2.1.1 Current Activities
Week of 5/23:
- Areas C-026 and C-027 (southern portion of the Walp Trucking parking lot) were excavated and backfilled with clean fill and 2A modified stone. Confirmation samples were both less than 1 ppm PCBs. Excavated soil is being stockpiled and stored on site temporarily pending transportation off site for disposal.
- A total of 4 capacitors were found and were placed in drums with absorbent material. Drums will be stored on site in a secure area and will be inspected daily until proper disposal is arranged.
Week of 5/30
- Areas C-028 was excavated to a depth of 40 inches and C-029 was excavated to 30 inches (southern portion of the Walp Trucking parking lot). Confirmation sampling was conducted in these areas and both areas contained PCBs less than 25 ppm.
- A total of 37 large capacitors were found and were placed in drums with absorbent material.
Week of 06/06:
- Areas C-028 and C-029 were backfilled.
- Areas C-030 and C-031 were excavated to a depth of 42 inches.
- A total of 161 large capacitors were found and were placed in drums with absorbent material.
Week of 06/13:
- Continued excavating in Areas C-030 and C-031. Confirmation Samples were greater than 1 ppm and less than 25 ppm.
- Placed orange safety fence at bottom of excavation and backfilled Areas C-030 and C-031.
- Backfilled and graded areas of the both the Walp Trucking and CSI properties.
- A total of 15 large capacitors were found and were placed in drums with absorbent material.
Other Tasks Completed During Reporting Period:
- Storm/groundwater that has collected in excavations was pumped to a temporary storage tank if soil in the excavation contained greater than 1 ppm PCBs or if there was a visible sheen. START collected a water sample from the tank. The sample contained PCBs at 11 ug/L. Based on the concentrations of PCBs detected in the water, the OSC determined that water could be released to site drainage through a sediment or carbon drum filter. Site drainage does not flow to a stream or river but instead sheet flows in the wooded lot adjacent to the site where it evaporates and/or percolates into the ground. The middle portion of the water column in the tank will be discharged to site drainage through a filter bag. Water sitting on bottom and top of the tank will be discharged through a carbon filter drum to ensure any oily sheen at the top of the tank or heavy sediment at the bottom of the tank are captured.
- START conducted daily air monitoring for particulates. No action levels were exceeded.
- To date, at total of approximately 419 large capacitors and 3 small transformers have been recovered from subsurface/surface of the site.
|