U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V
|
|
Subject:
|
POLREP #2
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333
|
|
To:
|
Douglas Ballotti, EPA
Thomas Short, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Dan Peabody, MDEGLE
Polly Synk, MDAG
Randy Rapp, Allegan County Health Dept
Dan Wedge, Allegan County
Cyndi Trobeck, City of Otsego
Bryan Winn, Otsego Township
Lisa Williams, U.S. FWS
Valincia Darby, U.S. DOI
Greg Baker, NOAA
|
|
From:
|
Paul Ruesch, OSC
|
|
Date:
|
8/31/2016
|
|
Reporting Period:
|
8/16/2016 - 8/31/2016
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
059B |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
4/6/2016 |
|
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
|
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
|
NPL Status: |
NPL |
|
Operable Unit: |
5 |
|
Mobilization Date: |
8/1/2016 |
|
Start Date: |
8/1/2016 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
MID006007306 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
DEQ |
|
FPN#: |
|
|
Reimbursable Account #: |
059B |
1.1.1 Incident Category
Time Critical Removal Action - PRP Oversight
1.1.2 Site Description
See PolRep #1
1.1.2.1 Location
See PolRep #1
1.1.2.2 Description of Threat
See PolRep #1
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See PolRep #1
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
Contractors continued preparations for contaminated sediment and riverbank soil excavation activities, which are expected to start in mid-September. The contaminated sediment staging area was completed and the waste water treatment plant was constructed at the BRSA 1 forward staging area.
2.1.2 Response Actions to Date
The following activities took place during the reporting period:
- Construction of contaminated sediment staging pad in BRSA 1;
- Mobilization and construction of waste water treatment plant in BRSA 1;
- Mobilization and testing of particulate (dust) monitoring system for BRSA 1;
- Commencement of survey/re-location of state-listed endangered mussels in BRSA 1 - 3 target excavation areas to a relocation area
upstream of the M-89 Bridge & Otsego City Water Treatment Plant;
- Bathymetric/hydrographic/overbank surveying
activities;
- Invasive species control (spraying) in BRSA 1 & BRSA 3; and
- Closure of the Kalamazoo River channel from the M-89 bridge to the Otsego Township Dam using buoys and land-based signage.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See PolRep #1
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
| Water bottles |
Plastic |
30 lbs |
NA |
recycling |
local drop-off |
| OCC |
Cardboard |
100 lbs |
NA |
recycling |
local drop-off |
| Steel |
Metal |
10 lbs |
NA |
recycling |
Shupan Recycling |
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:
- Complete construction of BRSA 1 staging area, including the contaminated sediments staging area, testing of waste water treatment plant, support areas, and riverbank access roads;
- Mobilize equipment, supplies and materials necessary to begin excavation of contaminated sediments and riverbank soils;
- Install water management structures necessary to de-water areas where excavation activities will take place in BRSA 1; and
- Complete mussel survey/relocation activities.
2.2.1.1 Planned Response Activities
See Section 2.2.1
2.2.1.2 Next Steps
See Section 2.2.1
2.2.2 Issues
US EPA received concurrence from the US FWS on a ‘not likely to adversely effect” determination for the federally endangered Northern Long Eared Bat and Indiana Bat on August 22.
|
|
|
2.3 Logistics Section
|
|
|
|
The project command center is located at 2063 Covault Lane. A forward staging area to support activities in BRSA 1 is located on Jefferson Road just east of the Pine Creek Dam. A staging area for equipment and materials is located at 602 Lincoln Road.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
See PolRep #1
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| START |
$265,000.00 |
$198,000.00 |
$67,000.00 |
25.28% |
|
Intramural Costs
|
| USEPA - Direct |
$50,000.00 |
$15,000.00 |
$35,000.00 |
70.00% |
| USEPA - InDirect |
$12,000.00 |
$5,000.00 |
$7,000.00 |
58.33% |
| |
| Total Site Costs |
$327,000.00 |
$218,000.00 |
$109,000.00 |
33.33% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
See POLREP #1
2.5.2 Liaison Officer
A public meeting was held for residents on August 23 at the Otsego Public Library. Approximately 40 residents attended the meeting along with another 20 contractors, consultants, and local officials. An update was provided on the project along with other cleanup projects within the overall Allied Paper, Inc./Portage Creek/Kalamazoo River Superfund Site. Questions were answered by representatives from US EPA, Michigan DEQ and Michigan DNR. The presentations from the meeting are posted in the 'Documents' section of the website.
Several inquiries from local residents on river access & closure, construction equipment noise and roadway impacts were responded to by the OSC.
All project work plans (latest drafts), which were approved by US EPA on August 26, have been posted to the 'Documents' section of the website.
2.5.3 Information Officer
A public website was established at the following address: www.epa.gov/superfund/allied-paper-kalamazoo.
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
N/A
3.2 Cooperating Agencies
See PolRep #1
|
|
4. Personnel On Site
|
|
|
On average, the following personnel were present on site during the reporting period:
US EPA - 1
START (US EPA contractor) - 1
Envirocon (general contractor): 12
AMEC-FW (project consultant): 2
Spicer Group (surveyors): 2
Environmental Solutions & Innovations, Inc. (mussel survey/relocation sub-contractor): 2
TOTAL: 20
|
|
5. Definition of Terms
|
|
|
GC General Contractor
AMEC-FW AMEC Foster Wheeler
BRSA Bank Removal and Stabilization Area
Michigan DEQ Michigan Department of Environmental Quality
Michigan DNR Michigan Department of Natural Resources
OSC On Scene Coordinator
PolRep Pollution Report
PRP Potentially Responsible Party
US EPA United States Environmental Protection Agency
US FWS United States Fish & Wildlife Service
|
|
6. Additional sources of information
|
|
|
6.1 Internet location of additional information/report
http://www.epaosc.org/otsegodam
www.epa.gov/superfund/allied-paper-kalamazoo
6.2 Reporting Schedule
PolReps will be generated every two weeks during active field activities.
|
|
7. Situational Reference Materials
|
|
|
None at this time
|
|
POLREP #2 Last Updated 9/13/2016
|
|
|