U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
ED-Coat - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IX
|
|
Subject:
|
POLREP #8
ED-Coat
A999
Oakland, CA
Latitude: 37.7998008 Longitude: -122.2819851
|
|
To:
|
Peter Guria, EPA Region 9
Lynn Keller, EPA Region 9
Jason Musante, EPA Region 9
|
|
From:
|
Olivia Trombadore, On-Scene Coordinator
|
|
Date:
|
10/23/2021
|
|
Reporting Period:
|
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
A999 |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
8/17/2021 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
8/31/2021 |
|
Start Date: |
8/31/2021 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
|
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
|
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
EPA-lead removal action at a defunct electroplating facility.
1.1.2 Site Description
The site is a large, defunct plating shop, which was shut down by the East Bay Municipal Utility District in 2012, when the utility revoked ED-Coat's permit to discharge wastewater from their operations. The facility has been idle since that time. In the interim, plating tanks full of corrosive solutions have degraded and many of them are now in very poor condition, presenting the threat of a release of toxic, corrosive liquids.
1.1.2.1 Location
715 4th St, Oakland, CA 94607
1.1.2.2 Description of Threat
Large plating tanks in very poor condition present the threat of a release of toxic, corrosive liquids.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
EPA and the California Department of Toxic Substances Control (DTSC) have conducted several sampling operations at the facility over the last few years. This sampling has confirmed the presence of thousands of gallons of corrosive liquids, both acids and bases, many of them with high concentrations of toxic metals. These liquids are stored in badly corroded steel tanks of various sizes. On many of the tanks there are also extensive deposits of corrosive sodium hydroxide crystals, and some of the tanks show evidence of past leaks of contents, including hydroxide crystals on the floor or on adjacent piping.
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
EPA mobilized to the site on August 31, 2021 to begin removal operations.
2.1.2 Response Actions to Date
During the week of October 18, 2021, ERRS contractors removed and cut tanks the final tanks, with work this week primarily being done on the F plating line. Today, all tanks on site have now had their contents removed and been cut up. Final RCRA Debris on site is staged for packaging and transport to the disposal facility. Additionally, all small containers have been lab packed or bulked and are staged for transport and disposal. This week ERRS shipped approximately 160 CY of RCRA debris and 4,200 gallons of RCRA Wastewaters (sludge). START continued air monitoring and sampling throughout the week and will demobilize from the site next week once all waste is containerized.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
ED-Coat and the various members of the Rossi family, as owners of the property and former operators of the facility, are the only identified PRPs at the Site.
2.1.4 Progress Metrics
Waste sent out for disposal from the E-D Coat Site:
CY = cubic yards
gal = gallons
| Waste Stream |
Container Type |
Disposal Quantity |
Units |
| RCRA Debris |
Roll Off Bin |
959 |
CY |
| Acid Solids |
CY Box |
4 |
CY |
| Alkaline Solids |
CY Box |
106 |
CY |
| Asbestos |
CY Box |
1 |
CY |
| RCRA Wastewater |
Tanker Truck |
19,200 |
gal |
| Non-RCRA Wastewater |
Tanker Truck |
25,624 |
gal |
| Inorganic Acid |
Tanker Truck |
7,324 |
gal |
| Inorganic Alkaline |
Tanker Truck |
3,254 |
gal |
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
Continue removal activities as described below.
2.2.1.1 Planned Response Activities
Transport the remainder of staged waste offsite for disposal. Pump out sumps the refilled due to rain events.
2.2.1.2 Next Steps
Transport waste off site for disposal
2.2.2 Issues
No new issues identified.
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
See budget table.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup Contractor |
$1,950,000.00 |
$1,697,211.79 |
$252,788.21 |
12.96% |
|
Intramural Costs
|
| USEPA - Direct |
$80,000.00 |
$40,000.00 |
$40,000.00 |
50.00% |
| |
| Total Site Costs |
$2,030,000.00 |
$1,737,211.79 |
$292,788.21 |
14.42% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
No information available at this time.
|
|
3. Participating Entities
|
|
|
No information available at this time.
|
|
4. Personnel On Site
|
|
|
EPA OSC - 1
START - 1
ERRS - 10
|
|
5. Definition of Terms
|
|
|
No information available at this time.
|
|
6. Additional sources of information
|
|
|
No information available at this time.
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #8 Last Updated 3/6/2023
|
|
|