|
2.1.1 Narrative
AMS
has indicated they do not have the financial means to implement the remainder
of the decommissioning plans. Because of this fact, OBEHRP has referred this site
to Region 5 for assessment and possible cleanup. EPA assessed the property in the fall of 2015 and is evaluating the data generated.
OBEHRP and EPA contacted the Site owner and they indicated that they do not have the means to restore power to the property.
2.1.2 Response Actions to Date
On June 18th EPA provided personnel to pump any accumulated water to the frac tank. no inclement weather was in the forecast so EPA provided security guards beginning in the evening of June 18th through June 19th.
On June 20th, EPA and OBEHRP returned to the site. No groundwater accumulated in the sump over the weekend. EPA and ERRS developed a plan to further secure entry points into the building and Electricians were hired to begin restoring necessary power on June 21st. EPA provided site security in the evening hours.
On June 21st, EPA and OBEHRP returned to the site. The security guard reported smelling gas outside the building intermittently and when one room of the building was opened, OBEHRP reported that it smelled like natural gas. EPA investigated and did not detect any gas odors; however as a precaution, the gas lines were shut off to the building as there is no need for natural gas to be running to the building. Electricians were on site developing plans for the necessary work. Approximately 500 gallons of water was pumped from the outside sump due to overnight rain storm. OBEHRP personel provided escorts throughout the building as necessary. EPA provided site security in the overnight hours.
From June 22nd through June 24th, EPA and OBEHRP were on site. OBEHRP were providing escorts throughout the building to workers as required by radiological guidelines. ERRS contractors began installing steel bars across all accessible windows to help prevent trespassing. Contracted electricians were on site and began installation of a new electrical panel. ERRS pumped water into the temporary storage tank as necessary. Inclement weather was predicted for the overnight hours on June 23rd and ERRS was on site overnight to manage water if necessary. Security guards were on site during off-shift hours.
No activities occurred on site on June 25th and June 26th. Twenty-four hour security guards were present (weekend).
On June 28th, EPA and OBEHRP were on Site. OBEHRP were providing escorts throughout the building to workers as required by radiological guidelines. ERRS completed installing steel bars across accessible windows. Electricians completed the installation of all necessary components and received the final completed inspection report to have power restored. Security guards were on site during off-shift hours.
On June 29th, EPA and OBEHRP were on Site. OBEHRP were providing escorts throughout the building to workers as required by radiological guidelines. Cleveland Public Power was on site and restored power to the new panel installed by the electricians. The entire water management system was tested and all components were in working order (pumps, composite sampler, etc). A path of lights was also installed by the electrician and was operable. OBEHRP had received analytical data for the water contained in temporary storage and it met direct discharge limits; therefore, that water was used to test the water management system. The front door lock was changed to limit the number of keys to the facility. Security guards were on site during off-shift hours.
On June 30th, EPA and OBEHRP were on Site. OBEHRP were providing escorts throughout the building to workers as required by radiological guidelines. The temporary storage tank had drained overnight into the sump for the water management system and the system worked as intended (pumped water through the system, pumps cycled on/off, etc). Electricians were on site to complete final work. A generator back-up system was tested and all components of the water management system can be operated by one generator if the building loses power. ERRS pressure washed the temporary storage tank for return. EPA and all contractors demobilized from site. Off-shift security was discontinued.
**UPDATED INFORMATION**
On July 7, 2016, OBEHRP reported additional vandalism at the AMS Site. Thieves cut the power to the building again and broke in through one of the bay (roll up) doors. Power was able to be restored to the pumping system.
Additional requests were received from OBEHRP to increase security at the site and EPA performed the following actions:
1) Repaired entrance gate to the facility on July 13th, 2016
2) Installed six solar powered motion detector lights around the building on July 14th, 2016
3) Cleared brush from around the building and welded external doors (leaving two exits) shut and further secured a window discovered after the brush clearing on July 18th, 2016.
OBEHRP arranged for the bay (roll up) doors to be secured by installing a cinderblock wall in the opening.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The PRP has been notified of the situation and was given a verbal order by EPA. The PRP indicated that they do not have the means to perform the necessary work to resume the normal pumping operations. OBEHRP also contacted the PRP and ordered them to restore power to the facility and they refused. Due to the resignation of the site's RSO, OBEHRP also ordered the PRP to provide a new RSO for the site as required under the radiological license.
2.1.4 Progress Metrics
| Regional Metrics |
| This is an Integrated River Assessment. The numbers should
overlap. |
Miles
of river systems cleaned and/or restored |
N/A |
| Cubic yards of contaminated sediments removed
and/or capped |
N/A |
| Gallons of oil/water recovered |
N/A |
| Acres of soil/sediment cleaned up in
floodplains and riverbanks |
N/A |
| Stand Alone Assessment |
Number
of contaminated residential yards cleaned up |
N/A |
| Number of workers on site |
4 |
| Contaminant(s)
of Concern |
Cobalt-60 |
| Oil
Response Tracking |
| Estimated volume |
Initial
amount released |
N/A |
| Final amount collected |
N/A |
| CANAPS Info |
FPN
Ceiling Amount |
N/A |
| FPN Number |
N/A |
| Body of Water affected |
N/A |
| Administrative
and Logistical Factors (Place X where applicable) |
| |
Precedent-Setting HQ
Consultations (e.g., fracking, asbestos) |
|
Community
challenges or high involvement |
X |
Radiological |
| |
More than one
PRP |
|
Endangered
Species Act / Essential Fish Habitat issues |
|
Explosives |
| |
AOC |
|
Historic
preservation issues |
|
Residential
impacts |
| |
UAO |
|
NPL
site |
|
Relocation |
| |
DOJ involved |
|
Remote
location |
|
Drinking
water impacted |
| |
Criminal
Charges Have Been Filed* |
|
Extreme
weather or abnormal field season |
|
Environmental
justice |
| |
Tribal
consultation or coordination or other issues |
X |
Congressional
involvement |
|
High
media interest |
| |
Statutory
Exemption for $2 Million |
|
Statutory
Exemption for 1 Year |
|
Active
fire present |
| |
Hazmat
Entry Conducted – Level A, B or C |
|
Incident
or Unified Command established |
|
Actual
air release (not threatened) |
| Green
Metrics |
| Metric |
Amount |
Units |
| Diesel Fuel Used |
N/A |
gallons |
| Unleaded Fuel Used |
N/A |
gallons |
| Alternative/E-85 Fuel Used |
N/A |
gallons |
| Electricity from
electric company |
|
N/A |
kWh |
| Electric Company Name and Account # |
N/A |
|
| Electricity from sources other than the electric company |
N/A |
kWh |
| Solid waste reused |
N/A |
|
| Solid waste recycled |
N/A |
|
| Water Used |
|
N/A |
gallons |
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|