2.1.1 Narrative
2.1.2 Response Actions to Date
Upon discovery of the oil spill on April 19, 2016, the RP hired
a local oil spill response contractor, Apache Oilfield Services, Inc. to
initiate containment and removal actions.
An underflow dam was constructed within Turkey Creek, at approximately 32.36272°,
-94.88089°. Oil was contained and
recovery efforts the first day resulted in approximately 6 bbls or crude oil
recovered. TX Railroad Commission
responded to reports of the discharge and monitored the clean-up.
As a result of heavy rains the night of April 19 and the
morning of April 20, 2016, the underflow dam was breached. Response contractors were on site at the time
and traveled downstream to get in front of the oil. Hard booms and sorbent booms were placed approximately
two miles downstream of the underflow dam breach to create a new containment
point, located at 32.39285, -94.84812. Due
to the impacted segments of Creek flowing through residential areas of Kilgore,
EPA mobilized its Superfund Technical Assessment and Response Team (START) contractor
to the incident to observe the oil spill response activities and assess the
actual or potential threat of the oil discharge.
START arrived in Kilgore, TX at approximately 1350 on April
21, 2016, and met with representatives of the RP and Terry Howard, Manager for
the Kilgore City Water Treatment. During
the assessment of the tank battery (spill site), no oil was observed actively leaking
and no visible oil was observed on the ground. Contractors had already
excavated visible impacted soil. An
assessment of the spill pathway from the spill origin to the location of the underflow
dam was conducted. No visible oil was
observed on the soil and no free oil was observed in the creek. Spill response personnel were removing the remaining
oil impacted debris and coordinating efforts to remove the remaining underflow
dam.
At the final downstream containment area, two sets of hard
booms, with sorbent booms, and absorbent peat moss were deployed to contain and
recover remaining oil and emulsion. Spill
response personnel were onsite removing remaining oil impacted debris. Although,
no impact to wildlife was observed, EPA contacted Texas Parks and Wildlife and
US DOI, to make them aware of possible natural resource damages.
5/23/2016 - The RP maintained containment and sorbent boom in the creek for several weeks to catch any remaining sheen. On 5/23/2016, the RP notified the OSC that there were no further areas of oil impact to address and requested concurrence to be complete. Based on the information provided the OSC concurred.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Breitburn Operating, L.P. (Operator 090732) as the operator
of the J.S. Bean “A” Facility (API 40185550), and is the responsible party of
this incident. A Notice of Federal
Interest (NOFI) was sent to the RP on April 21, 2016.
2.1.4 Progress Metrics
In total, approximately 7 bbl of crude oil and
approximately 10 cubic yards (yd3) of sorbents and oil impacted debris were recovered. The oil impacted debris was transported and disposed at
the Republic Service Landfill in Itasca, TX.
|