2.1.1 Narrative
Following the inspections noted in the previous section, HHCU sent a letter to the property owner and the demolition contractor on November 4, 2015, explaining the regulatory requirements associated with demolition of potentially asbestos-containing structures. An HHCU Notice of Violation (NOV) was sent to the property owner and demolition contractor on March 2, 2016. The NOV directed that a thorough inspection and inventory of suspect asbestos-containing materials be performed by an accredited asbestos inspector and that an asbestos abatement design be developed and submitted for review prior to beginning cleanup or demolition activities. The NOV further specified that the cleanup should be performed by North Carolina accredited personnel in accordance with applicable state and federal regulations and completed as quickly as possible.
On June 6, 2016, the North Carolina Department of Environmental Quality (DEQ) in coordination with the HHCU requested via email that the EPA Region 4 Emergency Response, Removal and Prevention Branch (ERRPB) conduct a Removal Site Evaluation at the Site and take action as necessary and appropriate to facilitate mitigation of potential threats associated with asbestos-containing demolition debris located on the property. Also on June 6, 2016, the HHCU sent a letter to ERRPB expressing their concern with the Site. Region 4 EPA mobilized contractor support from Emergency Rapid Response Service (ERRS) contractor, Environmental Restoration, LLC, and Superfund Technical Assessment and Response Team (START) contractor, Tetra Tech, Incorporated to assess and stabilize the site property.
The week of July 11, 2016 EPA and contractor support transitioned from site stabilization to ACM debris removal operations.
2.1.2 Response Actions to Date
June 6 – 11, 2016 - Perimeter Air Sampling -
Access Authorizations were received from neighboring properties (Mitchell
Community College and Housing Authority Apartments) to enhance sampling
locations. Perimeter Air Sampling Continued until June 11, when wetting
operations began. All perimeter air sampling results have been non-detect for
asbestos fibers. Sampling results are attached in the documents section. Wetting
operations continued prior to removal operations based on visual observations
and weather forecasts.
June 13 – July 3, 2016 - Contractor has been
acquired, security is present at the Site from 7 pm to 7 am daily and 24 hours
a day on weekends. This schedule was subject to change based on EPA and EPA
contractor site presence and completion of security fencing.
June 20 – 29, 2016 - Installation of a perimeter
fence line consisting of 6-ft tall chain-link with three-tier barbed wire, and
approximately 2,500 feet in length was installed.
July 5 – 12, 2016 – Emergency Rapid Response Service
(ERRS) contractor (Environmental Restoration, LLC) mobilized equipment, office
trailer and personnel to the Site.
July 13 – 15, 2016 – ERRS and two subcontracted
transport services (Thomas Transport and Southern Logistics) initiated removal operations on the
eastern side of the Site that accesses Cherry Street. Throughout the work hours
at the Site, the Superfund Technical Assessment and Response Team (START)
maintained air quality surveillance along the perimeter fence line as well as
monitoring personnel within the work zone.
During
this period, 24 shipments totaling 602.8 tons were shipped off site for
disposal.
July
14, 2016 -
The North Carolina Department of Health and Human Services (DHHS), Division of
Public Health (DPH), Health Hazards Control Unit (HHCU), which is the State
agency that implements the asbestos program in North Carolina visited the Site
to observe removal operations.
July
18 – 22, 2016
- ERRS and subcontracted transport services continue removal operations on the
eastern side of the Site accessible by West End Avenue. START continued to maintain air quality
surveillance along the perimeter fence line as well as monitoring personnel
within the work zone.
During
this period, 68 shipments totaling 1,743.35 tons were shipped off site for
disposal.
July
25 – 27, 2016
- ERRS and subcontracted transport services continue removal operations on the
eastern side of the Site accessible by West End Avenue. Operations transitioned
to the southwest area of the Site accessed by Cherry Street in the afternoon on
July 26th. START continued to maintain air quality surveillance
along the perimeter fence line as well as monitoring personnel within the work
zone.
During
this period, 43 shipments totaling 1154.50 tons were shipped off site for
disposal.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Negotiations between Regional Counsel and the PRP continue.
Efforts to identify additional PRPs continue.
Property Owner has signed Access Agreement.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
NA 2212,
Asbestos,9,
PG III,RQ
|
ACM Demolition Debris |
3500.65 Tons |
Numbered Sequence: 1 - 135 |
Double Poly Wrap |
Anson County LF & Charlotte Motor Speedway LF |
|
|
|
|
|
|
|
|
|
|
|
|
|