a residential neighborhood and is directly adjacent to a tributary to the Stoney Creek. The Site property is unsecured and accessible to trespassers. The results from the NJDEP sampling indicate there has been a release of CERCLA designated hazardous substances at the Site, which is a facility under Section 101(9) of CERCLA. Based on the available information, a CERCLA removal action is warranted at the Site. An Action memorandum signed by the Region 2 ERRD Director on August 10, 2015 authorized funding for the excavation and off-site disposal of contaminated soil. An Action Memorandum authorizing a ceiling increase of $1,265,000 for a total project ceiling of $3,245,000 was signed by the Regional Administrator on 12/23/2016. This Action Memorandum also authorizes a Change in Scope to account for additional soil excavation and 12-Month and $2M Exemptions.
1.1.2.1 Location
The Site
is located at 409 Basin Street in Princeton, New Jersey (Block 11503, Lots 2
& 8). Lot 2 is 0.27 acres in size and contains a dwelling
and lot 8 is 0.37 acres in size and is undeveloped. The Site also includes
adjacent parcels that have been impacted by the spread of contamination
including 403 Basin Street (Block 11503, Lot 1), 413 Basin Street (Block 11503,
Lot 3), 417 Basin Street (Block 11503, Lot 7) and multiple Lots in Block 11301.
The Site is in a residential neighborhood bordered by lands owned by Princeton
University. Residences are located immediately to the south along Basin Street.
A Princeton University apartment complex is located within 200 feet to the west
of the Site. A tributary to Stoney Creek flows from west to east along the
north boundary of the Site.
The Site is located at 40° 19’
59.44” (latitude) / -74° 39’ 19.6” (longitude).
1.1.2.2 Description of Threat
Analytical data generated from
NJDEP soil sampling events in 2014 and 2015 found the above hazardous
substances at concentrations well above the EPA RMLs. Elevated concentrations
of these contaminants were found in surface soils (0-6 inches BGS) and down to five
feet BGS. It is estimated that approximately 7,500 tons of soil will need to be
removed from the Site to address the release of hazardous substances.
It is believed that the mechanism
for past releases on the Site include improper management of transformer waste
oils (PCBs), burning of wire and debris (dioxin and benzo(a)pyrene) and
uncontrolled storage of metallic wastes (lead). The threat of future releases
from the Site exists through the spread of soil contamination through surface
water run-off, windblown dust and/or human tracking.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Beginning
in 2014, NJDEP performed extensive soil sampling at the Site to delineate the
extent of contamination. As of June 2015, NJDEP had performed four iterative
rounds of soil sampling at the Site. Surface soil (0 – 6”) was sampled within
the main Site property in May 2014.
Forty-six samples were collected. With the exception of two samples, all
results showed elevated levels of PCBs, lead and/or benzo(a)pyrene above
NJDEP’s residential standards.
A second
round of delineation samples were collected by NJDEP in August 2014. The
original 46 sample locations were expanded to eighty-three locations; both deep
samples within the Site where contamination had been detected and surface
samples along the outer perimeter of the Site. The results indicated deeper
contamination (18’’– 24”) in some areas. There was additional horizontal
contamination above acceptable levels to the north, west and east of the main
Site property. In addition to the PCB, metals, and SVOCs analyses, the second
round included dioxin samples from where an open burn pit was thought to have
been located. Dioxin results were as high as 1.3 ppb in this area.
In
December 2014 and June 2015, a third and fourth round of samples were collected
to complete the delineation of the horizontal extent of the surface
contamination and to delineate the extent of
vertical contamination in the sample points that had not reached an
uncontaminated zone. Additional dioxin
samples were also secured.
Overall
the sample results indicate that the soil throughout the Site is contaminated
with PCBs, lead, and benzo(a)pyrene above both NJDEP residential and non-residential
standards and EPA RMLs. Dioxin is found above the NJDEP Action Level in several
“burn pit’ locations on the Site.
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
Excavation and site restoration operations were completed in the reporting
period. All of the excavation area has been excavated and backfilled with clean certified fill to
date. A total of 6,573.15
tons of non-TSCA contaminated soil was trucked to the Swedesboro NJ landfill. A
total of 5,278.29 tons of TSCA characterized soil was shipped
for disposal to the Wayne Disposal Inc. landfill in Belleville, MI.
Site
restoration activities have been completed including the planting of replacement trees and the seeding of the excavation and disturbed areas. A watering program has been put in place for the summer of 2016 to ensure the survival of the replacement trees.
2.1.2 Response Actions to Date
The following response actions have been implemented to date:
- Developed a site health and safety plan, quality assurance project plan,
and community air monitoring plan.
- Mobilized
an Emergency and Rapid Response Services (ERRS) contractor to establish support
zones, contaminant reduction zones, and exclusion zones. Initial work included marking out underground utilities and establishing excavation and
staging areas.
- Established
engineering controls to assure proper management of excavated materials (i.e. dust suppression, lined soil staging area, erosion and
sedimentation control).
- Conducting air monitoring in order to monitor proper site management of excavated soil and protection of site workers and community members in close proximity to the site.
- Excavated and stockpiled approximately 9,425 tons of contaminated soil (a TSCA pile and a ID-27 pile).
- Transported 5,278.29 tons of TSCA regulated soil to Wayne Disposal, Inc. in Belleville Michigan.
- Transported 6,573.15 tons of PCB contaminated soil characterized as non-TSCA, industrial solid waste to the Gloucester County Solid Waste Landfill in Swedesboro, NJ.
- Determined acceptable local backfill sources. Backfilling of the excavation has been performed as digging progressed.
- Completed an off-site assessment of the Alexander Creek floodplain and adjacent areas located north and northeast of the Site.
- Completed full restoration of the Site and all disturbed areas.
- Demobilized the Site on May 4, 2016
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
EPA sent a notice of liability letter to the property owner of the Site (Block 11503, Lots 2& 8) . EPA has placed a lien on these properties.
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| TSCA |
Soil |
5,278.29 tons |
|
Landfill |
Wayne Disposal Inc., Belleville, MI |
| |
|
|
|
|
|
| Non-TSCA |
Soil |
6,573.15 tons |
|
Landfill |
Gloucester Co. Landfill, Swedesboro, NJ |
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
- Continued implementation of the watering plan
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
Completion of reports documenting the work.
2.2.2 Issues
None
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
An Action Memorandum authorizing a ceiling increase of $1,265,000 for a total project ceiling of $3,245,000 was signed by the Regional Administrator on 12/23/2016. This Action Memorandum also authorizes a Change in Scope to account for additional soil excavation and 12-Month and $2M Exemptions.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$2,675,000.00 |
$2,515,415.09 |
$159,584.91 |
5.97% |
| TAT/START |
$300,000.00 |
$280,000.00 |
$20,000.00 |
6.67% |
|
Intramural Costs
|
| |
| Total Site Costs |
$2,975,000.00 |
$2,795,415.09 |
$179,584.91 |
6.04% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
No safety issues to date.
2.5.2 Liaison Officer
Pat Seppi from EPA PAD has been assiting with community outreach. Meetings have been held with the Princeton University Community and the Town officials to discuss the site activities including EPA's air monitoring.
2.5.3 Information Officer
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
3.2 Cooperating Agencies
Representatives from NJDEP visited the completed Site in May 2016 and met with the OSC. NJDEP representatives expressed satisfaction with the work completed during this site visit. EPA will be providing NJDEP with a Site completion Report in July.
|
|
4. Personnel On Site
|
|
|
None - Site Demobed May 4, 2016
prior to the demobe in the period 6 ERRs and 1 RST and 2 OSCs (split time)
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #5 Last Updated 6/17/2016
|
|
|